MahaRERA Application

General Information

Other Than Individual

Organization

Sheth Developers Private Limited
Company
NA
Do you have any Past Experience ?
Yes

Address Details

Gr and 3rd Floor
Prius Infinity
Subhash Road
Vileparle (East)
Paranjpe B Scheme
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
400057

Organization Contact Details

02242933400

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1BEAUMONDEResidentialNA40792.26APPASAHEB MARATHE MARG PRABHADEVI MUMBAI 25CTS/TPS - IV 1090 AND 1092 MAHIM DIVISION31962011-07-312012-01-10
2VASANT GALAXYResidentialNA60714JUNCTION OF MG ROAD AND LINK ROAD BANGUR NAGAR GOREGAON WEST MUMBAI236/1 TO 3237/1,238,238/1 AND 239108032010-10-312011-03-30
3VASANT GARDENResidentialNA115000SWAPNA NAGARI OFF LBS MARG MULUND WEST MUMBAI 80CTS 29, 32 P, 618718252007-03-312007-12-01
4VASANT MARVELResidentialNA29655.85WESTRN EXPRESS HIGHWAY BORIWALI EAST MUMBAI - 66CTS NO 167-C 76412011-10-312012-07-12
5VASANT VALLEYResidentialNA68373.2MALAD EAST MUMBAI 96CTS 104 A TO J11272010-06-302010-12-09
6SIGMACommercialNA9463.25ZANDU PHARMACTICAL GOKHALE ROAD SOUTH DADAR W MUMBAI - 251148/1/1149,1302,1153,1147 AND 115422602014-07-302014-12-15
7CNERGYCommercialNA8905.7APPASAHEB MARATHE MARG PRABHADEVI MUMBAI 25FP NO 1090 AND 1092 OF TPS IV OF MAHIM DIVISION1332011-09-082011-09-08
8Vasant LawnsResidentialNA35796.75Vasant Lawns Voltas Compound Pokharan Rd No 2 Majiwade Thane w 400601S NO 35/4,5,8,9P,10P,11,51/4P,52/1P,2,53,70/2,3,9P,10P,11,13,71/1P,3P,4,5,72/1P,4P,6,7P,8P,1064652012-03-312013-11-12
9VIVIANA MALLCommercialNA49797.78Viviana Mall Voltas Compound Pokharan Rd No 2 Majiwade Thane w 400601S NO 48/1 TO 4 48/1P ,2, 3 4P 7P 49/1 TO 5, 73/1 TO 4,6, 74P,77/1 TO 4P, 5P, 78/1,2,3,81/1 AND 526P12402013-05-092013-05-09

Member Information

Member Name Designation Photo
Ashwin Natwarlal Sheth Authorized Signatory View Photo

Project

SHETH AVALON - PHASE 2
New Project
30/12/2025
No
Residential
No
OUT OF SURVEY NO48/1P,2,3,4,5P, 49/2P,4,73/1,2,3,4,5,6,74P,526P
15 MTR WIDE SERVICE ROAD
SHETH AVALON - PHASE 1
TMC PARKING PLAZA
SHETH AVALON - PHASE 1
MAHARASHTRA
Konkan
Thane
Thane
Thane (M Corp.)
W E HIGHWAY POKKHARAN RD NO 2
MAJIWADA
400601
6147.04
3
3
0
1272.34

FSI Details

6214.18
39691.6
45905.78

Bank Details

HDFC BANK LIMITED
HDFC0000212

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 506 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 SHALL BE DONE PRIOR TO OC OF LAST BLDG IN LAYOUT
Energy management : YES 0 SOLAR WATER HEATING
Fire Protection And Fire Safety Requirements : YES 0 AS PER CFO NOC
Electrical Meter Room, Sub-Station, Receiving Station : YES 35 SUBSTATION
GYMNASIUM SWIMMING POOL CLUB HOUSE AND OTHER RECREATION FACILITIES : YES 0 SHALL BE DONE PRIOR TO OC OF LAST BLDG IN LAYOUT
Aggregate area of recreational Open Space : YES 0 SHALL BE DONE PRIOR TO OC OF LAST BLDG IN LAYOUT
Open Parking : NO 0 NA
Water Supply : YES 0 AS PER TMC WATER SUPPLY
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 50 PROVISION OF STP
Storm Water Drains : YES 40 SHALL BE DONE PRIOR TO OC
Landscaping & Tree Planting : YES 0 SHALL BE DONE PRIOR TO OC OF LAST BLDG IN LAYOUT
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 PROVISION OF STP
Solid Waste Management And Disposal : YES 50 -

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 SHETH AVALON - PHASE 2 TOWER A 31/12/2024 1 1 4 44 1 0 206
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop 112.65 1 1
2 Shop 186.8 1 1
3 Shop 192.95 1 1
4 Shop 205.36 1 1
5 Shop 227.18 1 1
6 2BHK 94.35 9 0
7 4BHK 155.59 44 12
8 3BHK 122.87 35 12
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 25
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 22.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 SHETH AVALON - PHASE 2 TOWER B 31/12/2024 0 1 4 44 1 0 200
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop 112.65 1 1
2 Shop 164.24 1 1
3 Shop 184.5 1 1
4 Shop 205.22 1 1
5 4BHK 155.48 44 14
6 2BHK 96.43 9 1
7 3BHK 123.85 35 13
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 40
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 SHETH AVALON - PHASE 2 TOWER C 31/12/2024 0 1 4 28 1 0 100
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 165.89 6 0
2 4BHK 187.55 22 16
3 5BHK & more 229.45 28 6
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 28
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 42.8

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
JM Financial Products Limited A51900000277 Real Estate Agent
Gokani Consultants and Engineers LLP NA Engineer
ANIL JAGWANI NA Architect
ESKAYEM CONSULTANTS PRIVATE LIMITED NA Other Professional
BLUE LOTUS A51700003670 Real Estate Agent
Nitin Ajabrao Sonawane A51700003026 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
3 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
8 Architect’s Certificate of Percentage of Completion of Work (Form 1)
9 Architect’s Certificate of Percentage of Completion of Work (Form 1)
10 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
7 Engineer’s Certificate on Cost Incurred on Project (Form 2)
8 Engineer’s Certificate on Cost Incurred on Project (Form 2)
9 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
4 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
5 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
3 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
4 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 CERSAI details
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
5 Disclosure of sold/ booked inventory
6 Disclosure of sold/ booked inventory
7 Disclosure of sold/ booked inventory
8 Disclosure of sold/ booked inventory
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
2 Certificates of CA (Form 5)
3 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement