MahaRERA Application

General Information

Other Than Individual

Organization

SUDARSAN DEVELOPERS
Partnership
NA
Do you have any Past Experience ?
No

Address Details

A-3, GROUND FLOOR
CHANDAN APARTMENT
S. V. ROAD,
VILE PARLE WEST
NEAR GOLDEN TOBACCO CO.
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
400056

Organization Contact Details

02228633785

Past Experience Details

Member Information

Member Name Designation Photo
DIMPLE AMRUTLAL BHAVSAR Partner View Photo
SANTOSH KRISHNA KAMBLE Partner View Photo
PRATIK JAYANTI SANGOI Partner View Photo
RAVINDRA BALASAHEB GAIKWAD Partner View Photo

Project

NEW AJAY VILLA
New Project
30/06/2023
No
Residential
No
1153 1153 1 4
SAROJINI ROAD
PART 4 1 AND PART PLOT NO 5
PART PLOT NO 3 AND PLOT NO 4
PART PLOT NO 8 AND PLOT NO 7 1
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
SAROJINI ROAD
VILE PARLE WEST
400056
565.10
1
1
0
0

FSI Details

1525.77
0
1525.77

Bank Details

ICICI BANK
ICIC0006415

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 22 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 AS PER DESIGN OF CONSULTANT
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 0 AS PER CFO NOC ISSUED
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 AS PER ELECTRICITY SUPPLIER REQUIREMENT
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : YES 0 AS PER APPROVED PLAN
Water Supply : YES 0 AS PER MCGM NORMS
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 AS PER CONSULTANTS REPORT
Storm Water Drains : YES 0 AS PER CONSULTANTS REPORT
Landscaping & Tree Planting : NO 0 NA
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : YES 0 AS PER CONSULTANTS REPORT

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 NEW AJAY VILLA NEW AJAY VILLA 31/12/2022 0 1 0 10 1 4 22
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 91.51 1 1
2 3BHK 95.13 1 1
3 3BHK 83.33 1 1
4 2BHK 57.04 1 0
5 2BHK 71.35 2 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SANJAY B SHAH NA Architect
NITIN SHIVAJI GAIKWAD NA Engineer
VEER RAVINDRA SAKARIYA NA Chartered Accountant
Bhavin Ramiyani NA Other Professional

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
4 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
3 Other
4 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement