MahaRERA Application

General Information

Other Than Individual

Organization

Paradise Lifespaces LLP
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

1701
SATRA PLAZA
PALM BEACH ROAD
PLOT NO 19 & 20
APMC POLICE STATION
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
400703

Organization Contact Details

02227849000
WWW.PARADISEGROUP.CO.IN

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1SAI MOKSHResidentialNA2410.68sector 15 kharghar navi mumbai481732015-08-122015-06-19
2SAI GANGAResidentialNA1949SECTOR 5 ULWE21622017-05-152017-01-11
3SAI FORTUNEResidentialNA2349SECTOR 8 ULWE151992016-12-012016-11-21
4SAI SAHILResidentialNA1449SECTOR 5 ULWE NAVI MUMBAI6A1502017-05-012017-04-28
5SAI HARMONYResidentialNA2650SECTOR 21 ULWE9911152016-07-312016-07-15
6SAI SAPPHIREResidentialNA4000SECTOR 20 ULWE NAVI MUMBAI178,18011622015-07-312015-07-02
7SAI SPRINGResidentialNA5000SECTOR 35G KHARGHAR NAVI MUMBAI5,5A11482016-08-012016-07-21
8SAI MIRACLEResidentialNA4900SECTOR 35E16,17,1911102016-08-012016-07-22
9SAI CRYSTALResidentialNA6049SECTOR 35D KHARGHAR NAVI MUMBAI45,52,52A11662016-10-012016-09-30
10SAI WONDERResidentialNA2200SECTOR 35F KHARGHAR NAVI MUMBAI4,51952017-07-012017-05-09
11SAI SOLITAREResidentialNA3400SECTOR 35H KHARGHAR NAVI MUMBAI4,51832017-07-012017-06-21

Member Information

Member Name Designation Photo
Paradise Infracon Private Limited Partner View Photo
Manish Madhu Bathija Partner View Photo
Umesh Kumar Bhagwatprasad Upadhyay Authorized Signatory View Photo
Ebrahim Esmail Dhariwala Partner View Photo

Project

SAI WORLD CITY PHASE II
New Project
30/12/2025
No
Residential
Yes
98/8/1/3
Palaspe Junction
Kolkhe Nala
Kalundre River
NH 4B
MAHARASHTRA
Konkan
Raigarh
Panvel
Kolkhe
NH 4B
Panvel
410206
13595
1
1
0
0

FSI Details

35582
0
35582.00

Details of RERA Designated Separate Bank Account

State Bank of India
SBIN0001593

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
SAI WORLD CITY PHASE II Dhariwala Developments Partnership Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Upload Agreement / MoU Copy
4 Upload Agreement / MoU Copy
5 Upload Agreement / MoU Copy
6 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 838 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 As per CC
Water Conservation, Rain water Harvesting : YES 0 As per EC
Energy management : YES 0 As per CC
Fire Protection And Fire Safety Requirements : YES 0 As per CC
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 As per CC
Aggregate area of recreational Open Space : YES 0 As per CC
Open Parking : YES 0 As per CC
Water Supply : YES 0 As per CC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 As per CC and EC
Storm Water Drains : YES 0 As per EC
Landscaping & Tree Planting : YES 0 As per EC
Street Lighting : YES 0 As per CC
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 As per CC and EC
Solid Waste Management And Disposal : YES 0 As per EC

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 SAI WORLD CITY PHASE II Sale Building No 3 31/12/2024 2 1 2 31 1 13 838
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 56.9 196 117
2 2BHK 57.07 28 21
3 2BHK 64.08 153 95
4 3BHK 75.47 56 44
5 3BHK 86.58 56 52
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 70
2 X number of Basement(s) and Plinth 50
3 X number of Podiums 33
4 Stilt Floor 33
5 X number of Slabs of Super Structure 96
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 71
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 36
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 45
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

34
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 10
11 Overall Percentage of Completion of the work done For the entire Building /Wing 47.8

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Dimensions Architects Pvt Ltd NA Architect
Structural Concept Designs pvt ltd NA Engineer
Bhavika Enterprises NA Contractor
Vira & Gor NA Chartered Accountant
Aristo Real Estate Consultants A51700036861 Real Estate Agent
Rangani & Co NA Chartered Accountant
S U Radhakrishnani & co NA Chartered Accountant

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
3 Building Plan Approval / NA Order for plotted development
4 Building Plan Approval / NA Order for plotted development
5 Building Plan Approval / NA Order for plotted development
6 Building Plan Approval / NA Order for plotted development
7 Building Plan Approval / NA Order for plotted development
8 Building Plan Approval / NA Order for plotted development
9 Building Plan Approval / NA Order for plotted development
10 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement
1 Other – Legal
1 Other – Finance
1 Other – Technical