Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1BELLE VIEOthersCOMMERCIAL AND RESIDENTIAL5950GAT NO 668 WAGHOLIGAT NO 6682942014-05-302015-06-23
2BUONA VITAResidentialNA5051SATEGAT NO 3381542016-05-262017-07-30

Member Information

Member Name Designation Photo
HAREN SAHIB MALKANI Partner View Photo
NEHA HAREN SAHIB Partner View Photo
JAIWANTI PARSHOTAM PAHUJA Partner View Photo
PARSHOTAM TULSIDAS PAHUJA Partner View Photo

Project

BON VIVANT
On-Going Project
30/06/2018
30/06/2019
No
Others
No
S No 33/3A/2 Mundhawa Keshavnagar Pune 411036
Road
Property owned by Murlidhar Pandurang Lonkar
Property owned by Dharma Dagdu Lonkar
Property owned by Mr Jagannath Lonkar
MAHARASHTRA
Pune
Pune
Haveli
Mundhawa
Near Old Orbis School
Mundhawa-Keshavnagar
411036
6257.63
3
3
0
669.54

FSI Details

7849.31
1335
9184.31

Bank Details

HDFC BANK
HDFC0001210

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 54 19 50

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 25 WORK STARTED
Water Conservation, Rain water Harvesting : YES 0 YET TO COMMENCE
Energy management : YES 0 YET TO COMMENCE
Fire Protection And Fire Safety Requirements : YES 20 WORK UNDER PROGRESS
Electrical Meter Room, Sub-Station, Receiving Station : YES 50 SUB STATION READY
Aggregate area of recreational Open Space : YES 0 YET TO COMMENCE
Open Parking : YES 0 YET TO COMMENCE
Water Supply : YES 50 UGT. TANK COMPLETED
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 40 WORK UNDER PROGRESS
Storm Water Drains : YES 0 YET TO COMMENCE
Landscaping & Tree Planting : YES 0 YET TO COMMENCE
Street Lighting : YES 0 YET TO COMMENCE
Community Buildings : YES 50 RCC WORK COMPLETED
Treatment And Disposal Of Sewage And Sullage Water : YES 0 YET TO COMMENCE
Solid Waste Management And Disposal : YES 0 YET TO COMMENCE

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 BON VIVANT A WING 30/06/2019 1 1 0 13 1 17 23
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 40.64 1 1
2 2 BHK 67.18 1 0
3 2 BHK 64.67 1 0
4 2 BHK 64.96 1 0
5 2 BHK 67.62 1 0
6 1 BHK 40.74 5 4
7 1 BHK 42.35 5 3
8 2 BHK 49.03 4 3
9 2 BHK 55.99 2 1
10 2 BHK 56.45 2 1
11 2 BHK 51.46 3 3
12 2 BHK 55.02 3 2
13 2 BHK 51.84 3 3
14 2 BHK 55.18 3 3
15 2 BHK 47.96 4 3
16 2 BHK 55.97 1 0
17 2 BHK 55.66 1 0
18 2 BHK 52.48 1 1
19 2 BHK 52.73 1 0
20 2 BHK 52.73 1 1
21 1 BHK 38.07 4 0
22 1 BHK 42.25 1 0
23 2 BHK 48.25 1 0
24 2 BHK 49.32 1 1
25 2 BHK 52.41 1 1
26 1 BHK 36.45 4 2
27 2 BHK 55.70 8 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 50
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 40
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

40
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 49
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 BON VIVANT B WING 30/06/2019 1 1 0 13 1 17 23
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 67.18 1 0
2 2 BHK 64.67 1 0
3 2 BHK 64.96 1 0
4 2 BHK 67.62 1 0
5 1 BHK 40.74 5 5
6 1 BHK 42.35 5 5
7 2 BHK 48.42 1 1
8 2 BHK 56.16 1 0
9 2 BHK 48.89 1 1
10 2 BHK 51.62 8 6
11 2 BHK 55.02 4 3
12 2 BHK 48.13 4 3
13 2 BHK 48.61 4 4
14 2 BHK 52.41 1 1
15 2 BHK 55.97 1 1
16 2 BHK 52.41 1 1
17 1 BHK 36.45 5 4
18 2 BHK 55.18 4 3
19 1 BHK 38.07 5 2
20 2 BHK 55.40 1 1
21 2 BHK 52.59 1 1
22 2 BHK 55.89 4 1
23 2 BHK 52.32 4 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 60
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

60
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 53
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 BON VIVANT C WING 30/06/2019 1 1 0 5 0 16 8
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 40.94 8 8
2 OFFICE 26.58 4 2
3 OFFICE 20.71 12 9
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

80
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60
11 Overall Percentage of Completion of the work done For the entire Building /Wing 77

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Mr Aqueelur Rahman Mohammed Haneef NA Engineer
Mr Imran Mohammad Abbas Shaikh NA Architect
MR. VINAY G. PHADNIS NA Other Professional
Mr. Vinod Kumar Jain NA Other Professional
CHANDRAKANT N KAMBLE NA Contractor
Subhash Chandrakant Sonkamble A52100002477 Real Estate Agent
Nadir Badruddin Nilgiriwala A52100007548 Real Estate Agent
SATINDERPALSINGH JOGINDERPALSINGH ARORA A52100004752 Real Estate Agent
Big Deal Properties (India) Pvt. Ltd A52100000579 Real Estate Agent
Premlata Landmarks LLP A52100013295 Real Estate Agent
Property Pointer Private Limited A52100000787 Real Estate Agent
NAGARJUN SUBBAYA TADIKALA A52100015525 Real Estate Agent
VIKAS SATISH GUPTA A52100002607 Real Estate Agent
Nitin Raju Mane proprieter of Royalty realtors A52100017013 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
8 Building Plan Approval (IOD)
9 Building Plan Approval (IOD)
10 Building Plan Approval (IOD)
11 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
2 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
4 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Certificates of Architect (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement