MahaRERA Application

General Information

Other Than Individual

Organization

ROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED
Company
NA
Do you have any Past Experience ?
Yes

Address Details

CTS NO. 2254
1 MODI BAUG, COMMERCIAL BUILDING
GANESHKHIND ROAD
SHIVAJI NAGAR
NEAR AGRICULTURE COLLEGE
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411016

Organization Contact Details

02071017101
www.rohanbuilders.com

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Rohan Kritika D E K WingsResidentialNA3619S NO 117 A 1 117 B PARVATI PUNE 411009538A3942017-06-302017-04-28
2Rohan Kritika F G H I J WingResidentialNA7008S NO 117 A1 117 B PARVATI PUNE 411009CTS 538 A51872016-06-302017-03-30
3ROHAN LEHER 2 WINGS K L M N OResidentialNA1520BANER PUNE 411045S NO 53/5 ,53/6 ,54/1 ,54/12 BANER5502016-12-312017-03-31

Member Information

Member Name Designation Photo
SANJAY LUNKAD Authorized Signatory View Photo

Project

ROHAN ABHILASHA BUILDING B
On-Going Project
31/12/2021
30/12/2021
30/12/2023
Yes
Residential
No
GAT NO 1458 1459 1460 P 1461 1462 1463 1464 1465 WAGHOLI
18 MTR ROAD
BLDG A
12 MTR ROAD
BLDG D
MAHARASHTRA
Pune
Pune
Haveli
WAGHOLI
Bakre Avenue, F P No 226/3, Bhandarkar Road, Pune 411004
Bhandarkar Road
411010
6013.81
4
4
0
11790.73

FSI Details

23989.9
1200
25189.90

Bank Details

KOTAK MAHINDRA BANK LTD
KKBK0000723

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 407 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 ENTIRE PROJECT
Water Conservation, Rain water Harvesting : YES 100 ENTIRE PROJECT
Energy management : YES 100 ENTIRE PROJECT
Fire Protection And Fire Safety Requirements : YES 100 ENTIRE PROJECT
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 ENTIRE PROJECT
Sewerage line chamber STP : YES 100 BUILDING B
Storm water drains : YES 100 BUILDING B
Water supply : YES 100 BUILDING B
Aggregate area of recreational Open Space : YES 100 ENTIRE PROJECT
Open Parking : NO 0 NA
Water Supply : YES 100 ENTIRE PROJECT
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 ENTIRE PROJECT
Storm Water Drains : YES 100 ENTIRE PROJECT
Landscaping & Tree Planting : YES 100 ENTIRE PROJECT
Street Lighting : YES 100 ENTIRE PROJECT
Community Buildings : YES 100 CLUB HOUSE FOR ENTIRE PROJECT
Treatment And Disposal Of Sewage And Sullage Water : YES 100 ENTIRE PROJECT
Solid Waste Management And Disposal : YES 100 ENTIRE PROJECT

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 ROHAN ABHILASHA BUILDING B WING B1 30/06/2023 0 1 1 12 1 0 107
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 72.40 8 8
2 3BHK 76.92 3 3
3 3BHK 73.60 9 9
4 3BHK 78.16 23 23
5 3BHK 78.37 15 15
6 3BHK 73.03 1 1
7 3BHK 77.33 1 1
8 3BHK 77.69 1 1
9 1BHK 38.71 1 1
10 1BHK 39.49 1 1
11 3BHK 72.83 2 2
12 3BHK 72.90 2 2
13 3BHK 73.24 1 1
14 3BHK 79.19 4 4
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 ROHAN ABHILASHA BUILDING B WING B2 30/06/2023 0 1 1 12 1 0 100
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 68.14 2 2
2 2BHK 57.58 4 4
3 2BHK 56.11 9 9
4 2BHK 55.36 1 1
5 3BHK 69.17 12 12
6 3BHK 69.78 2 2
7 1BHK 34.86 1 1
8 1BHK 38.74 1 1
9 2BHK 57.22 5 5
10 3BHK 68.85 8 8
11 3BHK 69.64 2 2
12 3BHK 70.77 11 11
13 1BHK 55.33 2 2
14 2BHK 55.34 10 10
15 2BHK 55.51 2 2
16 2BHK 58.24 1 1
17 3BHK 67.97 10 10
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 95
11 Overall Percentage of Completion of the work done For the entire Building /Wing 89.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 ROHAN ABHILASHA BUILDING B WING B3 30/06/2023 0 1 1 12 1 0 100
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 53.07 18 18
2 2BHK 55.97 8 8
3 2BHK 56.14 4 4
4 2BHK 57.24 8 8
5 2BHK 57.23 2 2
6 1BHK 39.14 1 1
7 2BHK 53.68 4 4
8 2BHK 53.84 2 2
9 2BHK 56.13 8 8
10 2BHK 55.36 26 26
11 2BHK 57.87 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
4 ROHAN ABHILASHA BUILDING B WING B4 30/06/2023 0 1 1 12 1 0 100
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 64.81 4 4
2 3BHK 65.44 2 2
3 3BHK 65.75 6 6
4 3BHK 65.92 2 2
5 3BHK 68.84 4 4
6 3BHK 69.00 8 8
7 3BHK 69.66 4 4
8 3BHK 64.82 5 5
9 3BHK 69.16 21 21
10 3BHK 69.33 8 8
11 3BHK 69.80 4 4
12 1BHK 36.50 1 1
13 3BHK 64.51 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Prakash Kulkarni NA Architect
ROCKWELL HOMES REALTY SERVICES LLP A52100025931 Real Estate Agent
Live 24 Realty LLP A52000026307 Real Estate Agent
Shishu Singh A52100017226 Real Estate Agent
PROPTIGER MARKETING SERVICES PRIVATE LIMITED A51700000030 Real Estate Agent
Townsip Housing Private Limited A52100021523 Real Estate Agent
Trespect India Private Ltd A51900020838 Real Estate Agent
JM Financial Products Limited A51900000277 Real Estate Agent
Bipin Kumar Sharma A52100019826 Real Estate Agent
FULL BASKET PROPERTY SERVICES PRIVATE LIMITED A52100005036 Real Estate Agent
Pin Click Property Management Pvt Ltd. A52100012083 Real Estate Agent
Susmita Kumari A52100019489 Real Estate Agent
Capitalist Yard India Pvt Ltd A57200023087 Real Estate Agent
Bipin Kumar Sharma A52100019826 Real Estate Agent
PROPBUYING REALTORS PVT LTD A52100000476 Real Estate Agent
GRUHAM24 REALTY PRIVATE LIMITED A52100026876 Real Estate Agent
Suraj Pandit Darekar A52100008554 Real Estate Agent
Dattatray Rambhau Bhogil A52100018350 Real Estate Agent
MDN Properties Private Limited A52100017448 Real Estate Agent
Nobroker Technologies Solutions Private Limited A51800026821 Real Estate Agent
Sandip Shivaji Rathod A52100016264 Real Estate Agent
Avinash Mahamuni A52100026575 Real Estate Agent
R-Constellation Pvt. Ltd. A52100000304 Real Estate Agent
360 REALTORS LLP A51900000246 Real Estate Agent
NITIN SHANKAR KADDE A52100000577 Real Estate Agent
Nishikant Udaisingh Rajawat A52100024375 Real Estate Agent

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
ROHAN ABHILASHA BUILDING B CJSD PUNE 2/2020 Civil No Suit NA 2020 AWAITING NOTICE FOR OTHER DEFENDANTS
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
3 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
15 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
16 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
17 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
18 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
19 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
20 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
21 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
22 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
23 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
24 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
25 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
14 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
15 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
16 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
17 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
18 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
19 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
20 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
21 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
22 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
23 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
24 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Form 2A
2 Form 2A
3 Form 2A
4 Form 2A
5 Form 2A
6 Form 2A
7 Form 2A
8 Form 2A
9 Form 2A
10 Form 2A
11 Form 2A
12 Form 2A
13 Form 2A
14 Form 2A
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
5 Disclosure of sold/ booked inventory
6 Disclosure of sold/ booked inventory
7 Disclosure of sold/ booked inventory
8 Disclosure of sold/ booked inventory
9 Disclosure of sold/ booked inventory
10 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
2 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
3 Other
4 Other
5 Other
1 Other – Finance
1 Other – Technical
2 Other – Technical
3 Other – Technical
4 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement