MahaRERA Application

General Information

Other Than Individual

Organization

Ashank Macbricks Private Limited
Company
NA
Do you have any Past Experience ?
No

Address Details

5th Floor
Godrej One
Pirojshanagar
Vikhroli East
Eastern Express Highway
MAHARASHTRA
Konkan
Mumbai Suburban
Kurla
Kurla
400079

Organization Contact Details

02261198500

Past Experience Details

Member Information

Member Name Designation Photo
Rajib Das Director View Photo
Ruchir Mehrotra Authorized Signatory View Photo

Project

Godrej Exquisite
New Project
30/03/2025
No
Residential
Yes
141/5, 206/2
SNo 207 SNo 141 Hissa 3 SNo 141 Hissa 4
60mt wide DP Road
SNo 206 Hissa 3 SNo 206 Hissa 4 SNo 206 Hissa 5
SNo 141 Hissa 6
MAHARASHTRA
Konkan
Thane
Thane
Thane (M Corp.)
Ghodbunder Road
Kavesar
400607
14626
3
3
0
6531

FSI Details

4800
36205
41005.00

Bank Details

Axis Bank
UTIB0000004

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Godrej Exquisite Godrej Properties Limited (Development Manager) Company Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 705 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 As per approved plan
Energy management : YES 0 As per approved plan
Fire Protection And Fire Safety Requirements : YES 0 As per approved plan
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 As per approved plan
Aggregate area of recreational Open Space : YES 0 As per approved plan
Open Parking : NO 0 NA
Water Supply : YES 0 As per approved plan
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 As per approved plan
Storm Water Drains : YES 0 As per approved plan
Landscaping & Tree Planting : YES 0 As per approved plan
Street Lighting : NO 0 NA
Community Buildings : YES 0 Clubhouse provided
Treatment And Disposal Of Sewage And Sullage Water : YES 0 As per approved plan
Solid Waste Management And Disposal : YES 0 As per approved plan

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 Godrej Exquisite Tower 1 30/09/2024 0 1 4 39 1 0 248
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 Bed Premium 57.85 62 0
2 2 Bed Luxe 58.97 33 0
3 3 Premium 60.40 24 0
4 3 Bed Luxe 60.61 66 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 Godrej Exquisite Tower 2 30/09/2024 0 1 4 39 1 0 239
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 Bed Premium 57.85 62 0
2 2 Bed Luxe 58.97 33 0
3 3 Premium 61.32 24 0
4 3 Bed Luxe 60.61 66 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 Godrej Exquisite Tower 3 30/09/2024 0 1 4 39 1 0 218
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 Bed Luxe 44.16 9 0
2 2 Premium 45.49 4 0
3 2 Bed Premium 57.85 26 0
4 2 Bed Luxe 58.97 33 0
5 3 Premium 61.32 10 0
6 3 Bed Luxe 60.61 66 0
7 1 Bed Luxe 43.02 27 0
8 2 Premium 44.09 10 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval / NA Order for plotted development
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other