MahaRERA Application

General Information

Other Than Individual

Organization

DEV LAND & HOUSING PVT LTD
Company
NA
Do you have any Past Experience ?
No

Address Details

10TH FLOOR
DEV PLAZA
S V ROAD
ANDHERI WEST
OPP ANDHERI FIRE STATION
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
400058

Organization Contact Details

02240383838

Past Experience Details

Member Information

Member Name Designation Photo
VIJAY THAKORDAS THAKKAR Authorized Signatory View Photo

Project

DEV ASHOKA
On-Going Project
31/12/2017
31/05/2019
30/11/2020
No
Others
Yes
PLOT BEARING F P 45
60 FEET PROPOSED D P ROAD
PIPE LINE
KAMGAR HOSPITAL D P ROAD
ADJACENT FINAL PLOT NO 46
MAHARASHTRA
Konkan
Thane
Thane
Thane (M Corp.)
ESIC Hospital Road
Near Nitin Company Junction
400604
10909.78
3
3
0
2526.80

FSI Details

32983
0
32983.00

Bank Details

BANK OF MAHARASHTRA
MAHB0000110

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
DEV ASHOKA SHREE MANGALMURTI ENTERPRISES Partnership Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Upload Agreement / MoU Copy
4 Upload Agreement / MoU Copy
5 Upload Agreement / MoU Copy
6 Upload Agreement / MoU Copy
7 Upload Agreement / MoU Copy
8 Upload Agreement / MoU Copy
9 Upload Agreement / MoU Copy
10 Upload Agreement / MoU Copy
11 Upload Agreement / MoU Copy
12 Upload Agreement / MoU Copy
13 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 361 70 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 WIP
Energy management : YES 0 Solar
Fire Protection And Fire Safety Requirements : YES 30 WIP
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 WIP
0 : NO 0 NA
Common Podium 1 basement and 3 levels : YES 0 WIP
Fitness Centre and Swimming Pool : YES 0 Swimming Pool Proposed
Aggregate area of recreational Open Space : YES 0 WIP
Open Parking : YES 0 WIP
Water Supply : YES 0 WIP
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 30 WIP
Storm Water Drains : YES 25 WIP
Landscaping & Tree Planting : YES 0 WIP
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 WIP
Solid Waste Management And Disposal : YES 0 WIP

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 DEV ASHOKA DEV ASHOKA S1 31/05/2019 2 1 0 24 0 4 150
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 STORE NO 7 24.09 1 0
2 STORE NO 8 20.05 1 1
3 STORE NO 9 25.87 1 1
4 STORE NO 10 29.28 1 0
5 STORE NO 11 30.34 1 0
6 5.5 BHK 156.50 1 1
7 SHOP 1 AND 2 58.64 2 0
8 STORE 1 AND 2 116.91 1 0
9 OFFICE NO 1 118.17 1 0
10 OFFICE NO 5 45.24 1 1
11 SHOP NO 7 28.09 1 0
12 SHOP NO 8 23.99 1 1
13 SHOP NO 9 31.76 1 1
14 SHOP NO 10 32.33 1 0
15 SHOP NO 11 31.20 1 0
16 STORE NO 3 76.16 1 0
17 SHOP NO 5 32.66 1 0
18 SHOP NO 6 33.62 1 0
19 Type A 2BHK 58.25 37 16
20 Type B 2BHK 59.25 20 5
21 Type C 2BHK 56.75 20 5
22 Type D 2BHK 55.5 19 2
23 Type E 3BHK 73.75 19 8
24 OFFICE NO 6 36.38 1 0
25 SHOP 3 76.66 1 0
26 SHOP NO 4 33.21 1 0
27 STORE NO 4 AND 5 26.25 2 0
28 STORE NO 6 26.82 1 0
29 OFFICE NO 2 76.85 1 0
30 OFFICE NO 3 75.43 1 0
31 OFFICE NO 4 50.16 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 88
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 75
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 95
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

80
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 30
11 Overall Percentage of Completion of the work done For the entire Building /Wing 66.8
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 DEV ASHOKA DEV ASHOKA S2 31/05/2019 1 1 0 24 0 4 150
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 90
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 25
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 20
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 40
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 37.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 DEV ASHOKA DEV ASHOKA S3 31/05/2019 0 1 0 2 0 2 51
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP NO 26 29.13 1 0
2 SHOP NO 27 29.13 1 0
3 SHOP NO 29 29.13 1 0
4 OFFICE NO 13 28.83 1 0
5 OFFICE NO 14 28.83 1 0
6 OFFICE NO 15 28.83 1 0
7 OFFICE NO 16 28.83 1 0
8 Shop No. 30 24.73 1 0
9 Office No. 17 68.73 1 0
10 SHOP NO 25 29.13 1 1
11 SHOP NO 28 29.13 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
YOGESH N KELKAR AND ASSOCIATES NA Architect
AJAY MAHALE NA Engineer
United One Infra Pvt Ltd NA Contractor

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
3 Details of encumbrances
4 Details of encumbrances
5 Details of encumbrances
6 Details of encumbrances
7 Details of encumbrances
8 Details of encumbrances
9 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
8 Building Plan Approval (IOD)
9 Building Plan Approval (IOD)
10 Building Plan Approval (IOD)
11 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
2 Declaration in FORM B
3 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
2 Certificates of CA (Form 5)
3 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
3 Other
4 Other
5 Other
6 Other
7 Other
8 Other
9 Other
10 Other
11 Other
12 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement