MahaRERA Application

General Information

Other Than Individual

Organization

OM VIMAL DEVELOPERS
Partnership
NA
Do you have any Past Experience ?
No

Address Details

806
PRATHMESH POOJA CHS
TPS ROAD
BORIVALI-WEST
VEER SAVARKAR GARDEN
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Borivali
400092

Organization Contact Details

02228981111

Past Experience Details

Member Information

Member Name Designation Photo
NIRAV BHARAT SHAH Authorized Signatory View Photo
ASHOK MANILAL SHAH Partner View Photo
BHARAT MANILAL SHAH Partner View Photo
DILIP KANTILAL SHAH Partner View Photo
MILAN KANTILAL SHAH Partner View Photo
SANAT NARENDRA MEHTA HUF Partner View Photo
DEEPA SANAT MEHTA Partner View Photo

Project

VIMAL CLASSIC
On-Going Project
15/12/2021
20/12/2023
19/12/2024
No
Residential
No
183266
ROAD
R G AREA GARDEN
ROAD
BUILDING
MAHARASHTRA
Konkan
Palghar
Vasai
Vasai-Virar City (M Corp)
401203
2863.19
3
3
0
1306.58

FSI Details

4873.98
6232.65
11106.63

Bank Details

IDBI BANK
IBKL0000571

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 23 0 0
Covered Parking ( In Numbers) 0 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 FACILITY AVAILABE IN A LARGER LAYOUT
Water Conservation, Rain water Harvesting : YES 0 WORK IN PROGRESS
Energy management : YES 0 WORK IN PROGRESS
Fire Protection And Fire Safety Requirements : YES 0 WORK IN PROGRESS
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 WORK IN PROGRESS
Aggregate area of recreational Open Space : YES 0 WORK IN PROGRESS
Open Parking : YES 0 WORK IN PROGRESS
Water Supply : YES 0 FACILITY WILL START ONCE VVCMC WATER SUPPLY COMMEN
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 WORK IN PROGRESS
Storm Water Drains : YES 0 WORK IN PROGRESS
Landscaping & Tree Planting : YES 0 FACILITY AVAILABLE IN A LARGER LAYOUT
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 WORK IN PROGRESS
Solid Waste Management And Disposal : YES 0 WORK IN PROGRESS

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 VIMAL CLASSIC VIMAL CLASSIC-C 20/12/2022 0 1 0 16 9 5 9
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 25.64 1 0
2 SHOP 23.60 1 0
3 SHOP 29.79 1 0
4 SHOP 17.12 2 1
5 SHOP 24.21 1 0
6 SHOP 17.96 2 1
7 1BHK 31.72 30 1
8 1BHK 32.36 5 0
9 1BHK 32.48 5 0
10 1BHK 32.53 1 0
11 1BHK 32.54 18 0
12 1BHK 32.79 2 0
13 1BHK 32.91 2 0
14 1BHK 32.94 10 0
15 1BHK 34.94 1 0
16 1BHK 36.72 1 0
17 1BHK 36.84 1 0
18 1BHK 36.89 1 0
19 1BHK 36.9 1 0
20 1BHK 37.74 18 0
21 1BHK 37.78 7 0
22 1BHK 37.86 6 0
23 1BHK 37.91 1 0
24 1BHK 38 7 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 37
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 33.7
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 VIMAL CLASSIC VIMAL CLASSIC-D 20/12/2022 0 1 0 16 10 7 10
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 29.79 1 0
2 1BHK 29.8 1 0
3 1BHK 32.48 4 0
4 1BHK 32.88 2 2
5 1BHK 36.72 1 1
6 SHOP 24.21 1 1
7 SHOP 23.60 1 0
8 1BHK 36.89 1 1
9 1BHK 36.9 1 1
10 1BHK 37.26 1 1
11 1BHK 37.62 1 1
12 1BHK 37.8 1 1
13 1BHK 32.36 5 2
14 SHOP 25.64 1 1
15 1BHK 31.72 30 20
16 1BHK 32.54 19 3
17 1BHK 32.76 2 1
18 1BHK 32.94 10 5
19 1BHK 36.84 1 0
20 1BHK 37.74 19 16
21 1BHK 37.78 6 5
22 1BHK 37.86 6 5
23 1BHK 38 6 5
24 SHOP 17.12 2 2
25 SHOP 17.96 2 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

30
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 48
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 VIMAL CLASSIC VIMAL CLASSIC-E 20/12/2022 1 1 1 16 4 7 4
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 33.26 9 6
2 1BHK 33.66 6 4
3 1BHK 36.18 10 8
4 1BHK 36.30 6 3
5 1BHK 36.38 2 2
6 1BHK 37.74 6 6
7 1BHK 38.55 5 5
8 BASEMENT 41.10 1 0
9 BASEMENT 35.62 1 0
10 1BHK 32.85 1 0
11 1BHK 36.47 1 1
12 SHOP 35.98 1 0
13 SHOP 45.23 1 0
14 SHOP 23.36 1 1
15 BASEMENT 44.87 1 0
16 SHOP 41.46 1 0
17 SHOP 17.31 2 2
18 SHOP 25.10 1 0
19 1ST FLOOR SHOP 46.51 1 0
20 1ST FLOOR SHOP 37.03 1 0
21 1ST FLOOR SHOP 53.93 1 0
22 1BHK 31.32 10 7
23 1BHK 33.8 1 1
24 1BHK 35.63 1 0
25 1BHK 36.19 1 1
26 1BHK 36.22 1 0
27 1BHK 40.05 1 1
28 1BHK 36.21 8 6
29 1BHK 30.92 20 8
30 1BHK 32.54 9 2
31 1BHK 32.94 12 6
32 SHOP 17.15 1 0
33 1BHK 33.57 4 4
34 1BHK 35.72 1 0
35 SHOP 23.12 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

30
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 48

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
AJAY WADE & ASSOCIATES NA Architect

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 CERSAI details
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
5 Disclosure of sold/ booked inventory
6 Disclosure of sold/ booked inventory
7 Disclosure of sold/ booked inventory
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement