Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
1 |
HDIL PARADISE CITY SECTOR 3
|
BUILDING NO 1
|
|
0
|
1
|
0
|
5
|
1 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
COMMERCIAL |
17.27 |
3 |
1 |
2 |
RESIDENTIAL |
45.47 |
1 |
1 |
3 |
RESIDENTIAL |
40.91 |
7 |
7 |
4 |
RESIDENTIAL |
29.41 |
3 |
2 |
5 |
RESIDENTIAL |
29.86 |
21 |
17 |
6 |
COMMERCIAL |
13.08 |
3 |
3 |
7 |
COMMERCIAL |
13.17 |
3 |
2 |
8 |
COMMERCIAL |
13.77 |
1 |
0 |
9 |
COMMERCIAL |
10.59 |
3 |
3 |
10 |
COMMERCIAL |
10.81 |
1 |
1 |
11 |
COMMERCIAL |
12.60 |
1 |
0 |
12 |
COMMERCIAL |
12.84 |
2 |
2 |
13 |
COMMERCIAL |
12.99 |
1 |
0 |
14 |
COMMERCIAL |
14.51 |
1 |
0 |
15 |
COMMERCIAL |
14.16 |
1 |
1 |
16 |
COMMERCIAL |
17.14 |
3 |
1 |
17 |
COMMERCIAL |
9.33 |
1 |
0 |
18 |
COMMERCIAL |
9.87 |
1 |
1 |
19 |
RESIDENTIAL |
25.18 |
3 |
3 |
20 |
RESIDENTIAL |
30.34 |
3 |
3 |
21 |
RESIDENTIAL |
30.76 |
8 |
8 |
22 |
RESIDENTIAL |
42.10 |
1 |
1 |
23 |
RESIDENTIAL |
24.34 |
21 |
17 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
20
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
5
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
32.5
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
2 |
HDIL PARADISE CITY SECTOR 3
|
BUILDING NO 2
|
|
0
|
1
|
0
|
5
|
1 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
RESIDENTIAL |
34.07 |
5 |
3 |
2 |
RESIDENTIAL |
24.34 |
24 |
16 |
3 |
RESIDENTIAL |
29.86 |
24 |
18 |
4 |
RESIDENTIAL |
33.89 |
1 |
1 |
5 |
RESIDENTIAL |
36.97 |
1 |
1 |
6 |
RESIDENTIAL |
29.32 |
1 |
0 |
7 |
RESIDENTIAL |
28.46 |
4 |
2 |
8 |
RESIDENTIAL |
30.45 |
4 |
4 |
9 |
RESIDENTIAL |
27.22 |
8 |
7 |
10 |
RESIDENTIAL |
28.71 |
8 |
8 |
11 |
RESIDENTIAL |
29.41 |
6 |
3 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
80
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
18
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
3 |
HDIL PARADISE CITY SECTOR 3
|
BUILDING NO 3
|
|
0
|
1
|
0
|
5
|
1 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
RESIDENTIAL |
29.41 |
6 |
6 |
2 |
RESIDENTIAL |
34.07 |
5 |
5 |
3 |
RESIDENTIAL |
24.34 |
24 |
18 |
4 |
RESIDENTIAL |
29.86 |
24 |
18 |
5 |
RESIDENTIAL |
33.89 |
1 |
1 |
6 |
RESIDENTIAL |
36.97 |
1 |
1 |
7 |
RESIDENTIAL |
29.32 |
1 |
1 |
8 |
RESIDENTIAL |
28.46 |
4 |
3 |
9 |
RESIDENTIAL |
30.45 |
4 |
3 |
10 |
RESIDENTIAL |
27.22 |
8 |
6 |
11 |
RESIDENTIAL |
28.71 |
8 |
7 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
30
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
7
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
33.7
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
4 |
HDIL PARADISE CITY SECTOR 3
|
BUILDNG NO 4
|
|
0
|
1
|
0
|
5
|
1 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
RESIDENTIAL |
29.41 |
6 |
4 |
2 |
RESIDENTIAL |
34.07 |
5 |
3 |
3 |
RESIDENTIAL |
24.34 |
24 |
18 |
4 |
RESIDENTIAL |
29.86 |
24 |
15 |
5 |
RESIDENTIAL |
33.89 |
1 |
0 |
6 |
RESIDENTIAL |
36.97 |
1 |
1 |
7 |
RESIDENTIAL |
29.32 |
1 |
0 |
8 |
RESIDENTIAL |
28.46 |
4 |
2 |
9 |
RESIDENTIAL |
30.45 |
4 |
3 |
10 |
RESIDENTIAL |
27.22 |
8 |
8 |
11 |
RESIDENTIAL |
28.71 |
8 |
7 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
80
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
18
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
5 |
HDIL PARADISE CITY SECTOR 3
|
BUILDING NO 5
|
|
0
|
1
|
0
|
5
|
1 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
RESIDENTIAL |
25.76 |
30 |
22 |
2 |
RESIDENTIAL |
32.01 |
27 |
20 |
3 |
RESIDENTIAL |
27.76 |
9 |
8 |
4 |
RESIDENTIAL |
33.24 |
5 |
4 |
5 |
RESIDENTIAL |
30.27 |
5 |
4 |
6 |
RESIDENTIAL |
30.39 |
10 |
6 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
80
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
2
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
18
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
40
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
6 |
HDIL PARADISE CITY SECTOR 3
|
BUILDING NO 6
|
|
0
|
1
|
0
|
5
|
1 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
RESIDENTIAL |
27.22 |
8 |
8 |
2 |
RESIDENTIAL |
28.71 |
8 |
8 |
3 |
RESIDENTIAL |
24.34 |
24 |
17 |
4 |
RESIDENTIAL |
29.32 |
1 |
1 |
5 |
RESIDENTIAL |
33.89 |
1 |
1 |
6 |
RESIDENTIAL |
29.86 |
24 |
16 |
7 |
RESIDENTIAL |
29.41 |
6 |
4 |
8 |
RESIDENTIAL |
34.07 |
5 |
3 |
9 |
RESIDENTIAL |
28.46 |
4 |
4 |
10 |
RESIDENTIAL |
30.45 |
4 |
4 |
11 |
RESIDENTIAL |
36.97 |
1 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
15
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
11.5
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
7 |
HDIL PARADISE CITY SECTOR 3
|
BUILDING NO 7
|
|
0
|
1
|
0
|
5
|
1 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
COMMERCIAL |
9.33 |
1 |
0 |
2 |
COMMERCIAL |
10.59 |
3 |
2 |
3 |
COMMERCIAL |
10.80 |
1 |
1 |
4 |
COMMERCIAL |
12.69 |
1 |
1 |
5 |
COMMERCIAL |
12.84 |
2 |
2 |
6 |
COMMERCIAL |
13.08 |
3 |
3 |
7 |
COMMERCIAL |
13.17 |
3 |
2 |
8 |
COMMECIAL |
14.66 |
1 |
0 |
9 |
COMMERCIAL |
15.18 |
1 |
1 |
10 |
COMMERCIAL |
16.79 |
1 |
1 |
11 |
COMMERCIAL |
17.14 |
3 |
1 |
12 |
COMMERCIAL |
17.27 |
3 |
3 |
13 |
COMMERCIAL |
17.41 |
1 |
1 |
14 |
RESIDENTIAL |
29.41 |
3 |
2 |
15 |
RESIDENTIAL |
25.18 |
3 |
3 |
16 |
RESIDENTIAL |
30.34 |
3 |
3 |
17 |
RESIDENTIAL |
24.34 |
21 |
18 |
18 |
RESIDENTIAL |
29.86 |
21 |
17 |
19 |
RESIDENTIAL |
23.13 |
1 |
0 |
20 |
RESIDENTIAL |
34.07 |
2 |
1 |
21 |
RESIDENTIAL |
28.46 |
4 |
3 |
22 |
RESIDENTIAL |
31.55 |
1 |
0 |
23 |
RESIDENTIAL |
28.58 |
1 |
1 |
24 |
RESIDENTIAL |
27.22 |
7 |
7 |
25 |
RESIDENTIAL |
28.71 |
8 |
6 |
26 |
RESIDENTIAL |
30.45 |
3 |
2 |
27 |
COMMERCIAL |
10.54 |
1 |
1 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
20
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
30
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
45
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
8 |
HDIL PARADISE CITY SECTOR 3
|
BUILDING NO 8
|
|
0
|
1
|
0
|
5
|
1 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
COMMERCIAL |
9.93 |
3 |
1 |
2 |
RESIDENTIAL |
23.64 |
3 |
3 |
3 |
RESIDENTIAL |
25.28 |
3 |
3 |
4 |
RESIDENTIAL |
22.70 |
28 |
25 |
5 |
COMMERCIAL |
11.43 |
1 |
1 |
6 |
COMMERCIAL |
12.32 |
3 |
3 |
7 |
COMMERCIAL |
12.40 |
3 |
3 |
8 |
COMMERCIAL |
12.98 |
1 |
1 |
9 |
COMMERCIAL |
13.01 |
2 |
2 |
10 |
COMMERCIAL |
13.84 |
1 |
1 |
11 |
COMMERCIAL |
14.01 |
3 |
3 |
12 |
COMMERCIAL |
14.60 |
1 |
1 |
13 |
COMMERCIAL |
15.43 |
1 |
0 |
14 |
COMMERCIAL |
16.13 |
3 |
2 |
15 |
COMMERCIAL |
8.91 |
1 |
1 |
16 |
COMMERCIAL |
9.30 |
1 |
1 |
17 |
COMMERCIAL |
9.87 |
1 |
1 |
18 |
RESIDENTIAL |
27.59 |
12 |
11 |
19 |
RESIDENTIAL |
24.34 |
9 |
7 |
20 |
RESIDENTIAL |
29.41 |
3 |
2 |
21 |
RESIDENTIAL |
29.22 |
4 |
2 |
22 |
RESIDENTIAL |
32.26 |
1 |
1 |
23 |
RESIDENTIAL |
23.76 |
1 |
1 |
24 |
RESIDENTIAL |
31.64 |
3 |
2 |
25 |
RESIDENTIAL |
26.83 |
4 |
3 |
26 |
RESIDENTIAL |
24.92 |
9 |
7 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
15
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
11.5
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
9 |
HDIL PARADISE CITY SECTOR 3
|
BUILDING NO 9
|
|
0
|
1
|
0
|
5
|
1 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
RESIDENTIAL |
33.98 |
1 |
1 |
2 |
RESIDENTIAL |
26.83 |
8 |
7 |
3 |
RESIDENTIAL |
29.22 |
4 |
2 |
4 |
RESIDENTIAL |
29.41 |
6 |
5 |
5 |
RESIDENTIAL |
22.70 |
32 |
27 |
6 |
RESIDENTIAL |
24.34 |
12 |
11 |
7 |
RESIDENTIAL |
27.59 |
12 |
9 |
8 |
RESIDENTIAL |
34.07 |
1 |
0 |
9 |
RESIDENTIAL |
31.64 |
4 |
3 |
10 |
RESIDENTIAL |
24.92 |
8 |
7 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
15
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
11.5
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
10 |
HDIL PARADISE CITY SECTOR 3
|
BUILDING NO 10
|
|
0
|
1
|
0
|
5
|
1 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
RESIDENTIAL |
26.83 |
8 |
7 |
2 |
RESIDENTIAL |
29.41 |
6 |
6 |
3 |
RESIDENTIAL |
22.70 |
32 |
28 |
4 |
RESIDENTIAL |
24.34 |
12 |
10 |
5 |
RESIDENTIAL |
27.59 |
12 |
11 |
6 |
RESIDENTIAL |
34.07 |
1 |
1 |
7 |
RESIDENTIAL |
33.98 |
1 |
1 |
8 |
RESIDENTIAL |
29.22 |
4 |
3 |
9 |
RESIDENTIAL |
31.64 |
4 |
1 |
10 |
RESIDENTIAL |
24.92 |
8 |
6 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
80
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
18
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
11 |
HDIL PARADISE CITY SECTOR 3
|
BUILDING NO 11
|
|
0
|
1
|
0
|
5
|
1 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
RESIDENTIAL |
27.59 |
12 |
10 |
2 |
RESIDENTIAL |
24.92 |
8 |
6 |
3 |
RESIDENTIAL |
34.07 |
1 |
1 |
4 |
RESIDENTIAL |
33.98 |
1 |
1 |
5 |
RESIDENTIAL |
29.22 |
4 |
3 |
6 |
RESIDENTIAL |
31.64 |
4 |
4 |
7 |
RESIDENTIAL |
26.83 |
8 |
6 |
8 |
RESIDENTIAL |
29.41 |
6 |
3 |
9 |
RESIDENTIAL |
22.70 |
32 |
30 |
10 |
RESIDENTIAL |
24.34 |
12 |
11 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
10
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
12 |
HDIL PARADISE CITY SECTOR 3
|
BUILDING NO 12
|
|
0
|
1
|
0
|
5
|
1 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
RESIDENTIAL |
26.83 |
8 |
5 |
2 |
RESIDENTIAL |
29.41 |
6 |
6 |
3 |
RESIDENTIAL |
22.70 |
32 |
26 |
4 |
RESIDENTIAL |
24.34 |
12 |
9 |
5 |
RESIDENTIAL |
27.59 |
12 |
11 |
6 |
RESIDENTIAL |
34.07 |
1 |
1 |
7 |
RESIDENTIAL |
33.98 |
1 |
1 |
8 |
RESIDENTIAL |
29.22 |
4 |
3 |
9 |
RESIDENTIAL |
31.64 |
4 |
4 |
10 |
RESIDENTIAL |
24.92 |
8 |
6 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
80
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
18
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
13 |
HDIL PARADISE CITY SECTOR 3
|
BUILDING NO 13
|
|
0
|
1
|
0
|
5
|
1 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
RESIDENTIAL |
24.92 |
8 |
6 |
2 |
RESIDENTIAL |
26.83 |
8 |
6 |
3 |
RESIDENTIAL |
29.41 |
6 |
5 |
4 |
RESIDENTIAL |
22.70 |
32 |
27 |
5 |
RESIDENTIAL |
24.34 |
12 |
11 |
6 |
RESIDENTIAL |
27.59 |
12 |
11 |
7 |
RESIDENTIAL |
34.07 |
1 |
1 |
8 |
RESIDENTIAL |
33.98 |
1 |
1 |
9 |
RESIDENTIAL |
29.22 |
4 |
4 |
10 |
RESIDENTIAL |
31.64 |
4 |
3 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
15
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
11.5
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
14 |
HDIL PARADISE CITY SECTOR 3
|
BUILDING NO 14
|
|
0
|
1
|
0
|
5
|
1 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
COMMERCIAL |
9.33 |
1 |
0 |
2 |
COMMERCIAL |
9.87 |
1 |
1 |
3 |
COMMERCIAL |
10.81 |
1 |
0 |
4 |
COMMERCIAL |
12.60 |
1 |
1 |
5 |
COMMERCIAL |
12.84 |
2 |
1 |
6 |
COMMERCIAL |
12.99 |
1 |
1 |
7 |
COMMERCIAL |
13.08 |
3 |
3 |
8 |
COMMERCIAL |
13.17 |
3 |
3 |
9 |
COMMERCIAL |
13.77 |
1 |
1 |
10 |
COMMERCIAL |
14.66 |
1 |
0 |
11 |
COMMERCIAL |
14.51 |
1 |
1 |
12 |
COMMERCIAL |
17.14 |
3 |
2 |
13 |
COMMERCIAL |
17.27 |
3 |
3 |
14 |
RESIDENTIAL |
45.47 |
1 |
1 |
15 |
RESIDENTIAL |
42.10 |
1 |
1 |
16 |
RESIDENTIAL |
40.91 |
7 |
3 |
17 |
RESIDENTIAL |
30.76 |
8 |
5 |
18 |
RESIDENTIAL |
29.41 |
3 |
3 |
19 |
RESIDENTIAL |
25.18 |
3 |
1 |
20 |
RESIDENTIAL |
30.34 |
3 |
2 |
21 |
RESIDENTIAL |
24.34 |
21 |
19 |
22 |
RESIDENTIAL |
29.86 |
21 |
15 |
23 |
COMMERCIAL |
10.59 |
3 |
3 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
20
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
5
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
32.5
|
|