MahaRERA Application

General Information

Other Than Individual

Organization

Om Builders and Developers
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

102
Guru Ganesh CHS LTD.
Mahatma Phule Cross road
Mulund East
Near C.D. Deshmukh Garden
MAHARASHTRA
Konkan
Mumbai Suburban
Kurla
Kurla
400081

Organization Contact Details

02221630837

Past Experience Details

Member Information

Member Name Designation Photo
Sachin Ashok Yadav Partner View Photo
Milind Ashok Yadav Authorized Signatory View Photo
Ashok Tukaram Yadav Partner View Photo

Project

ASHOKA HEIGHTS
On-Going Project
01/11/2020
30/12/2022
30/12/2023
No
Residential
Yes
635 637PT
9 metre wide road
CTS No 638 639 640 848
CTS No 633 631
CTS No 640
MAHARASHTRA
Konkan
Mumbai Suburban
Kurla
Kurla
NAHUR VILLAGE ROAD
MULUND WEST
400080
2117.81
1
1
0
573.39

FSI Details

9290.23
0
9290.23

Bank Details

AXIS BANK
UTIB0001622

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 90 40 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 Shall be done prior to OC
Water Conservation, Rain water Harvesting : YES 0 Shall be done prior to OC
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 60 Shall be done prior to OC
Electrical Meter Room, Sub-Station, Receiving Station : YES 80 Shall be done prior to OC
Fitness Centre : YES 0 Shall be done prior to OC
Society office : YES 0 Shall be done prior to OC
Aggregate area of recreational Open Space : YES 0 Shall be done prior to OC
Open Parking : YES 0 6
Water Supply : YES 0 Shall be done prior to OC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 Shall be done prior to OC
Storm Water Drains : YES 100 Shall be done prior to OC
Landscaping & Tree Planting : YES 0 Shall be done prior to OC
Street Lighting : YES 100 Shall be done prior to OC
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 Shall be done prior to OC
Solid Waste Management And Disposal : YES 0 Shall be done prior to OC

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 ASHOKA HEIGHTS A and B WING 30/12/2023 0 1 0 24 1 6 90
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 54.46 22 15
2 2 BHK 55.86 23 18
3 2 BHK 56.13 44 30
4 1BHK 35.78 44 36
5 1BHK 36.15 41 34
6 1 BHK 36.87 21 20
7 1 BHK 38.2 23 14
8 Shop 29.54 1 0
9 Shop 18.58 1 0
10 Shop 13.38 1 0
11 Shop 25.08 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 90
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Sudhakar S Ingavale NA Other Professional
SHREE ASSOCIATES NA Architect
CA Esha Bhanushali NA Chartered Accountant
Mera RERA NA Other Professional
Vinayak Chopdekar & Associates NA Engineer

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 a Details of encumbrances concerned to Finance
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
5 Commencement Certificates / NA Order for plotted development
6 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
2 Declaration in FORM B
3 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
2 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
3 Other
4 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC006000000000119 Anthony Ashwin Peter View Orders
2 CC006000000000207 Dipak Annapa Patil View Orders
3 CC006000000000974 Ankit Pankaj Panchal View Orders
4 CC006000000057891 SUNIL VISHNU KUBAL View Orders
5 CC006000000057093 Kundip Sunderji Thakker View Orders