MahaRERA Application

General Information

Other Than Individual

Organization

Natu Paranjape Realtors
Others
Association of Persons
Do you have any Past Experience ?
No

Address Details

601 / 701
9 MANSI
Ram Maruti Road, Cross Lane No. 1
Naupada
Behind Lokmanya Tilak Udyan
MAHARASHTRA
Konkan
Thane
Thane
Thane (M Corp.)
400602

Organization Contact Details

02225394545
www.natuparanjape.com

Past Experience Details

Other Organization Type Member Information

Name Member Type
Madhav Kashinath Natu Others
Chandrashekhar Prabhakar Paranjape Others
Makarand Yashwant Paranjape Others
Sachin Mukund Natu Others
Sameer Mukund Natu Others
Manisha Madhav Natu Others

Project

9RIVIERA HILLS
On-Going Project
31/12/2018
31/03/2019
30/10/2020
No
Residential
No
PART OF NEW C.S. NO.194-C
PARTLY BY CS NO 187 AND PARTLY BY CS NO 188
BY CS NO 193
PARTLY BY MUMBAI PUNE RD AND PARTLY BY CS NO 194B
BY CS NO 283 CENTRAL RAILWAY LINE
MAHARASHTRA
Konkan
Thane
Thane
Thane (M Corp.)
400605
5551.00
1
1
0
1963.85

FSI Details

11243.21
0
11243.21

Bank Details

HDFC BANK LIMITED
HDFC0000488

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 193 125 30

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 SHALL BE DONE PRIOR TO OC
Water Conservation, Rain water Harvesting : YES 0 SHALL BE DONE PRIOR TO OC AS PER TMC CC NORMS
Energy management : YES 0 POWER SUPPLY BY MSEDCL
Fire Protection And Fire Safety Requirements : YES 15 AS PER CFO NOC
Electrical Meter Room, Sub-Station, Receiving Station : YES 40 SHALL BE DONE PRIOR TO OC AS PER MSEDCL NORMS
GYMNASIUM : YES 70 126SQ.MTR AREA ON 20TH FLOOR - SANCTIONED PLAN
MULTIPURPOSE HALL : YES 0 GROUND+1PART - 150.57 SQ.MTR AREA IN RG1
SWIMMING POOL WITHOUT LIFE GUARD : YES 60 LESS THAN 4FEET DEPTH POOL ON 22ND FLOOR
Aggregate area of recreational Open Space : YES 0 GROUND / PAVED / ABOVE PARKING
Open Parking : NO 0 NA
Water Supply : YES 35 WATER CONNECTION WILL BE DONE AFTER OC BY TMC.
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 SHALL BE DONE PRIOR TO OC IF REQUIRED AS PER CC
Storm Water Drains : YES 30 SHALL BE DONE PRIOR TO OC AS PER SWD REMARKS
Landscaping & Tree Planting : YES 10 ON GROUND AND RG
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 9RIVIERA HILLS 9 RIVIERA HILLS 0 1 0 28 1 0 193
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 RK 26.66 1 0
2 1 BHK 45.81 27 16
3 1 BHK 49.51 17 12
4 1 BHK 49.14 2 2
5 1 HALF BHK 58.88 2 2
6 2 BHK 64.86 16 10
7 2 HALF BHK 80.28 16 13
8 3 BHK 79.18 2 1
9 3 HALF BHK 101.03 24 17
10 3 HALF BHK 121.57 1 0
11 1 BHK 46.31 26 21
12 1 BHK 45.56 22 14
13 2 BHK 64.20 24 17
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 95
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 70
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

80
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 23
11 Overall Percentage of Completion of the work done For the entire Building /Wing 68.8

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
ASSOCIATE ENGINEERS NA Contractor
SUMEDHA GORE NA Architect
ANIRUDDHA NAKHAWA NA Engineer

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
4 Copy of Layout Approval (in case of layout)
5 Copy of Layout Approval (in case of layout)
6 Copy of Layout Approval (in case of layout)
7 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement