MahaRERA Application

General Information

Other Than Individual

Organization

Oberoi Realty Limited
Company
NA
Do you have any Past Experience ?
Yes

Address Details

3rd Floor
Commerz
Off Western Express Highway
Goregaon East
International Business Park, Oberoi Garden City
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Borivali
400063

Organization Contact Details

02266773333
www.oberoirealty.com

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Exquisite by Oberoi RealtyResidentialNA3116.79Exquisite Oberoi Garden City Off Western Express Highway Goregaon East Mumbai 400 063590/A/A/A/1 pt of Village Pahadi Goregaon38022014-12-312015-05-11
2Priviera by Oberoi RealtyResidentialNA264.80Priviera Junction of Sarojini Road and Main Avenue Road Santacruz West Mumbai Maharashtra 400 054415/B/1 of Village Bandra West Mumbai1122015-05-022015-05-02
3Commerz 2CommercialNA1790.30Commerz 2 International Business Park Oberoi Garden City Off Western Express Highway Goregaon East Mumbai 400 06395/4/B/3 of Village Dindoshi102013-12-312013-12-31

Member Information

Member Name Designation Photo
Rajendra Chandorkar Authorized Signatory View Photo
Saumil Daru Authorized Signatory View Photo

Project

Esquire
On-Going Project
31/12/2017
30/06/2018
Yes
Residential
No
590/A/A/1 pt of Village Pahadi Goregaon
590 A A 1 pt of Village Pahadi Goregaon
590 A A 1 pt of Village Pahadi Goregaon
590 A A 1 pt of Village Pahadi Goregaon
590 A A 1 pt of Village Pahadi Goregaon
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Borivali
Off Western Express Highway
Goregaon
400063
3306.78
3
3
0
0

FSI Details

141199.01
8801
150000.01

Bank Details

Axis Bank Limited
UTIB0000373

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) NA NA 0
Covered Parking ( In Numbers) 2756 NA 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 Will be provided
Water Conservation, Rain water Harvesting : YES 100 Will be provided
Energy management : YES 100 Will be provided
Fire Protection And Fire Safety Requirements : YES 100 Will be provided
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 Will be provided as necessary
Prop Public Parking to be handed over to MCGM at any location in LargerProperty incl under RE Proj : YES 0 To be handed over to MCGM
Aggregate area of recreational Open Space : YES 100 To be provided as per provisions of DCR
Open Parking : NO 0 NA
Water Supply : YES 100 Will be provided
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 Will be provided
Storm Water Drains : YES 100 Will be provided
Landscaping & Tree Planting : YES 100 Will be provided
Street Lighting : YES 100 Will be provided
Community Buildings : YES 100 Clubhouse proposed to be provided
Treatment And Disposal Of Sewage And Sullage Water : YES 100 Will be provided
Solid Waste Management And Disposal : YES 100 Will be provided

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Esquire Tower A 30/06/2018 3 1 5 59 3 0 925
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK Superior Zone 1 127.01 210 171
2 3BHK Superior Zone 2 138.57 86 17
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Esquire Tower B 30/06/2018 3 1 6 59 2 0 919
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 4BHK Royale Zone 1 190.77 82 79
2 3BHK Superior Zone 2 138.57 56 4
3 3BHK Superior Zone 1 127.01 136 106
4 4BHK Royale Zone 2 192.11 20 20
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 Esquire Tower C 30/06/2018 3 1 6 59 1 0 912
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK Superior Zone 1 127.01 139 119
2 3BHK Superior Zone 2 138.57 58 9
3 3BHK Supreme Zone 2 138.99 28 17
4 3BHK Supreme Zone 1 127.43 67 67
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Architect Shashank Kokil NA Architect
Leslie E. Robertson Associates Consulting Engineers (India) Pvt Ltd NA Engineer
Larsen & Toubro Limited (Civil Contractor) NA Contractor
Neilsoft Limited (MEP Consultant) NA Other Professional
Delta Electro Mechanical Pvt.Ltd. (MEP and Fire Fighting Contractor) NA Other Professional
Rowan Williams Davies & Irwin, Inc. (Wind Tunnel Consultant) NA Other Professional
David Blackwood Murray Studio DBM (Landscape Consultant) NA Other Professional
Meinhardt Façade Technology (S) Pte Ltd (Facade Consultant) NA Other Professional
Walker Parking Consultants (Traffic Consultant) NA Other Professional
Fortune Consultants Ltd. (FCL) (Vertical Transport Consultant) NA Other Professional
Langan Engineering and Environmental Services (Geotechnical Consultant) NA Other Professional
En3 Sustainability Solutions Pvt. Ltd. (LEED Consultant) NA Other Professional
Schindler India Private Limited (Elevator Contractor) NA Other Professional
Doors & Doors System (I) Pvt.Ltd. (Windows Contractor Tower A) NA Other Professional
Belgium Aluminium & Glass Industries (Windows Contractor Tower B) NA Other Professional
R.K. Facade Pvt. Ltd. (Windows Contractor Tower C) NA Other Professional
A.A. Nayak Constructions Pvt. Ltd. (Waterproofing Contractor) NA Other Professional
Larsen & Toubro (Waterproofing Contractor) NA Other Professional
PERFECT PROPERTIES & CONSULTANCY A51800004556 Real Estate Agent
KANCHAN DIWAN A51900010969 Real Estate Agent
Archana Sanjay Joshi A51800007568 Real Estate Agent
SHARMA REALTOR A51800007870 Real Estate Agent
RAJESH NAVINCHANDRA DOSHI A51800000103 Real Estate Agent
Akshay Joysher A51800005261 Real Estate Agent
MITESH ATMARAM CHANDGOTHIA A51800002536 Real Estate Agent
RUPIYAA.COM A51800002924 Real Estate Agent
SAVANI REALTY A51800004860 Real Estate Agent
VD Realty A51800003227 Real Estate Agent
Janki Properties A51800001308 Real Estate Agent
nilesh Devraj mishra A51800012329 Real Estate Agent
OPENMINDS A51800009280 Real Estate Agent
Rahul Bramhdev Singh A51800011778 Real Estate Agent
Vijay Ramesh Bajaj A51800008521 Real Estate Agent
AMIT RAJARAM SAKRE A51900009018 Real Estate Agent
SUDHIR P DOSHI A51800003212 Real Estate Agent
AMIT KISHOR WAGHELA A51800009452 Real Estate Agent
ASHIRWAD PAREEK A51800003996 Real Estate Agent
Varun Shivkumar Narsaria A51800005902 Real Estate Agent
invest plant A51900008517 Real Estate Agent
CBRE South Asia Private Limited A51600003050 Real Estate Agent
K RAVINDRAN VATKAI POONATH SUKUMARAN NAYAR NAIR A51900010073 Real Estate Agent
MITESH ATMARAM CHANDGOTHIA A51800002536 Real Estate Agent
Shafiq Zinat Ali Qureshi A51800011528 Real Estate Agent
Gurneet Singh Anand A51800012035 Real Estate Agent
Rise And Above Properties A51800000115 Real Estate Agent
ACCORD ESTATE CONSULTANT A51800006995 Real Estate Agent
HARIOM CHHAGANLAL JAIPURIA A51800001384 Real Estate Agent
Pawankumar Bairagra A51800000313 Real Estate Agent

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
Esquire National Consumer Dispute Redressal Commission New Delhi 693 Civil No Other Complaint 2017 Pending
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
2 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
2 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Certificates of Architect (Form 4)
2 Certificates of Architect (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC006000000012043 GANGOTRI MERCHANTS PRIVATE LIMITED View Orders