MahaRERA Application

General Information

Individual

Individual

Ninath
Bhausaheb
Shingade
Bhausaheb N Shingade
No

Address For Official Communication

905-908
Shelton Cubix
Plot no-87,
CBD Belapur
Sector-15
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
400614

Contact Details

02249700789
konnark.com

Past Experience Details

Project

Konnark Gardens
On-Going Project
20/05/2021
20/11/2021
No
Residential
No
26/5
Gat no-24
Gat no- 5-9 And 5-11
Gat no-26-2
Gat no-20 And 22
MAHARASHTRA
Konkan
Raigarh
Panvel
Chindharan
Chindran
Chindran
410206
13040.40
7
7
0
1304.40

FSI Details

2429.34
8768.68
11198.02

Bank Details

IDBI Bank
IBKL0000183

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 0 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 Work under progress
Water Conservation, Rain water Harvesting : YES 0 Work under progress
Energy management : YES 0 Work under progress
Fire Protection And Fire Safety Requirements : NO 0 NA
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 Work under progress
Aggregate area of recreational Open Space : YES 0 NA
Open Parking : NO 0 NA
Water Supply : YES 0 Regularized after OC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 Work under progress
Storm Water Drains : YES 0 Work under progress
Landscaping & Tree Planting : YES 0 Tree will be provided as per RERA
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 Work under progress
Solid Waste Management And Disposal : YES 0 Work under progress

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 Konnark Gardens 1 20/05/2021 0 1 0 4 1 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop 6.93 3 0
2 Shop 7.39 1 0
3 Shop 9.13 1 0
4 Shop 9.86 1 0
5 Shop 9.9 3 0
6 Shop 9.93 3 0
7 1BHK 26.56 33 32
8 1BHK 28.17 10 9
9 1BHK 28.80 1 1
10 2BHK 38.64 3 3
11 2BHK 39.19 3 3
12 2BHK 40.51 1 1
13 2BHK 40.99 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 1
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 95
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

95
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 10
11 Overall Percentage of Completion of the work done For the entire Building /Wing 65.1
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 Konnark Gardens 2 20/05/2021 0 1 0 5 1 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 26.56 18 18
2 1BHK 27.64 18 18
3 1BHK 27.84 1 1
4 1BHK 28.17 5 5
5 1BHK 29.26 6 5
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 95
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

95
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 74
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 Konnark Gardens 3 20/05/2021 0 1 0 5 1 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 27.84 1 1
2 1BHK 28.17 5 4
3 1BHK 29.26 6 6
4 1BHK 26.56 17 17
5 1BHK 26.64 1 1
6 1BHK 27.64 18 18
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 95
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

95
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 74
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
4 Konnark Gardens 4 20/05/2021 0 1 0 5 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 26.56 24 24
2 1BHK 28.17 8 8
3 Shop 7.3 2 0
4 Shop 9.9 2 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 95
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

95
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 74
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
5 Konnark Gardens 5 20/05/2021 0 1 0 5 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop 9.93 4 0
2 1BHK 26.56 24 24
3 1BHK 28.17 8 8
4 Shop 6.93 4 0
5 Shop 9.9 4 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 95
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

95
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 74
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
6 Konnark Gardens 6 20/05/2021 0 1 0 5 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1RK 19.96 1 1
2 1RK 19.97 2 2
3 1BHK 26.56 18 15
4 1BHK 26.60 3 3
5 1BHK 27.34 6 6
6 1BHK 27.41 1 0
7 1BHK 27.64 6 6
8 1BHK 28.09 1 0
9 1BHK 28.17 4 0
10 1BHK 28.42 1 0
11 1BHK 28.96 2 0
12 1BHK 29.24 1 0
13 1BHK 29.26 1 0
14 2BHK 38.02 3 3
15 2BHK 44.17 1 1
16 2BHK 49.95 1 1
17 Shop 6.81 1 0
18 Shop 7.02 1 0
19 Shop 8.4 1 0
20 Shop 9.16 1 0
21 Shop 9.76 1 0
22 Shop 9.87 1 0
23 Shop 9.93 4 0
24 Shop 6.93 2 0
25 Shop 9.9 4 0
26 1BHK 43.56 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 95
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

95
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 74
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
7 Konnark Gardens 7 20/05/2021 0 1 0 5 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1RK 18.38 3 3
2 1RK 19.22 1 0
3 1BHK 26.56 18 16
4 1BHK 27.26 2 0
5 1BHK 27.59 1 0
6 1BHK 30.06 1 1
7 1BHK 34.26 1 1
8 2BHK 38.64 3 2
9 2BHK 39.85 3 3
10 2BHK 40.40 1 0
11 2BHK 41.17 2 2
12 2BHK 43.08 1 1
13 2BHK 49.95 1 1
14 1BHK 39.43 1 1
15 1BHK 45.2 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 95
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

95
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 74

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Anarch NA Architect
Vinit Consultants NA Engineer
Jadhav & Company NA Chartered Accountant

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Details of encumbrances
Details of encumbrances
Details of encumbrances
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other
Other