MahaRERA Application

General Information

Other Than Individual

Organization

Chaitanya Enterprises
Partnership
NA
Do you have any Past Experience ?
No

Address Details

Radhakunj Bungalow
Maryland Complex
I C Colony
Borivali West
Near Union Bank
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Borivali
400103

Organization Contact Details

02228951392
www.chaitanyagroup.co.in

Past Experience Details

Member Information

Member Name Designation Photo
Rahul S Wadikar Partner View Photo
Radhakrishna S Desai Partner View Photo
Jayesh V Mantri Partner View Photo
Amith P Puthran Partner View Photo
Prashant B Pawar Partner View Photo

Project

Chaitanya Om Shivam - Om Shivam Premises CSL
New Project
31/05/2024
31/08/2024
No
Others
Yes
680A/1/ 8
FP NO 680A-1-3
ACCESS ROAD
DP ROAD
680A-1-1
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Borivali
Shimpoli Road
Borivali West
400092
1328.64
1
1
0
0

FSI Details

3945
0
3945.00

Details of RERA Designated Separate Bank Account

HDFC BANK
HDFC0000410

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Chaitanya Om Shivam - Om Shivam Premises CSL Ms. Bhavana Mankad Societies Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Upload Agreement / MoU Copy
4 Upload Agreement / MoU Copy
5 Declaration in Form B
6 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 76 76 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 100 Will Be Provided
Energy management : YES 100 Will Be Provided
Fire Protection And Fire Safety Requirements : YES 100 Will Be Provided
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 Will Be Provided
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 100 Will Be Provided
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 Will Be Provided
Storm Water Drains : YES 100 Will Be Provided
Landscaping & Tree Planting : YES 100 Will Be Provided
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 100 Will Be Provided
Solid Waste Management And Disposal : YES 100 Will Be Provided

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Chaitanya Om Shivam - Om Shivam Premises CSL Chaitanya Om Shivam 31/05/2024 0 1 1 18 1 0 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 70.15 1 1
2 3BHK 65.16 1 0
3 Shop 25.82 1 1
4 Shop 25.82 1 1
5 Shop 20.25 1 1
6 Shop 21.87 1 1
7 Shop 41.45 1 1
8 Shop 44.45 1 1
9 1BHK 35.51 12 8
10 2BHK 44.85 14 10
11 2BHK 53.78 3 2
12 Shop 28.08 2 2
13 2BHK 56.89 11 9
14 2BHK 54.47 2 0
15 Shop 22.35 1 1
16 2BHK 63.80 1 1
17 3BHK 68.82 1 1
18 3BHK 69.12 6 6
19 3BHK 73.20 9 7
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Rasik P Hingoo Associates NA Architect
Haresh Dhaduk NA Chartered Accountant
Chakor Raul NA Engineer

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
2 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
8 Architect’s Certificate of Percentage of Completion of Work (Form 1)
9 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
7 Engineer’s Certificate on Cost Incurred on Project (Form 2)
8 Engineer’s Certificate on Cost Incurred on Project (Form 2)
9 Engineer’s Certificate on Cost Incurred on Project (Form 2)
10 Engineer’s Certificate on Cost Incurred on Project (Form 2)
11 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement
1 Other – Legal
1 Other – Finance
1 Other – Technical