MahaRERA Application

General Information

Other Than Individual

Organization

ROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED
Company
NA
Do you have any Past Experience ?
Yes

Address Details

CTS NO. 2254
1 MODI BAUG, COMMERCIAL BUILDING
GANESHKHIND ROAD
SHIVAJI NAGAR
NEAR AGRICULTURE COLLEGE
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411016

Organization Contact Details

02071017101
www.rohanbuilders.com

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Rohan Kritika D E K WingsResidentialNA3619S NO 117 A 1 117 B PARVATI PUNE 411009538A3942017-06-302017-04-28
2Rohan Kritika F G H I J WingResidentialNA7008S NO 117 A1 117 B PARVATI PUNE 411009CTS 538 A51872016-06-302017-03-30
3ROHAN LEHER 2 WINGS K L M N OResidentialNA1520BANER PUNE 411045S NO 53/5 ,53/6 ,54/1 ,54/12 BANER5502016-12-312017-03-31

Member Information

Member Name Designation Photo
SANJAY LUNKAD Authorized Signatory View Photo

Project

ROHAN ANANTA PHASE II
New Project
30/09/2024
Yes
Residential
No
S NO 125/1/B/1, 125/1/B/2, 125/2/1, 125/2/2
24 MTR WIDE ROAD
PHASE I WING A5
S NO 125 PART
S NO 124
MAHARASHTRA
Pune
Pune
Mulshi
Tathwade
Mumbai Bengaluru Bypass
Tathawade
411033
2293.08
4
4
0
0

FSI Details

10448.48
9666.11
20114.59

Bank Details

AXIS BANK LIMITED
UTIB0000037

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 297 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 ENTIRE PROJECT
Water Conservation, Rain water Harvesting : YES 0 As per sanction plan
Energy management : YES 0 ENTIRE PROJECT
Fire Protection And Fire Safety Requirements : YES 0 As per provisional fire NOC
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 As per MSEDCL norms
Aggregate area of recreational Open Space : YES 0 ENTIRE PROJECT
Open Parking : YES 0 ENTIRE PROJECT
Water Supply : YES 0 PCMC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 ENTIRE PROJECT
Storm Water Drains : YES 0 ENTIRE PROJECT
Landscaping & Tree Planting : YES 0 ENTIRE PROJECT
Street Lighting : YES 0 ENTIRE PROJECT
Community Buildings : YES 0 ENTIRE PROJECT
Treatment And Disposal Of Sewage And Sullage Water : YES 0 STP
Solid Waste Management And Disposal : YES 0 OWC

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 ROHAN ANANTA PHASE II WING A1 31/03/2024 1 1 1 12 1 0 39
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 9.99 1 0
2 SHOP 12.92 2 0
3 SHOP 12.08 2 0
4 SHOP 19.54 6 0
5 2 BHK 46.80 9 0
6 2 BHK 48.00 11 0
7 2 BHK 48.24 10 0
8 2 BHK 54.19 6 0
9 2 BHK 49.44 11 0
10 2BHK 51.87 5 0
11 2 BHK 51.88 6 0
12 2BHK 52.73 5 0
13 2 BHK 52.84 10 0
14 2 BHK 53.09 6 0
15 2BHK 53.81 5 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 00
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
2 ROHAN ANANTA PHASE II WING A2 31/03/2024 1 1 1 12 0 0 66
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 56.57 5 0
2 2 BHK 56.58 17 0
3 2 BHK 45.08 10 0
4 2BHK 45.43 10 0
5 2 BHK 46.51 11 0
6 2BHK 46.86 5 0
7 2 BHK 46.87 5 0
8 2 BHK 55.15 5 0
9 2 BHK 55.16 6 0
10 2BHK 55.17 10 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 10
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
3 ROHAN ANANTA PHASE II WING A3 31/03/2024 1 1 1 12 0 13 99
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 45.15 1 1
2 2BHK 50.07 1 1
3 2BHK 56.51 3 3
4 2 BHK 45.12 4 4
5 2 BHK 45.13 3 3
6 2 BHK 45.48 4 4
7 2 BHK 45.49 2 2
8 2 BHK 45.54 4 4
9 2 BHK 45.88 1 1
10 2 BHK 46.56 8 8
11 2 BHK 46.66 4 4
12 2 BHK 46.92 4 4
13 2 BHK 46.93 3 3
14 2 BHK 47.32 2 2
15 2 BHK 55.01 6 6
16 2 BHK 55.02 9 9
17 2 BHK 55.04 3 3
18 2 BHK 55.05 3 3
19 2 BHK 56.43 11 11
20 2 BHK 56.49 3 3
21 2 BHK 56.53 4 4
22 2 BHK 58.38 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 15
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 31.5
Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
4 ROHAN ANANTA PHASE II WING A4 31/03/2024 1 1 1 12 0 16 93
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 55.15 1 1
2 2 BHK 46.31 11 11
3 2 BHK 46.47 4 4
4 2 BHK 46.68 2 2
5 2 BHK 56.57 4 4
6 2 BHK 56.65 1 1
7 2 BHK 56.66 1 1
8 2 BHK 44.88 10 10
9 2 BHK 45.24 10 10
10 2 BHK 46.67 4 4
11 2 BHK 55.16 2 2
12 2 BHK 55.17 14 14
13 2 BHK 55.20 4 4
14 2 BHK 56.58 8 8
15 2 BHK 56.68 8 8
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 25
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 32.5

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Ar Shashank P Phadke NA Architect

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
ROHAN ANANTA PHASE II Joint CJSD 1318/2018 Civil No Suit 2018 Suit filed by promoter Summons to defendant
NA

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other