MahaRERA Application

General Information

Other Than Individual

Organization

ABM ASSOCIATES
Partnership
NA
Do you have any Past Experience ?
No

Address Details

S NO 19/4
ABM HOMES
LANE NO 11
DHANORI
KAMAL PARK,OPP CANARA BANK
MAHARASHTRA
Pune
Pune
Haveli
DHANORI
411015

Organization Contact Details

09766795050

Past Experience Details

Member Information

Member Name Designation Photo
MANOJ AGARWAL Authorized Signatory View Photo
BALASAHEB BABAN TINGARE Partner View Photo
ANIL VASANTRAO TINGARE Partner View Photo

Project

ABM HOMES
On-Going Project
22/12/2017
30/03/2018
No
Residential
Yes
19/4
REMAINING LAND OF SAME SR NUMBER
20 FT INTERNAL ROAD ADJOINING TO DHANORI ROAD
LOTUS CO OP HOUSING SOCIETY
REMAINING LAND OF SAME SR NO
MAHARASHTRA
Pune
Pune
Haveli
DHANORI
411015
930.29
1
1
0
0

FSI Details

0
685.15
685.15

Bank Details

IDBI BANK
IBKL0000668

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
ABM HOMES DNYANESHWAR BABASAHEB TINGARE Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
ABM HOMES DNYANESHWAR BABASAHEB TINGARE Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
ABM HOMES ROHINI DANYESHWAR TINGARE Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
ABM HOMES ROHINI DANYESHWAR TINGARE Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 18 13 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 50 IN PROGRESS
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : NO 0 NA
Electrical Meter Room, Sub-Station, Receiving Station : YES 70 IN PROGRESS
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 60 IN PROGRESS
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 60 IN PROGRESS
Storm Water Drains : YES 50 IN PROGRESS
Landscaping & Tree Planting : YES 0 IN PROGRESS
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 50 IN PROGRESS
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 ABM HOMES BUILDING AB 30/03/2018 0 1 0 4 0 72 18
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 29.64 6 4
2 1 BHK 30.92 1 0
3 1BHK 31.12 1 0
4 1 BHK 33.97 2 1
5 1BHK 34.2 6 4
6 1 RK 21.66 2 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 70
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 70
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

60
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 60
11 Overall Percentage of Completion of the work done For the entire Building /Wing 60

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SUNIL MAHAJAN NA Architect

Litigations Details

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Certificates of Architect (Form 4)
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other