MahaRERA Application

General Information

Other Than Individual

Organization

PAGARANI UNIVERSAL INFRASTRUCTURE PVT. LTD.
Company
NA
Do you have any Past Experience ?
Yes

Address Details

Plot No 288
Universal Cubical
Haji Zahur Ahmed Qureshi
Jogeshwari (West)
Opp Universal Garden
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
400102

Organization Contact Details

02226782802

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Universal Garden-1ResidentialNA6912.15Plot No 288 B Amrit Nagar Jogeshwari West Mumbai 400102CTS 288 B11282014-03-312014-02-28
2Mashyak TowersResidentialNA7166.30CTS 978 979 Chincholi Bunder Road Malad West Mumbai 400064978, 97911012015-03-312014-08-14
3Universal Garden - IResidentialNA6912.15Plot No 288B Amrut Nagar Jogeshwari West Mumbai 400102CTS 288B11282014-03-312014-02-28

Member Information

Member Name Designation Photo
Narendra Narayan Pagarani Authorized Signatory View Photo
Narayan Jethanand Pagarani Managing Director View Photo

Project

Universal Cubical
On-Going Project
31/12/2017
31/12/2018
31/12/2019
Yes
Residential
No
CTS. 288A/292
CTS 110 of Village Goregaon
CTS 286 - 16 of Village Bandivali
D P Road CTS No 288 - B of Village Bandivali
Water Channel - Nallah
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
Amrut Nagar
Jogeshwari West
400102
10326.09
2
1
1
1204.34

FSI Details

19709.44
2510.74
22220.18

Bank Details

Central Bank of India
CBIN0283873

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 287 0 75

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 DP Road constructed with Storm Water Drain
Water Conservation, Rain water Harvesting : YES 95 Partly completed
Energy management : YES 50 Work in Progress
Fire Protection And Fire Safety Requirements : YES 90 Work in Progress
Electrical Meter Room, Sub-Station, Receiving Station : YES 90 Work in Progress
Aggregate area of recreational Open Space : YES 0 Not yet started
Open Parking : YES 0 Not yet started
Water Supply : YES 95 Water main laid with DP Road
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 95 Part sewerage line laid along DP Road + chambers
Storm Water Drains : YES 98 SWD alongwith DP Road & partly in plot completed
Landscaping & Tree Planting : YES 60 Work in progress
Street Lighting : YES 100 Payment made to MGCM
Community Buildings : YES 60 Not yet started
Treatment And Disposal Of Sewage And Sullage Water : YES 50 Not yet started
Solid Waste Management And Disposal : YES 25 Not yet started

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Universal Cubical Universal Cubical 31/12/2018 0 1 1 23 1 111 287
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 63.55 28 18
2 2 BHK 63.36 38 31
3 3 BHK 84.26 42 31
4 2 BHK 64.01 78 71
5 2 BHK 63.45 42 36
6 1 BHK 42.74 82 76
7 1 BHK 41.43 12 6
8 1 BHK 43.76 2 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 90
4 Stilt Floor 100
5 X number of Slabs of Super Structure 98
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 98
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 95
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 98
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

96
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 90
11 Overall Percentage of Completion of the work done For the entire Building /Wing 96.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Universal Cubical Proposed Bulding 1 0 1 0 0 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 45 90 0
2 2 BHK 65 150 0
3 3 BHK 85 40 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Mr Anil Kagutkar NA Architect
Kamlesh Bhatt A51800000446 Real Estate Agent
C B Patel NA Engineer
Hanif Yakub Zamindar A51800001585 Real Estate Agent
NAIMUDDIN IQBAL AHMED SIDDIQUE A51800005672 Real Estate Agent
Mohamed Umer Zaveri A51800003716 Real Estate Agent
RIYAZAHMED ABDULLAH BHAMLA A51800010614 Real Estate Agent
Salim Merchant A51800011801 Real Estate Agent
Abrar Abdul Razak Dhanani A51900006731 Real Estate Agent
SAMEER SHAUKAT KHANDWALA A51800013671 Real Estate Agent
MUNAF SIDDIK NATHANI A51800012364 Real Estate Agent
SHAUKAT YUSUF KHANDWALA A51800011974 Real Estate Agent
Manzer Anjum A51800008071 Real Estate Agent
FAISAL GHORI A51800016000 Real Estate Agent
Mohammed Akbar Mohmmed Sharif Khan A51800016458 Real Estate Agent
MOHAMMED ZAID RIYAZAHMED BHAMLA A51800016976 Real Estate Agent
Parveen salim Merchant A51800016839 Real Estate Agent
Gaurav Jogesh Mehra A51900007830 Real Estate Agent
Amrien Abrar Dhanani A51800017455 Real Estate Agent
SAEEDA ABDUL RAZAK DHANANI A51800017725 Real Estate Agent
MUSTAQUEEM AHMAD KHAN A51800005128 Real Estate Agent
SUMAIYA SHOEB PATEL A51800017962 Real Estate Agent
MOHAMMED SHOAIB SHADAB SHAIKH A51800011711 Real Estate Agent
PRAKASH KHUSHAL SOLANKI A51800003275 Real Estate Agent
MOHD JAVED KHAN A51800016879 Real Estate Agent
Shabbir Hussain Abdul Gaffar Dharodia Proprietor of Grace Properties A51800014133 Real Estate Agent
Mohamed Umer Mohamed Rafique Fruitwala A51800012794 Real Estate Agent

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
Universal Cubical High Court 936 Civil Yes Other Notice of Motion 2014 Pending
Universal Cubical High Court 28 Civil Yes Suit NA 2012 Pending
Universal Cubical City Civil Court 203666 Civil Yes Writ Petition NA 2016 Dismissed in Default

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 CERSAI details
1 Disclosure of sold/ booked inventory
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
2 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
3 Other
4 Other
5 Other
6 Other
7 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC006000000194140 MOHAMMED FAROOQUE KHOKAR View Orders
2 CC006000000194930 MARIAM SALIM VEHVARIA View Orders
3 CC006000000194928 MUDDASAR M SALIM VEHVARIA View Orders