MahaRERA Application

General Information

Other Than Individual

Organization

ASIAN VENTURES
Others
AOP
Do you have any Past Experience ?
No

Address Details

UNIT NO 1 GROUND FLOOR
NIRMAL CHS
DHOLE PATIL ROAD
DHOLE PATIL ROAD
NEAR AKSHAY COMPLEX
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411001

Organization Contact Details

Past Experience Details

Other Organization Type Member Information

Name Member Type
MEHERNOSH DARA BOBINMAKER Others
RAKESH SUBHASHCHANDRA KHURANA Others
RAHIV SUBHASHCHANDRA KHURANA Others
BRIJESH RAKESH KHURANA Others

Project

RIVA
On-Going Project
31/03/2019
30/09/2020
21/05/2026
No
Residential
Yes
SR NO 43 /3
SR NO 44
SR NO 43 HISSA NO 3
SR NO 40
SR NO 43 HISSA NO 3
MAHARASHTRA
Pune
Pune
Haveli
Pisoli
MAHARTASHTRA
PISOLI
411060
4000
1
1
0
400

FSI Details

5099.28
732
5831.28

Bank Details

BANK OF MAHARASHTRA
MAHB0000330

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
RIVA ASIAN VENTURES Others Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
RIVA AISAN VENTURES Others Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
RIVA ASIANVENTURES Others Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
RIVA RAJIV SUBHASHCHANDRA KHURANA Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 23 17 50

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 60 BBM AND CURB STONE
Water Conservation, Rain water Harvesting : YES 100 RAIN WATER HARVESTING
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 0 WILL BE DONE AFTER MAIN BUILDING STRUCTURE
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 WILL BE DONE AFTER MAIN BUILDING STRUCTURE
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : YES 24 WILL BE DONE AFTER MAIN BUILDING STRUCTURE
Water Supply : YES 50 TANKERS AND BOREWELL
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 40 RCC TANKS CASTED
Storm Water Drains : YES 50 RCC TANK CASTED
Landscaping & Tree Planting : YES 60 CURBSTONES AND COMPOUND WALLS
Street Lighting : YES 0 WILL BE DONE AFTER MAIN BUILDING STRUCTURE
Community Buildings : YES 80 RCC
Treatment And Disposal Of Sewage And Sullage Water : NO 0 BLOCK WORK.. ETC COMPLETED
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 RIVA RIVA 31/03/2020 1 1 0 13 1 24 23
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 95.23 3 0
2 3BHK 100.06 2 2
3 2BHK 67.82 1 1
4 2BHK 61.32 2 2
5 1BHK 42.55 7 4
6 1BHK 42.83 8 5
7 1BHK 45.06 5 4
8 1BHK 45.24 8 6
9 1BHK 47.57 4 0
10 1BHK 47.85 1 0
11 1BHK 49.98 6 2
12 2BHK 70.14 1 1
13 2BHK 73.77 7 6
14 2BHK 75.72 10 9
15 2BHK 79.34 4 0
16 2BHK 83.43 8 6
17 2BHK 87.05 8 5
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 95
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 90
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 85
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

85
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90.5

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
TAJ CONSTRCUTION NA Contractor
A DESIGN STUDIO NA Architect
DELCONS CONSULTANTS INDIA PVT LTD NA Engineer
YASHIDA CONSULTANTS NA Other Professional
AMIT INFRASTRUCTURECONSULTANTS NA Other Professional
Subhash Chandrakant Sonkamble A52100002477 Real Estate Agent
Shreekant Damodar Singhania A52100002942 Real Estate Agent
RICHARD SUBHASH HASNALY A52100003512 Real Estate Agent
ASHISH MODI A52100003744 Real Estate Agent
RUZBE DARUWALA A51800001872 Real Estate Agent
Charudatta Satish Lakhamade A52100001152 Real Estate Agent
VARUN DEVENDRA MATHURAWALA A52100001699 Real Estate Agent
Honaji Balasaheb Sanas A52100002585 Real Estate Agent
CHIRAG SHARAD SHAH A52100013950 Real Estate Agent
Gurmeet Kaur Saluja A52100005049 Real Estate Agent
ASIF ENTERPRISES NA Contractor
RATHOD ENTEPRISES NA Contractor
MUKESH BHAVSAR NA Contractor
RAMHIT CHOUHAN NA Contractor
Harikripa Elelctricals NA Contractor
PAWAN PARAS NAGPAL A52100022543 Real Estate Agent
P V Patadiya & Co NA Chartered Accountant

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
2 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 CERSAI details
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
4 Proforma of Allotment letter
5 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement