Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
1 |
PURANIK CITY SECTOR 2
|
HBC 1
|
01/07/2025
|
0
|
1
|
0
|
8
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
Shop |
11.84 |
1 |
0 |
2 |
Shop |
20.21 |
1 |
0 |
3 |
Shop |
19.51 |
1 |
0 |
4 |
Shop |
29.34 |
1 |
0 |
5 |
Shop |
27.14 |
1 |
0 |
6 |
Shop |
28.94 |
1 |
0 |
7 |
Shop |
22.98 |
1 |
0 |
8 |
2 BHK A |
43.92 |
3 |
3 |
9 |
2 BHK A1 |
43.92 |
1 |
1 |
10 |
2 BHK B |
43.89 |
8 |
4 |
11 |
2 BHK B1 |
43.89 |
1 |
0 |
12 |
2 BHK E |
40.63 |
3 |
1 |
13 |
2 BHK E1 |
40.63 |
1 |
1 |
14 |
2 BHK F |
43.92 |
3 |
3 |
15 |
2 BHK C |
43.82 |
4 |
3 |
16 |
2 BHK D |
40.59 |
5 |
4 |
17 |
2 BHK G |
43.89 |
6 |
6 |
18 |
2 BHK H |
43.82 |
3 |
3 |
19 |
2 BHK I |
40.59 |
3 |
2 |
20 |
2 BHK J |
40.63 |
3 |
3 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
40
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
7
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
25
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
7
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
37.9
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
2 |
PURANIK CITY SECTOR 2
|
HBC 2
|
01/07/2025
|
0
|
1
|
0
|
8
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
Shop |
11.84 |
1 |
0 |
2 |
Shop |
20.21 |
1 |
0 |
3 |
Shop |
19.51 |
1 |
0 |
4 |
Shop |
29.34 |
1 |
0 |
5 |
Shop |
27.14 |
1 |
0 |
6 |
Shop |
28.94 |
1 |
0 |
7 |
Shop |
22.98 |
1 |
0 |
8 |
2 BHK A |
43.92 |
3 |
3 |
9 |
2 BHK A1 |
43.92 |
1 |
1 |
10 |
2 BHK B |
43.89 |
8 |
5 |
11 |
2 BHK B1 |
43.89 |
1 |
0 |
12 |
2 BHK E1 |
40.63 |
1 |
0 |
13 |
2 BHK G |
43.89 |
6 |
6 |
14 |
2 BHK J |
40.63 |
3 |
3 |
15 |
2 BHK C |
43.82 |
4 |
4 |
16 |
2 BHK D |
40.59 |
5 |
5 |
17 |
2 BHK E |
40.63 |
3 |
3 |
18 |
2 BHK F |
43.92 |
3 |
3 |
19 |
2 BHK H |
43.82 |
3 |
2 |
20 |
2 BHK I |
40.59 |
3 |
3 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
75
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
6
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
7
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
28.8
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
3 |
PURANIK CITY SECTOR 2
|
JB 1
|
01/04/2025
|
0
|
1
|
0
|
8
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2 BHK B |
39.65 |
20 |
18 |
2 |
2 BHK E |
39.65 |
12 |
11 |
3 |
1 BHK A |
34.22 |
9 |
5 |
4 |
1 BHK C |
34.14 |
10 |
9 |
5 |
1 BHK D |
34.22 |
6 |
4 |
6 |
1 BHK F |
34.14 |
6 |
4 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
40
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
10
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
7
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
35.7
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
4 |
PURANIK CITY SECTOR 2
|
JB 2
|
01/04/2025
|
0
|
1
|
0
|
8
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1 BHK A |
34.23 |
9 |
3 |
2 |
1 BHK C |
34.15 |
10 |
9 |
3 |
1 BHK F |
34.15 |
6 |
2 |
4 |
2 BHK B |
39.65 |
20 |
14 |
5 |
1 BHK D |
34.23 |
6 |
5 |
6 |
2 BHK E |
39.65 |
12 |
12 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
11
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
10
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
00
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
7
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
32.8
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
5 |
PURANIK CITY SECTOR 2
|
LB 1
|
01/07/2025
|
0
|
1
|
0
|
8
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1 BHK H |
30.07 |
3 |
3 |
2 |
1 RK D |
19.87 |
8 |
7 |
3 |
1 RK E |
19.83 |
8 |
2 |
4 |
1 BHK F |
30.07 |
3 |
3 |
5 |
1 BHK G |
30.04 |
6 |
5 |
6 |
1 BHK A |
30.07 |
10 |
8 |
7 |
1 BHK B |
30.04 |
10 |
6 |
8 |
1 RK C |
19.88 |
15 |
11 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
20
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
7
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
32.7
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
6 |
PURANIK CITY SECTOR 2
|
KB
|
01/04/2025
|
0
|
1
|
0
|
8
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1 BHK E |
30.04 |
5 |
5 |
2 |
1 BHK D |
29.92 |
5 |
5 |
3 |
1 BHK F |
30.07 |
5 |
4 |
4 |
2 BHK H |
38.90 |
3 |
3 |
5 |
2 BHK I |
38.93 |
3 |
2 |
6 |
1 BHK J |
29.92 |
3 |
2 |
7 |
1 BHK K |
30.04 |
3 |
2 |
8 |
2 BHK B |
38.90 |
5 |
4 |
9 |
1 BHK A |
29.94 |
4 |
2 |
10 |
1 BHK G |
29.94 |
3 |
3 |
11 |
1 BHK L |
30.07 |
3 |
2 |
12 |
2 BHK C |
38.93 |
5 |
3 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
40
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
12
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
25
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
7
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
38.4
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
7 |
PURANIK CITY SECTOR 2
|
PB 1
|
01/04/2025
|
0
|
1
|
0
|
8
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1 BHK A |
30.62 |
9 |
7 |
2 |
1 BHK B |
34.23 |
20 |
11 |
3 |
1 BHK C |
30.61 |
10 |
8 |
4 |
1 BHK D |
30.62 |
6 |
6 |
5 |
1 BHK E |
34.23 |
12 |
6 |
6 |
1 BHK F |
30.61 |
6 |
4 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
50
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
7
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
25.7
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
8 |
PURANIK CITY SECTOR 2
|
PB 2
|
01/07/2025
|
0
|
1
|
0
|
8
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1 BHK B |
34.23 |
20 |
6 |
2 |
1 BHK F |
30.61 |
6 |
6 |
3 |
1 BHK A |
30.62 |
9 |
8 |
4 |
1 BHK C |
30.61 |
10 |
7 |
5 |
1 BHK D |
30.62 |
6 |
4 |
6 |
1 BHK E |
34.23 |
12 |
8 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
23
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
7
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
33
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
9 |
PURANIK CITY SECTOR 2
|
LB 2
|
01/07/2027
|
0
|
1
|
0
|
8
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1 BHK A |
30.07 |
10 |
0 |
2 |
1 BHK B |
30.04 |
10 |
0 |
3 |
1 RK C |
19.87 |
15 |
0 |
4 |
1 RK D |
19.87 |
8 |
0 |
5 |
1 RK E |
19.83 |
8 |
0 |
6 |
1 BHK F |
30.07 |
3 |
0 |
7 |
1 BHK G |
30.04 |
6 |
0 |
8 |
1 BHK H |
30.07 |
3 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
0
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
10 |
PURANIK CITY SECTOR 2
|
MA
|
01/07/2027
|
0
|
1
|
0
|
5
|
0 |
0 |
0 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1 RK A |
19.87 |
4 |
0 |
2 |
1 RK B |
19.90 |
10 |
0 |
3 |
1 RK C |
19.83 |
5 |
0 |
4 |
1 BHK D |
30.08 |
5 |
0 |
5 |
1 BHK E |
30.06 |
5 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
0
|
2
|
X number of Basement(s) and Plinth
|
0
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
0
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
0
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
0
|
|