MahaRERA Application

General Information

Other Than Individual

Organization

SHRI GANESH DEVELOPERS
Partnership
NA
Do you have any Past Experience ?
No

Address Details

SHOP NO 9
PUSHPMINA CHS
PLOT NO 30,SECTOR 10
KAMOTHE
KAMOTHE
MAHARASHTRA
Konkan
Raigarh
Panvel
Kamothe
410209

Organization Contact Details

02227455592

Past Experience Details

Member Information

Member Name Designation Photo
SANJAY PATIL Authorized Signatory View Photo
RAMDAS GOWARI Partner View Photo

Project

SIDDHIVINAYAK AARAMBH
New Project
23/01/2023
No
Residential
Yes
66
PLOT 64 AND 65
15 MTR ROAD
9 MTR ROAD
PLOT NO 67
MAHARASHTRA
Konkan
Raigarh
Panvel
Panvel
PLOT NO 66 SECTOR R5, R AND R, POCKET NO 1
PUSHPAK NODE
410206
699.95
1
1
0
0

FSI Details

1045.35
00
1045.35

Bank Details

BANK OF INDIA
BKID0000142

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
SIDDHIVINAYAK AARAMBH MINNATH CHANDRAKANT PATIL Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
SIDDHIVINAYAK AARAMBH NILESH CHANDRAKANT PATIL Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
SIDDHIVINAYAK AARAMBH POOJA MINNATH PATIL Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
SIDDHIVINAYAK AARAMBH YOGESH CHANDRAKANT PATIL Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 11 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 100 PROJECT COMPLETE
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 100 PROJECT COMPLETE
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 PROJECT COMPLETE
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 100 PROJECT COMPLETE
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 PROJECT COMPLETE
Storm Water Drains : NO 0 NA
Landscaping & Tree Planting : YES 100 PROJECT COMPLETE
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 SIDDHIVINAYAK AARAMBH SIDDHIVINAYAK AARAMBH 23/01/2022 0 1 0 7 0 2 11
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 21.862 1 0
2 SHOP 14.240 1 0
3 SHOP 13.784 1 0
4 SHOP 15.248 1 0
5 SHOP 14.830 1 0
6 SHOP 14.855 1 0
7 RES1BHK 17.026 1 0
8 1BHK 19.057 1 0
9 1RK 15.130 1 0
10 1RK 18.930 1 0
11 1RK 19.210 5 0
12 1BHK 19.355 1 0
13 1BHK 20.766 4 0
14 1BHK 20.993 1 0
15 1BHK 22.929 1 0
16 1BHK 23.330 5 0
17 1BHK 23.725 1 0
18 1BHK 23.752 2 0
19 1BHK 26.455 4 0
20 1BHK 27.466 2 0
21 1BHK 51.428 3 0
22 SHOP 25.388 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
ATUL PATEL ARCHITECHTS NA Architect

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Proforma of Allotment letter
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement