MahaRERA Application

General Information

Other Than Individual

Organization

SIGMA VENTURES
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

601, SOUTH BLOCK
SACRED WORLD MALL
JAGTAP ROAD
WANOWRI
JAGTAP CHOWK
MAHARASHTRA
Pune
Pune
Haveli
wanwadi
411040

Organization Contact Details

02042700588

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1SIGMA BLOSSOMOthersResidential & commercial1200hadapsar pune42A/1B/142242017-01-012017-01-01
2SIGMA CENTURIAResidentialNA4300Sr no 204 FURSUNGI204/4,5,6,71702018-08-182018-08-19

Member Information

Member Name Designation Photo
PRASHANT SHASHIKANT PUNEKAR Partner View Photo
RAJESH EKNATH TUPE Partner View Photo
ROHAN VASANT NAVALE Partner View Photo

Project

SIGMA AVENTINO
New Project
30/12/2024
No
Others
Yes
46/2
46
46
47
road
MAHARASHTRA
Pune
Pune
Haveli
MOHAMMADWADI
jarande nagar road
jarande lawns
411060
4300
1
1
0
395.85

FSI Details

4354.34
6531.50
10885.84

Bank Details

The SVC co operative bank LTD
SVCB0000109

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
SIGMA AVENTINO RAJENDRA RAMBHAU JARANDE Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 109 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 In progress
Water Conservation, Rain water Harvesting : YES 0 In progress
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 0 In progress
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 In progress
Aggregate area of recreational Open Space : YES 0 In progress
Open Parking : YES 0 In progress
Water Supply : YES 10 In progress
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 In progress
Storm Water Drains : YES 50 In progress
Landscaping & Tree Planting : YES 0 In progress
Street Lighting : YES 0 In progress
Community Buildings : YES 0 In progress
Treatment And Disposal Of Sewage And Sullage Water : YES 0 In progress
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 SIGMA AVENTINO SIGMA AVENTINO 30/12/2024 1 1 0 16 0 9 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop 24.5 1 0
2 Shop 24.55 1 1
3 Shop 24.58 1 1
4 Shop 24.6 1 0
5 2BHK 60.82 48 24
6 Shop 20.53 3 0
7 Shop 23.51 2 1
8 2BHK 62.94 16 10
9 2BHK 66.84 16 13
10 2.5BHK 62.95 16 8
11 2.5BHK 78.4 16 8
12 2BHK 78.78 16 12
13 Shop 34.5 1 0
14 Shop 34.74 1 0
15 Shop 34.79 2 1
16 Shop 36.93 1 0
17 Shop 37.03 1 1
18 Shop 20.11 1 1
19 Shop 20.24 2 0
20 Shop 20.39 2 2
21 Shop 20.48 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 80
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 65
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 40
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 65
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

55
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 30
11 Overall Percentage of Completion of the work done For the entire Building /Wing 73.5

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SWAPNIL KSHIRSAGAR NA Architect
VIVEK PARADKAR NA Chartered Accountant
SIDDHI CONSTRUCTION NA Contractor
ATUL SAKHARE NA Engineer

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
3 Building Plan Approval / NA Order for plotted development
4 Building Plan Approval / NA Order for plotted development
5 Building Plan Approval / NA Order for plotted development
6 Building Plan Approval / NA Order for plotted development
7 Building Plan Approval / NA Order for plotted development
8 Building Plan Approval / NA Order for plotted development
9 Building Plan Approval / NA Order for plotted development
10 Building Plan Approval / NA Order for plotted development
11 Building Plan Approval / NA Order for plotted development
12 Building Plan Approval / NA Order for plotted development
13 Building Plan Approval / NA Order for plotted development
14 Building Plan Approval / NA Order for plotted development
15 Building Plan Approval / NA Order for plotted development
16 Building Plan Approval / NA Order for plotted development
17 Building Plan Approval / NA Order for plotted development
18 Building Plan Approval / NA Order for plotted development
19 Building Plan Approval / NA Order for plotted development
20 Building Plan Approval / NA Order for plotted development
21 Building Plan Approval / NA Order for plotted development
22 Building Plan Approval / NA Order for plotted development
23 Building Plan Approval / NA Order for plotted development
24 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
5 Commencement Certificates / NA Order for plotted development
6 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement