MahaRERA Application

General Information

Other Than Individual

Organization

BVG DEVELOPERS
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

B-5
SANT TUKARAM VYAPAR SANKUL
NIGDI ROAD
NIGDI
NIGDI PRADHIKARAN
MAHARASHTRA
Pune
Pune
Haveli
411044

Organization Contact Details

02027658259

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1aResidentialNA100AAAS1012021-09-132021-09-13

Member Information

Member Name Designation Photo
BIBHISHAN VYANKATRAO GAIKWAD Authorized Signatory View Photo
BIBHISHAN VYANKATRAO GAIKWAD Partner View Photo
BALASAHEB VYANKATRAO GAIKWAD Partner View Photo

Project

SILVER GRACIA
New Project
30/12/2023
No
Residential
No
78
PROPERTY OF SR NO 93 AND 94
PROPERTY OWNED BY MR DNYANOBA BHONDVE
24 MTRS DP RD AND SR NO 77
18 MTRS DP RD AND SR NO 86
MAHARASHTRA
Pune
Pune
Haveli
Ravet
RAVET ROAD
RAVET
412101
20800
2
2
0
1852

FSI Details

16144
0
16144.00

Bank Details

STATE BANK OF INDIA
SBIN0004523

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 134 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 COMMON FOR ALL PHASES
Water Conservation, Rain water Harvesting : YES 100 AS STIPULATED IN SANCTION
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 100 AS PER NORMS
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 AS PER ELECTRICAL CONSULTANTS SUGGESTION
Aggregate area of recreational Open Space : YES 100 COMMON FOR ALL PHASES
Open Parking : YES 100 AS PER PLAN
Water Supply : YES 100 AGREED BY PCMC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 STP
Storm Water Drains : YES 100 CONNECTED TO PCMC
Landscaping & Tree Planting : YES 100 AS DESIGNED BY LANDSCAPE DESIGNER
Street Lighting : YES 100 ON INTERNAL ROADS ONLY
Community Buildings : YES 100 AS SUGGESTED BY ARCHITECT
Treatment And Disposal Of Sewage And Sullage Water : YES 100 EXCESS SULLAGE CONNECTED TO PCMC
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 SILVER GRACIA B WING 30/06/2023 0 1 1 20 1 34 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 66.78 18 15
2 2BHK 53.31 32 27
3 2BHK 53.15 36 27
4 3BHK 65.39 18 17
5 3BHK 66.71 18 15
6 3BHK 67.23 18 12
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 SILVER GRACIA D WING 30/06/2023 0 1 1 20 1 37 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 48.94 36 14
2 1BHK 35.60 32 30
3 2BHK 49.67 36 28
4 2BHK 52.28 36 22
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
MEHUL SHAH NA Architect
ANUP CHAVAN NA Engineer
MILIND TILWANKAR NA Chartered Accountant

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
8 Building Plan Approval (IOD)
9 Building Plan Approval (IOD)
10 Building Plan Approval (IOD)
11 Building Plan Approval (IOD)
12 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
1 CERSAI details
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement