MahaRERA Application

General Information

Other Than Individual

Organization

ARIHANT AASHIYANA PRIVATE LIMITED
Company
NA
Do you have any Past Experience ?
No

Address Details

25TH FLOOR, B-WING
"ARIHANT AURA"
THANE BELAPUR ROAD
PLOT NO. 13/1, TTC INDUSTRIAL AREA
TURBHE
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
400705

Organization Contact Details

02262493333

Past Experience Details

Member Information

Member Name Designation Photo
SAMEER GAJANAN GOLAPKAR Authorized Signatory View Photo

Project

ARIHANT ADVIKA
New Project
31/12/2028
No
Residential
Yes
PLOT NO 8 IN BUILDING NO. 19 TO 45
8 METER WIDE ROAD
PLOT NO 7
14 METER WIDE ROAD
9A MUNICIPAL OPEN SPACE OR GARDEN
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
SECTOR 09 VASHI
VASHI
400703
11182.69
4
4
0
1675.76

FSI Details

65733.60
8945.60
74679.20

Bank Details

ICICI BANK
ICIC0001881

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
ARIHANT ADVIKA ARIHANTAASHIYANA PRIVATE LIMITED Company Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
ARIHANT ADVIKA KAILAS SHIKHAR CO-OPERATIVE SOCIETY Societies Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 631 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 CC with Tremix
Water Conservation, Rain water Harvesting : YES 0 WNS
Energy management : YES 0 WNS
Fire Protection And Fire Safety Requirements : YES 0 WNS
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 WNS
Aggregate area of recreational Open Space : YES 0 WNS
Open Parking : NO 0 NA
Water Supply : YES 0 G. I. WATER LINE NETWORK
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 STP TREATED
Storm Water Drains : YES 0 WNS
Landscaping & Tree Planting : YES 0 WNS
Street Lighting : YES 0 WNS
Community Buildings : YES 0 WNS
Treatment And Disposal Of Sewage And Sullage Water : YES 0 WNS
Solid Waste Management And Disposal : YES 0 WNS

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 ARIHANT ADVIKA WING A ADORA- INCENTIVE FREE SALE 31/12/2028 1 1 3 23 1 0 256
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK TYPE 1 57.63 88 2
2 2 BHK TYPE 2 67.46 84 6
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 90
5 X number of Slabs of Super Structure 10
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 30
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 ARIHANT ADVIKA WING B BENECIA-INCENTIVE FREE SALE 31/12/2028 1 1 3 23 1 0 255
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK TYPE 5 67.16 18 3
2 2 BHK TYPE 4 58.01 22 0
3 2 BHK TYPE 3 67.41 23 3
4 3 BHK TYPE 1 87.08 69 9
5 3 BHK TYPE 2 70.83 22 2
6 1BHK 44.19 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 90
5 X number of Slabs of Super Structure 10
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 30
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 ARIHANT ADVIKA WING C CLARISA- REHAB BUILDING 31/12/2028 1 1 0 28 1 0 60
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 29.38 302 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 10
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 21
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
4 ARIHANT ADVIKA WING D DELLA- REHAB BUILDING 31/12/2028 1 1 0 28 1 0 60
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 29.38 346 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 10
5 X number of Slabs of Super Structure 00
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 21

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
YOGITA BHNDARKAR NA Architect
K C JAIN KALA & CO NA Chartered Accountant
KALEEM SAYAD NA Engineer
Mumbai Property Exchange Pvt Ltd A51900000211 Real Estate Agent
KEYSTONE REALTY A51800023534 Real Estate Agent
KEY MANSIONS PRIVATE LIMITED A51900001761 Real Estate Agent
Mohammed Yusuf Shah A51700027537 Real Estate Agent
CORAZON HOMES PRIVATE LIMITED A52100028952 Real Estate Agent
Riya Haresh Rochani A51700002538 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
3 Building Plan Approval / NA Order for plotted development
4 Building Plan Approval / NA Order for plotted development
5 Building Plan Approval / NA Order for plotted development
6 Building Plan Approval / NA Order for plotted development
7 Building Plan Approval / NA Order for plotted development
8 Building Plan Approval / NA Order for plotted development
9 Building Plan Approval / NA Order for plotted development
10 Building Plan Approval / NA Order for plotted development
11 Building Plan Approval / NA Order for plotted development
12 Building Plan Approval / NA Order for plotted development
13 Building Plan Approval / NA Order for plotted development
14 Building Plan Approval / NA Order for plotted development
15 Building Plan Approval / NA Order for plotted development
16 Building Plan Approval / NA Order for plotted development
17 Building Plan Approval / NA Order for plotted development
18 Building Plan Approval / NA Order for plotted development
19 Building Plan Approval / NA Order for plotted development
20 Building Plan Approval / NA Order for plotted development
21 Building Plan Approval / NA Order for plotted development
22 Building Plan Approval / NA Order for plotted development
23 Building Plan Approval / NA Order for plotted development
24 Building Plan Approval / NA Order for plotted development
25 Building Plan Approval / NA Order for plotted development
26 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
8 Architect’s Certificate of Percentage of Completion of Work (Form 1)
9 Architect’s Certificate of Percentage of Completion of Work (Form 1)
10 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
7 Engineer’s Certificate on Cost Incurred on Project (Form 2)
8 Engineer’s Certificate on Cost Incurred on Project (Form 2)
9 Engineer’s Certificate on Cost Incurred on Project (Form 2)
10 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
3 Other
4 Other
5 Other
6 Other
7 Other
8 Other
9 Other
10 Other
11 Other
12 Other
13 Other
14 Other
15 Other
16 Other
17 Other
18 Other
19 Other
20 Other
21 Other
22 Other
23 Other
24 Other
25 Other
26 Other
27 Other
28 Other
29 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement