MahaRERA Application

General Information

Other Than Individual

Organization

MARVEL ZETA DEVELOPERS PVT LTD
Company
NA
Do you have any Past Experience ?
No

Address Details

301-302
JEWEL TOWER
LANE NO-5
KOREGOAN PARK
PUNE
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411001

Organization Contact Details

02030250700
WWW.MARVELREALTORS.COM

Past Experience Details

Member Information

Member Name Designation Photo
VISHWAJEET SUBHASH JHAVAR Managing Director View Photo
MAHESH BANSILAL LADDHA Authorized Signatory View Photo

Project

Marvel Piazza phase -01
On-Going Project
31/03/2018
30/06/2021
30/12/2022
No
Residential
Yes
S NO 226/1 , 226/2
20 MTR ROAD
REMAINING PLOT
PLOT BOUNDARY
PLOT BOUNDARY
MAHARASHTRA
Pune
Pune
Haveli
LOHGAON
411047
21605.91
11
11
0
2160.59

FSI Details

22573.85
5000
27573.85

Bank Details

AXIS Bank Limited
UTIB0001302

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Marvel Piazza phase -01 EMPIRE EXCELLENCE DEVELOPERS Partnership Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 261 90 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 INTERNAL ROAD
Water Conservation, Rain water Harvesting : YES 0 RAIN WATER HARVESTING
Energy management : YES 0 SOLAR WATER HEATING SYSTEM
Fire Protection And Fire Safety Requirements : YES 0 AS PER STATUTORY REQUIREMENTS
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 AS PER MSEDCL REQUIREMENTS
Aggregate area of recreational Open Space : YES 0 AS PER STATUTORY REQUIREMENTS
Open Parking : NO 0 NA
Water Supply : YES 0 WATER INFRA : PLUMBING NETWORKING AND UGWT
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 AS PER STATUTORY REQUIREMENTS
Storm Water Drains : YES 0 AS PER STATUTORY REQUIREMENTS
Landscaping & Tree Planting : YES 0 AS PER STATUTORY REQUIREMENTS
Street Lighting : YES 0 AS PER DESIGN
Community Buildings : YES 0 CLUB HOUSE
Treatment And Disposal Of Sewage And Sullage Water : YES 0 AS PER STATUTORY REQUIREMENTS
Solid Waste Management And Disposal : YES 0 AS PER STATUTORY REQUIREMENTS

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Marvel Piazza phase -01 A 1 1 1 4 0 0 34
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 90.89 1 0
2 4.5 BHK 208.54 2 1
3 3 BHK 119.9 1 0
4 2BHK 86.85 1 0
5 4.5BHK 218.87 1 0
6 4.5 BHK 218.87 1 0
7 3 BHK 100.01 1 0
8 3 BHK 97.16 1 1
9 2 BHK 70.30 1 1
10 2 BHK 66.58 1 1
11 4.5 BHK 175.43 2 2
12 4.5 BHK 170.87 2 1
13 3 BHK 122.88 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 40
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

95
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50
11 Overall Percentage of Completion of the work done For the entire Building /Wing 67.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Marvel Piazza phase -01 B 1 1 1 4 0 0 31
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 129.08 1 0
2 3BHK 119.9 1 0
3 4BHK 219.37 1 0
4 3.5BHK 170.68 1 0
5 3BHK 105.82 1 0
6 3BHK 102.95 1 0
7 3BHK 100.98 1 1
8 3BHK 98.08 1 1
9 4.5BHK 176.42 2 0
10 4.5BHK 171.36 2 0
11 3.5BHK 148.04 1 0
12 3.5BHK 144.52 1 0
13 3BHK 128.35 1 0
14 2BHK 123.69 1 0
15 4.5BHK 209.12 1 0
16 3.5BHK 175.81 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 40
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 10
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

60
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 10
11 Overall Percentage of Completion of the work done For the entire Building /Wing 50
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 Marvel Piazza phase -01 C 1 1 1 4 0 0 23
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 129.05 1 0
2 2BHK 86.87 1 0
3 2BHK 86.91 1 0
4 3.5BHK 171.06 1 0
5 3BHK 105.78 1 1
6 3BHK 102.96 1 1
7 2BHK 78.19 1 1
8 2BHK 68.43 1 1
9 2BHK 78.32 1 1
10 2BHK 67.72 1 1
11 3.5BHK 149.41 1 0
12 3.5BHK 145.88 1 0
13 3BHK 128.38 1 0
14 2BHK 98.62 1 0
15 2BHK 91.91 1 0
16 3.5BHK 177.18 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 75
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

95
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 20
11 Overall Percentage of Completion of the work done For the entire Building /Wing 60
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
4 Marvel Piazza phase -01 D 1 1 1 4 0 0 21
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3.5BHK 128.58 1 0
2 2BHK 87.2 1 0
3 2BHK 86.86 1 0
4 3BHK 128.58 1 0
5 3BHK 105.29 2 2
6 3BHK 101.22 2 2
7 2BHK 72.64 1 1
8 2BHK 68.73 1 1
9 2BHK 72.3 1 1
10 2BHK 68.37 1 1
11 3BHK 127.84 2 0
12 2BHK 98.43 1 1
13 2BHK 98.87 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 30
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

95
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 20
11 Overall Percentage of Completion of the work done For the entire Building /Wing 58.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
5 Marvel Piazza phase -01 E 1 1 1 4 0 0 23
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 129.07 1 0
2 3BHK 120.09 1 0
3 3.5BHK 170.51 1 0
4 3BHK 129.07 1 0
5 3BHK 105.82 2 0
6 3BHK 102.98 2 1
7 3BHK 101.16 1 0
8 3BHK 98.25 1 1
9 3.5BHK 147.79 1 0
10 3.5BHK 144.26 1 0
11 3BHK 128.36 2 0
12 3BHK 124.02 1 0
13 3.5BHK 175.59 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 20
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 5
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 90
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

85
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 10
11 Overall Percentage of Completion of the work done For the entire Building /Wing 51
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
6 Marvel Piazza phase -01 F 1 1 1 4 0 0 23
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 128.82 1 0
2 3.5BHK 165.78 1 0
3 2BHK 86.92 1 0
4 2BHK 86.92 1 0
5 3BHK 106.37 1 0
6 3BHK 103.56 1 0
7 3.5BHK 136.83 1 0
8 3.5BHK 160.59 1 0
9 2BHK 87.85 2 1
10 3.5BHK 132.33 1 1
11 2BHK 67.36 2 2
12 2BHK 64.84 2 2
13 3BHK 128.9 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 10
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

70
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 10
11 Overall Percentage of Completion of the work done For the entire Building /Wing 47
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
7 Marvel Piazza phase -01 G 1 1 1 4 0 0 14
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 86.16 1 0
2 2BHK 87.23 1 0
3 2BHK 86.93 1 0
4 2BHK 70.64 1 1
5 2BHK 68.02 1 0
6 2BHK 67.52 1 1
7 2BHK 64.89 1 1
8 2BHK 71.42 1 1
9 2BHK 68.79 1 1
10 2BHK 91.2 1 1
11 2BHK 88.04 1 1
12 2BHK 91.96 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 30
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 5
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

70
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 5
11 Overall Percentage of Completion of the work done For the entire Building /Wing 49
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
8 Marvel Piazza phase -01 H 1 1 1 4 0 0 25
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 128.89 1 0
2 3.5BHK 166.11 1 0
3 3.5BHK 166.11 1 0
4 3BHK 128.89 1 0
5 3BHK 105.62 2 0
6 3BHK 102.8 2 2
7 3.5BHK 133.37 2 1
8 3.5BHK 129.98 2 0
9 3BHK 128.21 2 1
10 3.5BHK 162.94 2 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 20
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 40
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

70
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 5
11 Overall Percentage of Completion of the work done For the entire Building /Wing 51.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
9 Marvel Piazza phase -01 J 1 1 1 4 0 0 13
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 121.86 1 1
2 3.5BHK 164.99 1 0
3 3BHK 125.71 1 0
4 3.5BHK 166.49 1 1
5 3BHK 99.32 1 0
6 3BHK 96.51 1 1
7 3.5BHK 135.71 1 1
8 3.5BHK 132.23 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 60
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 80
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

85
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 60.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
10 Marvel Piazza phase -01 K 1 1 1 4 0 0 25
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 128.21 2 0
2 3.5BHK 162.96 2 0
3 3BHK 128.88 1 0
4 3.5BHK 166.14 1 1
5 3.5BHK 166.14 1 0
6 3BHK 128.88 1 0
7 3BHK 105.61 2 2
8 3BHK 102.79 2 1
9 3.5BHK 133.4 2 0
10 3.5BHK 130.01 2 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 35
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 40
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

20
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 46.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
11 Marvel Piazza phase -01 L 1 1 1 4 0 0 29
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 128.88 1 0
2 4.5BHK 219.3 1 0
3 3.5BHK 166.21 1 0
4 3BHK 128.88 1 0
5 3BHK 103.59 2 1
6 3BHK 100.71 2 1
7 4.5BHK 178.1 1 0
8 4.5BHK 174.99 1 0
9 3.5BHK 129.55 1 0
10 3.5BHK 126.76 1 0
11 3BHK 126.29 2 2
12 4.5BHK 211.22 1 0
13 3.5BHK 158.61 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 35
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 35
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 70
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

20
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 46

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
RAHUL MALWADKAR NA Architect
RAJESH VASUDEV MANKANI NA Engineer
NITIN SHANKAR KADDE A52100000577 Real Estate Agent
GLADWIN BAPTIST A52100002660 Real Estate Agent
JANET DORAIRAJ A52100004089 Real Estate Agent
ELARA MARKETING SERVICES PRIVATE LIMITED A51700000030 Real Estate Agent
Addressofchoice Realty Pvt Ltd A52100000116 Real Estate Agent
A K Properties A52100000622 Real Estate Agent
PROPERTY CHEF CONSULTING SERVICES A52100000044 Real Estate Agent
CBRE South Asia Private Limited A51600003050 Real Estate Agent
Paresh Lachman Hardwani A52100000163 Real Estate Agent
JONES LANG LASALLE PROPERTY CONSULTANTS (INDIA) PRIVATE LIMITED A51900000251 Real Estate Agent
Ravi Chaitanya Varma A52100000903 Real Estate Agent
Shalini Ravi Varma A52100000047 Real Estate Agent
JN Realtors and Property Managers A52100004139 Real Estate Agent
Vijay Anand A52100000084 Real Estate Agent
PROPOZONE TECHNOLOGIES PRIVATE LIMITED A52100002247 Real Estate Agent
PROPFINDER INDIA PRIVATE LIMITED A52100004005 Real Estate Agent
HIREN NATVARLAL TRIVEDI A52100001413 Real Estate Agent
Makaan Hunt Pvt Ltd A52100000430 Real Estate Agent
ICICI Home Finance Company Limited A51800000727 Real Estate Agent
Subhash Chandrakant Sonkamble A52100002477 Real Estate Agent
Ashwin Bhishma Vohra A52100002999 Real Estate Agent
NIKHIL JAIN A52100000055 Real Estate Agent
MAHEK KAPADIA A52100003545 Real Estate Agent
DIPEN LOOMBA A52100002949 Real Estate Agent
R-Constellation Pvt. Ltd. A52100000304 Real Estate Agent
360 REALTORS LLP A51900000246 Real Estate Agent
PROPBUYING REALTORS PVT LTD A52100000476 Real Estate Agent
Property Pointer Private Limited A52100000787 Real Estate Agent
HDFC Realty Limited A51900000107 Real Estate Agent
Vivek G Pungaliya A52100000690 Real Estate Agent
Premlata Estate Solutions Pvt. Ltd. A52100000033 Real Estate Agent
Property Pointer Private Limited A52100000787 Real Estate Agent
Pankaj Kumar Chaurasia A52100000283 Real Estate Agent
chanderjeet chaturbhuj bhatia A52100002394 Real Estate Agent
Urvi Anchan A52100004475 Real Estate Agent
LAXMIKANT TANAJI DHANWADE A52100000144 Real Estate Agent
BILLION YARDS INFRATECH A51800003230 Real Estate Agent
Khushnum Nitin Chauhan A52100003503 Real Estate Agent
SOMNATH DNYANESHWAR HINGANE A52100000243 Real Estate Agent
Vikas Das A52100002200 Real Estate Agent
Zodiac Realtors and Developers A51800002891 Real Estate Agent
Vijay Purshottam Manakikar A52100000028 Real Estate Agent
Pramod Pandurang Potpelwar A52100004660 Real Estate Agent
MANJUSHA MAHESH BELLUR A52100000509 Real Estate Agent
Shrradhaa Daven Kakkad A52100000830 Real Estate Agent
Anupam Vinodkumar Gadodia A52100003713 Real Estate Agent
Mahesh Nanikram Lalchandani A52100001856 Real Estate Agent
Ameeth Kothari A52100000092 Real Estate Agent
Padmakshi Mondial Wealth Management Private Limited A51900003916 Real Estate Agent
AARTI AJAY CHAUBE A52100001933 Real Estate Agent
SHARMILA SWAMINATHAN IYER A52100002367 Real Estate Agent
LOVEENA LEONARDO A52100003486 Real Estate Agent
Ravi Chaitanya Varma A52100000903 Real Estate Agent
Shalini Ravi Varma A52100000047 Real Estate Agent
GLOBAL REALTORS A52100000018 Real Estate Agent
Arthur Morris A52100003774 Real Estate Agent
RAJNISH KUMAR JAIN A51800001742 Real Estate Agent
Chirag Saunak Kapadia A52100000054 Real Estate Agent
RAHUL ANAND GAIKWAD A52100000661 Real Estate Agent
Hitendra Panditrao Choudhary A52100001901 Real Estate Agent
PEARL REALTORS A52100000187 Real Estate Agent
KEY2HOME PROPERTY ADVISORS A52100000051 Real Estate Agent
ABHIJIT SAHEBRAO SABBARWAR A52100000382 Real Estate Agent
Atul Ramchandra Mazire A52100000560 Real Estate Agent
WG CDR VERINDAR KUMAR JANDIAL A52100002832 Real Estate Agent
My Home Real Estate A52100000038 Real Estate Agent
Moses Doming Mascarenhas A52100000747 Real Estate Agent
Pearlquest Associates Pvt Ltd A52100001979 Real Estate Agent
SAMSON DANIEL MASSY A52100001246 Real Estate Agent
Khozem Taher Bayadwala A52100005032 Real Estate Agent
Prasad Hanmant Kulkarni A52100000272 Real Estate Agent
Amrut Shantaram Ghorpade A52100000268 Real Estate Agent
Richa Bijlani A52100004019 Real Estate Agent
Rajendra Kumar Rathore A52100000247 Real Estate Agent
YASHODHAR PURUSHOTTAM KARMARKAR A52100001983 Real Estate Agent
PROPENGINE REALTECH LLP A52100000628 Real Estate Agent
Kiran Girish Padiyar A52100007132 Real Estate Agent
ASHISH TANDON A52100008836 Real Estate Agent
S SATYANARAYAN PATRO A52100007317 Real Estate Agent
Parvez Fida Shaikh A52600008677 Real Estate Agent
Yatish Lalwani A52100007824 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
8 Building Plan Approval (IOD)
9 Building Plan Approval (IOD)
10 Building Plan Approval (IOD)
11 Building Plan Approval (IOD)
12 Building Plan Approval (IOD)
13 Building Plan Approval (IOD)
14 Building Plan Approval (IOD)
15 Building Plan Approval (IOD)
16 Building Plan Approval (IOD)
17 Building Plan Approval (IOD)
18 Building Plan Approval (IOD)
19 Building Plan Approval (IOD)
20 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC005000000000207 SHAUL SION NAGAWKAR View Orders
2 CC005000000010429 VIVEK RAMESHCHANDRA DHODIA View Orders
3 CC005000000010429 VIVEK RAMESHCHANDRA DHODIA View Orders
4 CC005000000010429 RAMESHCHANDRA M DHODIA View Orders
5 CC005000000010429 RAMESHCHANDRA M DHODIA View Orders
6 CC005000000010794 Shobharani Shinde for herself and power-of-attorney holder of Vaibhav Shinde View Orders
7 CC005000000011576 Shobha Shinde for herself and power-of-attorney holder of Vaibhav Shinde View Orders
8 CC005000000064405 KISHOR VISHWASRAO PATIL AND MEGHA KISHOR PATIL View Orders
9 CC005000000064415 BALBHIM DASHRATH MORE AND RANI BALBHIM MORE View Orders
10 CC005000000064848 prashant amrith rao View Orders