MahaRERA Application

General Information

Other Than Individual

Organization

M/s YOGI DEVELOPERS CORPORATION
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

2nd Floor
Citi Mall
New Link Road
Andheri West
Next to Infinity Mall
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
400053

Organization Contact Details

02266984000

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1NEW ERA CResidentialNA10178.39THANE KALYAN DOMBIVALI24/2 pt, 25 pt, 26 pt11442021-06-302018-09-26
2YOGIDHAMResidentialNA18550PHASE III THANE KALYAN DOMBIVALI24/2 pt, 25 pt, 26 pt99202014-12-302014-12-30

Member Information

Member Name Designation Photo
Deepak Ramesh Mehta Authorized Signatory View Photo
YASH B AJMERA Authorized Signatory View Photo

Project

AJMERA BLISS
New Project
30/04/2024
No
Residential
Yes
22, 18,11,23,24,2PT,2PT,2PT,2PT,2PT,2PT,2PT,2PT,25,1,2,3,4PT,4PT,5,6,7,26
S NO 22 PT
S NO 24
S NO 21
12 METER DP ROAD
MAHARASHTRA
Konkan
Thane
Kalyan
Kalyan-Dombivali (M Corp.)
KALYAN MURBAD ROAD
KALYAN WEST
421301
67432.17
1
1
0
10114.83

FSI Details

3355.92
2516.94
5872.86

Bank Details

HDFC BANK
HDFC0000194

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
AJMERA BLISS MAHAMMAD HUASAIN MAULAVI Individual Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 36 0 0
Covered Parking ( In Numbers) 0 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 NONE
Water Conservation, Rain water Harvesting : YES 0 NONE
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 0 AS PER CFO
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 AS PER MSEB
Aggregate area of recreational Open Space : YES 0 NA
Open Parking : YES 0 WORK IN PROGRESS
Water Supply : YES 0 NONE
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 TO BE PROVIDE
Storm Water Drains : YES 0 NONE
Landscaping & Tree Planting : YES 0 NONE
Street Lighting : YES 0 ON INTERNAL ROAD
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 AJMERA BLISS BUILDING NO 7 31/10/2023 0 1 0 21 1 64 1
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 41.45 84 75
2 2BHK 60.7 42 30
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 10
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

98
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 90
11 Overall Percentage of Completion of the work done For the entire Building /Wing 79.8

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
RACHNA SHILP NA Architect
PARTHIV AND CO NA Chartered Accountant
SOMNATH TAUR NA Engineer

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
7 Engineer’s Certificate on Cost Incurred on Project (Form 2)
8 Engineer’s Certificate on Cost Incurred on Project (Form 2)
9 Engineer’s Certificate on Cost Incurred on Project (Form 2)
10 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 CERSAI details
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
5 Disclosure of sold/ booked inventory
6 Disclosure of sold/ booked inventory
7 Disclosure of sold/ booked inventory
8 Disclosure of sold/ booked inventory
9 Disclosure of sold/ booked inventory
10 Disclosure of sold/ booked inventory
11 Disclosure of sold/ booked inventory
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement