MahaRERA Application

General Information

Other Than Individual

Organization

Turquoise Housing LLP
Others
Limited Liability Partnership
Do you have any Past Experience ?
Yes

Address Details

Office No 403 & 503
Supreme Square
DP Road Parihar Chowk
Aundh
Near Hotel Shivsagar
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411007

Organization Contact Details

02067295000
www.supremeuinversal.in

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1EstabanResidentialNA2000South Lane no 7 Ghorpadi Koregaon Park Pune 411001Final plot no 391C and 391 A1112015-01-312015-02-12

Other Organization Type Member Information

Name Member Type
Vishal Suresh Jumani Individual
Sunny Ramesh Bijlani Individual
Jumani Landmarks LLP Others
Bijlani Realty LLP Others

Project

Supreme Villagio I
New Project
31/03/2025
No
Residential
No
Gut No 248 249 250 251 254
15 Mtr Road Gut no 255 Gut no 257
90 Mtr Proposed Road and Gut no 247
Gut no 222 and Gut no 323
Gut no 255 Gut no 257 and Gut no 275
MAHARASHTRA
Pune
Pune
Mawal
Somatane
Shirgaon Road
Somatne
410506
11000.86
1
1
0
5810.42

FSI Details

10033.26
00
10033.26

Bank Details

HDFC BANK LTD
HDFC0000052

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 75 64 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 Roads
Water Conservation, Rain water Harvesting : YES 0 RWH Pits
Energy management : YES 0 Yes
Fire Protection And Fire Safety Requirements : NO 0 NA
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 Yes
Aggregate area of recreational Open Space : YES 44 Landscape Area
Open Parking : NO 0 NA
Water Supply : YES 18 Yes
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 24 drainage line
Storm Water Drains : YES 20 SW Drain
Landscaping & Tree Planting : YES 39 Landscape
Street Lighting : YES 0 Lighting pole
Community Buildings : YES 82 Club House
Treatment And Disposal Of Sewage And Sullage Water : YES 20 STP work
Solid Waste Management And Disposal : YES 30 OWC Plant

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Supreme Villagio I Row houses B 31/12/2024 0 75 0 2 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Row House Type 13 128.26 1 1
2 Row House Type 15 128.02 1 1
3 Row House Type 21 128.26 2 2
4 Row House Type 14 128.26 1 1
5 Row House Type 17 128.26 1 1
6 Row House Type 11 124.56 1 0
7 Row House Type 1 127.38 1 0
8 Row House Type 2 127.38 1 1
9 Row House Type 10 128.26 2 1
10 Row House Type 12 128.02 1 1
11 Row House Type 24 128.26 2 2
12 Row House Type 22 82.13 1 1
13 Row House Type 3 110.11 1 1
14 Row House Type 19 117.82 1 0
15 Row House Type 4 110.11 1 1
16 Row House Type 18 82.97 1 0
17 Row House Type 9 127.38 48 47
18 Row House Type 16 128.02 1 1
19 Row House Type 20 128.02 1 1
20 Row House Type 25 128.02 1 1
21 Row House Type 7 77.16 1 1
22 Row House Type 23 102.83 1 1
23 Row House Type 5 87.39 1 1
24 Row House Type 6 87.39 1 1
25 Row House Type 8 120.77 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 61
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 10
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 9
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

7
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 7
11 Overall Percentage of Completion of the work done For the entire Building /Wing 29.4

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
A N J K & Co LLP NA Chartered Accountant
Jitendra Rawat A52100020162 Real Estate Agent
NITESH KUMAR SINGH A52100002854 Real Estate Agent
JANARDAN MANSING BHOSALE A52700038123 Real Estate Agent
Roopesh Menon A52100021114 Real Estate Agent
ANAND AJIT GUPTE A52100025185 Real Estate Agent
proprise property consulting private limited A52100025032 Real Estate Agent
Auraexcellente Realinfracon Private Limited A52100032621 Real Estate Agent
TSDN REALTORS LLP A52100002195 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
3 Building Plan Approval / NA Order for plotted development
4 Building Plan Approval / NA Order for plotted development
5 Building Plan Approval / NA Order for plotted development
6 Building Plan Approval / NA Order for plotted development
7 Building Plan Approval / NA Order for plotted development
8 Building Plan Approval / NA Order for plotted development
9 Building Plan Approval / NA Order for plotted development
10 Building Plan Approval / NA Order for plotted development
11 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
2 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
7 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
2 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
2 CERSAI details
3 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
2 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement
2 Deviation Report with respect to model copy of Agreement
3 Deviation Report with respect to model copy of Agreement