MahaRERA Application

General Information

Other Than Individual

Organization

PRIME BUILDCON
Partnership
NA
Do you have any Past Experience ?
No

Address Details

Shop No. 2
Shrishti Homes
Adarsh Colony
Tingere Nagar
Shanti Medical
MAHARASHTRA
Pune
Pune
Haveli
VISHRANTWADI
411032

Organization Contact Details

02026690331
www.parkvista.in

Past Experience Details

Member Information

Member Name Designation Photo
Kapil Suresh Gupta Authorized Signatory View Photo
Vijay Anantram Goyal Authorized Signatory View Photo
Sanjay Shyamlal Singhal Authorized Signatory View Photo
Ashish Sanjay Singhal Partner View Photo
Mukesh Anantram Goyal Partner View Photo
Vipul Ashok Agarwal Partner View Photo
Ashok Rajendraprasad Agarwal Partner View Photo
Yogita Pandurang Kulkarni Partner View Photo

Project

Park Vista Phase 1
On-Going Project
30/09/2020
30/03/2021
No
Residential
Yes
289/1A/1/1
A3 building and internal road
A1 building and internal road
by Sno 291 P of R Moze and Lohegaon Road
by Sno 289 P of Tarabai Karanje and 6 m road
MAHARASHTRA
Pune
Pune
Haveli
LOHGAON
411047
3265.02
1
1
0
1047.51

FSI Details

6863.25
0
6863.25

Bank Details

Corporation Bank
CORP0001215

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Park Vista Phase 1 Prime Buildcon Partnership Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 33 23 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 Complete
Water Conservation, Rain water Harvesting : YES 100 Complete
Energy management : YES 100 Complete
Fire Protection And Fire Safety Requirements : YES 100 Complete
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 Complete
Entrance Gate Structure : YES 100 Complete
Aggregate area of recreational Open Space : YES 100 Complete
Open Parking : YES 100 Complete
Water Supply : YES 100 Complete
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 Complete
Storm Water Drains : YES 100 Complete
Landscaping & Tree Planting : YES 100 Complete
Street Lighting : YES 100 Complete
Community Buildings : YES 90 Almost Complete
Treatment And Disposal Of Sewage And Sullage Water : YES 100 Complete
Solid Waste Management And Disposal : YES 100 Complete

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Park Vista Phase 1 A2 30/09/2020 0 1 0 12 1 291 34
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2RHK 46.04 1 1
2 2RHK 47.28 4 3
3 2RHK 47.37 6 4
4 1RHK 35.62 24 3
5 2RHK 45.72 4 3
6 2RHK 47.59 3 3
7 2RHK 46.62 8 5
8 2RHK 44.48 20 19
9 2RHK 45.83 6 2
10 2RHK 46.73 12 6
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 100

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Ar Imran Shaikh of Ms Cubix Architects Associates NA Architect
VIKAS SATISH GUPTA A52100002607 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement