MahaRERA Application

General Information

Other Than Individual

Organization

KRUSHNA DHAM BUILDERS & DEVELOPERS GHOT
Partnership
NA
Do you have any Past Experience ?
No

Address Details

A-2009
BIMA COMPLEX
2ND FLOOR
KALAMBOLI
NAVI MUMBAI
MAHARASHTRA
Konkan
Raigarh
Panvel
Kalamboli
410218

Organization Contact Details

02227422333

Past Experience Details

Member Information

Member Name Designation Photo
HARESH NATHURAM PORJI Partner View Photo
HARESH NATHURAM PORJI Authorized Signatory View Photo
PATHIK SANDEEP AGARWAL Partner View Photo
HIRALAL KHODABHAI PATEL Partner View Photo
KISHORILAL BALDEO SHARMA Partner View Photo

Project

KRUSHNA KUNJ
New Project
30/12/2025
No
Residential
No
SURVEY NO. 5/2, 5/5, 5/6, 5/4-7 GHOT
0
0
0
0
MAHARASHTRA
Konkan
Raigarh
Panvel
Ghot
GHOT
PANVEL
410210
11130
8
8
0
1109.20

FSI Details

16655
0
16655

Bank Details

STATE BANK OF INDIA
SBIN0000448

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 32 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 70 WILL BE PROVIDED AS PER PANVEL MUNICIPAL CORP.
Water Conservation, Rain water Harvesting : YES 50 WILL BE PROVIDED AS PER GOVT NORMS
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : NO 0 NA
Electrical Meter Room, Sub-Station, Receiving Station : YES 50 ELECTRIC METER ROOM ONLY
Aggregate area of recreational Open Space : YES 0 WILL BE PROVIDED AS PER PLAN
Open Parking : NO 0 NA
Water Supply : YES 50 WILL BE PROVIDED AS PER PANVEL MUNICIPAL CORP.
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 50 WILL BE PROVIDED AS PER PANVEL MUNICIPAL CORP.
Storm Water Drains : YES 0 WILL BE PROVIDED AS PER PANVEL MUNICIPAL CORP.
Landscaping & Tree Planting : YES 0 TREE PLANTING ONLY
Street Lighting : YES 50 WILL BE PROVIDED AS PER GOVT NORMS
Community Buildings : YES 100 CLUB HOUSE
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 KRUSHNA KUNJ BUILDING NO 1 AND 2 SHOPS 31/12/2024 0 1 0 8 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop 15.16 1 0
2 Shop 15.44 1 0
3 Shop 11.05 1 1
4 Shop 14.70 1 1
5 Shop 13.63 1 1
6 Shop 16.41 1 1
7 Shop 17.93 1 1
8 Shop 12.96 4 1
9 Shop 11.24 1 1
10 Shop 14.45 1 1
11 Shop 10.08 5 4
12 Shop 14.04 6 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 75
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 32.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 KRUSHNA KUNJ BUILDING NO 1 AND 2 FLATS 31/12/2024 0 1 0 8 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 34.88 12 0
2 1BHK 35.15 15 0
3 1BHK 35.72 20 0
4 2BHK 49.30 3 0
5 2BHK 44.15 3 0
6 2BHK 44.74 4 0
7 1BHK 28.92 4 2
8 1BHK 34.15 4 2
9 1BHK 28.35 3 3
10 1BHK 33.08 3 2
11 1BHK 35.45 16 2
12 2BHK 49.88 4 1
13 2BHK 50.67 8 1
14 2BHK 50.01 6 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 75
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 50
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 32.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 KRUSHNA KUNJ BUILDING NO 3 31/12/2024 0 1 0 5 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 31.11 10 10
2 1BHK 30.54 2 2
3 1BHK 30.42 2 2
4 1BHK 30.92 10 9
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
4 KRUSHNA KUNJ BUILDING NO 4 31/12/2024 0 1 0 5 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 31.04 2 2
2 1BHK 31.55 2 2
3 1BHK 32.78 2 2
4 1BHK 30.58 2 2
5 1BHK 32.50 2 2
6 1BHK 30.76 2 2
7 1BHK 30.44 8 8
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
5 KRUSHNA KUNJ BUILDING NO 5 31/12/2024 0 1 0 5 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 30.40 2 2
2 1 BHK 30.49 4 4
3 1 BHK 30.44 18 17
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
6 KRUSHNA KUNJ BUILDING NO 6 31/12/2024 0 1 0 5 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK A WING 30.49 8 8
2 1 BHK A WING 30.35 2 2
3 1 BHK A WING 30.57 2 2
4 1 BHK B WING 30.47 2 2
5 1 BHK A WING 30.44 10 10
6 1 BHK A WING 30.47 2 2
7 1 BHK B WING 30.44 8 8
8 1 BHK B WING 31.12 2 2
9 1 BHK B WING 30.57 2 2
10 1 BHK B WING 30.49 8 7
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 50
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 85
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
7 KRUSHNA KUNJ BUILDING NO 7 31/12/2024 0 1 0 8 1 0 10
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK A WING 45.11 7 5
2 2 BHK A WING 43.52 7 3
3 2 BHK A WING 48.01 14 6
4 2 BHK B WING 46.10 7 7
5 1 BHK B WING 35.56 7 4
6 2 BHK B WING 44.55 7 1
7 1 BHK A WING 35.56 7 3
8 1 BHK B WING 35.80 14 4
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 40
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

25
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 56.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
8 KRUSHNA KUNJ BUILDING NO 8 31/12/2024 0 1 0 5 0 0 20
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK B WING 49.85 8 8
2 2 BHK A WING 49.30 8 8
3 2 BHK B WING 49.30 8 8
4 2 BHK A WING 49.85 8 8
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
AN ARCH NA Architect
VASTUKALP NA Engineer
CHANDRESH BUILDTECH NA Contractor
ABHL & ASSOCIATES NA Chartered Accountant

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
3 Copy of the legal title report
4 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
4 Copy of Layout Approval (in case of layout)
5 Copy of Layout Approval (in case of layout)
6 Copy of Layout Approval (in case of layout)
7 Copy of Layout Approval (in case of layout)
8 Copy of Layout Approval (in case of layout)
9 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
14 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
15 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
16 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
17 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
18 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
19 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
20 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
14 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
15 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
16 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
17 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
18 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
19 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
20 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
21 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
5 Disclosure of sold/ booked inventory
6 Disclosure of sold/ booked inventory
7 Disclosure of sold/ booked inventory
8 Disclosure of sold/ booked inventory
9 Disclosure of sold/ booked inventory
10 Disclosure of sold/ booked inventory
11 Disclosure of sold/ booked inventory
12 Disclosure of sold/ booked inventory
13 Disclosure of sold/ booked inventory
14 Disclosure of sold/ booked inventory
15 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement