MahaRERA Application

General Information

Other Than Individual

Organization

KABRA AND ASSOCIATES
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

1001, 10TH FLOOR,
KAMLA HUB
N.S. ROAD NO.1, OFF GULMOHAR ROAD
JVPD SCHEME, VILE PARLE (WEST)
NEXT TO AROMAS CAFE
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
400049

Organization Contact Details

02226210202
www.kabragroup.net

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1NEW VINAYResidentialNA2434.80Sunder Nagar Near Mumbai University Kalina Santacruz East Mumbai 984918/298/131702015-05-312015-12-31
2KABRA ARGENTUM - UNNAT NAGAR - 43/44ResidentialNA1709Plot No. 43 - 44 Unnat Nagar II Off S V Road Goregaon West Mumbai - 62318, 318 / 1 to 161792015-09-302016-01-20
3RAGESHREEOthersResidential cum Commercial2233.40Sodawala Lane Opp. Pandya Hospital Borivali West Mumbai - 92509 509 1/41692016-06-302017-05-09
4ALYA GARNETOthersResidential cum Commercial13935Brahmand Azad Nagar Behind Universal School Brahmand Thane West - 40060787/2/1 2/2 2/3 4A 4B 4C 5A 5B 5C 122/17 122/1811072014-03-292012-12-12
5NATRAJOthersResidential cum Commercial2566Corner of Prem Nagar & Sodawala Lane Opp. Prabhodhan Thackarey Hall Borivali West Mumbai 922433 243 1/10 1161932017-06-302017-05-30
6NANDANWADIResidentialNA501.67Plot No.257 Jawahar Nagar Next to Mount Mary High School Goregaon West Mumbai - 62505 505/ 1 and 21212014-06-302014-05-09
7CHRISTINAResidentialNA1548Shree Nagar Estate Vidyaniketan Marg Off M G Road Goregaon West Mumbai - 62276-B1512015-05-012014-09-16
8VIHANGResidentialNA527Building No. 16 Siddharth Nagar IV Opp. Vivek College Goregaon West Mumbai - 62348 part 348/57 to 611412015-03-312017-06-10

Member Information

Member Name Designation Photo
GAUTAM JAIGOPAL KABRA Authorized Signatory View Photo
DILIP SATYANARAYAN SONI Authorized Signatory View Photo
SHYAMSUNDER ASHARAM KABRA Partner View Photo
RAJESH ASHARAM KABRA Partner View Photo
GAUTAM JAIGOPAL KABRA Partner View Photo
MANISH KAMALKISHORE KABRA Partner View Photo
ABHISHEK KAMALKISHORE KABRA Partner View Photo
GOURAV JAIGOPAL KABRA Partner View Photo
VINIL SHYAMSUNDER KABRA Partner View Photo

Project

KABRA AURUM WING A B C AND D Redevelopment of Goregaon Unnat Nagar II Plot No 51 to 55 CHSL
On-Going Project
31/12/2019
31/12/2019
Yes
Residential
No
PLOT NO 51 TO 55 CTS 307 PART
By 9 mtr wide Road
By 9 mtr wide Road and Partly by Plot No 50
By MHADA Plot
By Plot No 49 and 50
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
400064
3281.02
1
1
0
0

FSI Details

15328.41
0
15328.41

Bank Details

KOTAK MAHINDRA BANK LTD
KKBK0000643

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) NONE NA 0
Covered Parking ( In Numbers) 149 149 100

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 100 Work Complete
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 100 Work Complete
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 Work Complete
Aggregate area of recreational Open Space : YES 100 Work Complete
Open Parking : YES 100 Work Complete
Water Supply : YES 100 SHALL BE DONE PRIOR OC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 No STP Plant
Storm Water Drains : YES 100 Work Complete
Landscaping & Tree Planting : YES 100 Work Complete
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 KABRA AURUM WING A B C AND D Redevelopment of Goregaon Unnat Nagar II Plot No 51 to 55 CHSL KABRA AURUM 0 2 1 21 2 6 149
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK TYPE 1 35.12 17 17
2 1 BHK TYPE 2 37.81 10 3
3 1 BHK TYPE 3 41.81 18 18
4 1 BHK TYPE 4 49.24 37 37
5 2 BHK TYPE 1 59.37 19 19
6 2 BHK TYPE 2 60.39 2 2
7 2 BHK TYPE 3 64.85 16 16
8 2 BHK TYPE 4 69.68 2 2
9 2 BHK TYPE 5 70.33 12 12
10 2 BHK TYPE 6 71.54 33 33
11 2.5 BHK TYPE 1 77.02 1 0
12 3 BHK TYPE 1 81.57 19 19
13 3 BHK TYPE 2 87.42 19 17
14 3 BHK TYPE 3 120.78 2 2
15 4 BHK TYPE 1 108.98 8 8
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Parvati Corporation VINOD KHIMJI MAVANI NA Contractor
Bharat Electricals BHARAT N. PATEL NA Contractor
Anil Enterprises ANIL VISHWAKARMA NA Contractor
Arjun Arts AMEYA ARJUN KADAM NA Contractor
Hari Om Plumber Contractor ROHIT MANJI VERAT NA Contractor
ARCH HEMANT TALATY NA Architect
Rasik P Hingoo and Associates ARCH KINJAL HINGOO NA Architect
Reza Kabul Architects Pvt. Ltd. ARCH REZA KABUL NA Architect
ASCENT Structural Engineers Pvt Ltd MR SHRINIWAS MAHAMUNI NA Engineer
RIDDHI SIDDHI HOUSING LLP A51800001069 Real Estate Agent
ARVIND KUNDANMAL JAIN A51900003469 Real Estate Agent

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
KABRA AURUM WING A B C AND D Redevelopment of Goregaon Unnat Nagar II Plot No 51 to 55 CHSL BOMBAY CITY CIVIL COURT S C SUIT NO 1502 OF 2015 Civil No Suit NA 2015 CASE PENDING
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Form 2A
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Certificates of Architect (Form 4)
2 Certificates of Architect (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
2 Status of Formation of Legal Entity (Society/Co Op etc.)
3 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC006000000057380 Mr. & Mrs. Rekha and Rajkumar Hemdev View Orders