MahaRERA Application

General Information

Other Than Individual

Organization

Klassik Vinyl Products LLP
Others
LLP
Do you have any Past Experience ?
No

Address Details

Unit No. F-1, 1st Floor
Shanti Nagar Co-operative Industrial Estate Limited
Vakola
Santacruz East
Opp Grand Hyatt
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
400055

Organization Contact Details

02230645000
www.kalpataru.com

Past Experience Details

Other Organization Type Member Information

Name Member Type
Narendra Kumar Lodha, Body Corporate Nominee Others
Shyam Agarwal, Body Corporate Nominee Others

Project

Kalpataru Bliss Apartments
New Project
30/03/2025
Yes
Residential
No
CTS No 4958D pt, 4958D-52Pt, 53Pt, 54Pt, 55 to 71, 75 pt, 76 to 124 of Village Kolekalyan
13 Mt wide Road
Partly by CTS No 4958D-125 Partly CTS No 4961
CTS 4953D Part
CTS No 4956 and 4950A
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
Manipada Road
Kalina
400098
1946.54
1
1
0
485.69

FSI Details

2507.14
4592.86
7100.00

Bank Details

ICICI Bank Ltd
ICIC0000004

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 101 28 25

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 To be done before completion of the Project
Water Conservation, Rain water Harvesting : YES 0 To be done before completion of the Project
Energy management : YES 0 To be done before completion of the Project
Fire Protection And Fire Safety Requirements : YES 0 To be done before completion of the Project
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 Electric Meter Room and Substation Only
Fitness Centre : YES 0 To be done before completion of the Project
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 0 Supply from Local Authority
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 STP only
Storm Water Drains : YES 0 To be done before completion of the Project
Landscaping & Tree Planting : YES 0 To be done before completion of the Project
Street Lighting : YES 0 To be done before completion of the Project
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 To be done before completion of the Project
Solid Waste Management And Disposal : YES 0 To be done before completion of the Project

Building Details

Sr.No. Project Name Name Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Slab of Super Structure Number of Stilts Number of Open Parking Number of Closed Parking
1 Kalpataru Bliss Apartments Kalpataru Bliss Wing A and Wing B 30/09/2023 3 1 0 15 1 0 101
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Types of 3 BHK 1346.78 15 6
2 Types of 2 BHK 3468.92 50 12
3 Types of 2.5 BHK 1120.14 14 3
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 51
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 5.1

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
PROPTIGER MARKETING SERVICES PRIVATE LIMITED A51700000030 Real Estate Agent
Quikr Realty Limited A51900000107 Real Estate Agent
360 REALTORS LLP A51900000246 Real Estate Agent
Manisha Lifespaces Consulting Pvt. Ltd. A51800008040 Real Estate Agent
JM Financial Products Limited A51900000277 Real Estate Agent
Dream Homes Realty A51700000406 Real Estate Agent
Mystic India Realtors & Consultant A51900006152 Real Estate Agent
New Project Deals A51900003045 Real Estate Agent
Manoj Kotwani Associates A51700001311 Real Estate Agent
Honeydew Advisory Services Pvt LTD A51800004408 Real Estate Agent
MAA REALTY A51800010766 Real Estate Agent
Property Junction International A51800013473 Real Estate Agent
PROPFINDER INDIA PRIVATE LIMITED A52100004005 Real Estate Agent
MalikMakaan A51800001064 Real Estate Agent
VIDHYAN CHINNATHAMBI NADAR A51800003010 Real Estate Agent
GOLDSTONE REALTY A51800004148 Real Estate Agent
Raja B Singh A51800002044 Real Estate Agent
KALPESH RATILAL PATEL A51800000469 Real Estate Agent
GRD REALTY PVT LTD A51900002118 Real Estate Agent
SURENDRA GALA A51800002733 Real Estate Agent
Sameer Ansari A51800010244 Real Estate Agent
Drilltech Engineers Pvt. Ltd NA Contractor
SKAF Construction Pvt Ltd NA Contractor
Milind Naik NA Engineer
M/S Entech Consultant (Form 1 & Form 4) NA Architect
C R Mohnot & Co (Form 3) NA Chartered Accountant
Statutory Auditor R R Saboo and Co NA Chartered Accountant
GA Design(Design Consultant) NA Other Professional
Epicons consultants Pvt Ltd(Structural Consultant) NA Other Professional
Engineering creations public health(MEP Consultant) NA Other Professional
Atul Gulati (Project Architect) NA Other Professional

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
Kalpataru Bliss Apartments City Survey Office Bandra Complaint No M S1414/Disputed Mutation Entry No 36/Kolekalyan/2018 Others No Other 2018 Pending
NA
Kalpataru Bliss Apartments Collector Mumbai Suburban District Yet to be get Others No Other 2018 Pending
NA
Kalpataru Bliss Apartments CEO SRA Yet to be get Others No Other 2018 Pending
NA
Kalpataru Bliss Apartments City Civil Court Dindoshi 2219 Civil No Suit 2017 Notice of Motion stage
NA
Kalpataru Bliss Apartments High Court 33816 Civil No Writ Petition 2017 Admission stage matter is infructuous
NA

Uploaded Documents

Document Name Uploaded Document
Copy of the legal title report
Details of encumbrances
Copy of Layout Approval (in case of layout)
Building Plan Approval (IOD)
Commencement Certificates / NA Order for plotted development
Declaration in FORM B
Proforma of the allotment letter and agreement for sale
Proforma of the allotment letter and agreement for sale
Status of Formation of Legal Entity (Society/Co Op etc.)
Status of Conveyance
Other