MahaRERA Application

General Information

Other Than Individual

Organization

Chariot Properties LLP
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

1701
Satra Plaza
Palm Beach Road
Vashi
APMC Police Station
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
400703

Organization Contact Details

02227849000
www.paradisegroup.co.in

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Sai RiverdaleResidentialNA5499Sector 7 TalojaPlot 11 and 1212442017-10-182017-07-03
2Sai HarmonyResidentialNA2650Sector 21 UlwePlot No 9911152017-07-312017-07-15
3Sai SapphireResidentialNA4000Sector 20 UlwePlot 178 18011622015-07-312015-07-02
4Sai SpringResidentialNA5000Sector 35G KhargharPlot 5 5A11482016-08-012016-07-21
5Sai MiracleResidentialNA4900Sector 35EPlot 16 17 1911102016-08-012016-07-22
6Sai CrystalResidentialNA6049Sector 35DPlot 45 52 52A11662016-10-012016-09-30
7Sai WonderResidentialNA2200Sector 35F KhargharPlot 4 51952017-07-012017-05-09
8Sai SolitaireResidentialNA3400Sector 35H KhargharPlot 4 51832017-01-012016-06-26
9Sai MannatResidentialNA13759Sector 34APlot 1 1A 1B1 1B2 1B3 1B613252017-07-312017-07-16

Member Information

Member Name Designation Photo
Manish Madhu Bathija Partner View Photo
Amit Madhu Bathija Partner View Photo
Madhu Bhagwandas Bathija Partner View Photo

Project

SAI SUNCITY PHASE 1
New Project
30/12/2026
No
Others
Yes
33part,61,62/1part
24 Meter Road
Survey no 60
Survey no 35
Survey no 63
MAHARASHTRA
Konkan
Raigarh
Panvel
Ghot
Suncity Road
Ghot
410206
8256
2
2
0
2092

FSI Details

15872
6832
22704.00

Bank Details

ICICI Bank
ICIC0000228

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
SAI SUNCITY PHASE 1 Ananta Namdeo Nighukar Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Upload Agreement / MoU Copy
4 Upload Agreement / MoU Copy
5 Upload Agreement / MoU Copy
6 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 119 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 As per CC
Water Conservation, Rain water Harvesting : YES 0 As per CC
Energy management : YES 0 As per CC
Fire Protection And Fire Safety Requirements : YES 0 As per CC
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 As per CC
Aggregate area of recreational Open Space : YES 0 As per CC
Open Parking : YES 0 As per CC
Water Supply : YES 0 As per CC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 As per CC
Storm Water Drains : YES 0 As per CC
Landscaping & Tree Planting : YES 0 As per CC
Street Lighting : YES 0 As per CC
Community Buildings : YES 0 As per CC
Treatment And Disposal Of Sewage And Sullage Water : YES 0 As per CC
Solid Waste Management And Disposal : YES 0 As per CC

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 SAI SUNCITY PHASE 1 Tower 1-VEGA 30/12/2026 1 1 1 16 1 5 59
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop 52.42 1 0
2 1BHK 41.8 47 34
3 2BHK 59.97 47 35
4 Shop 26.69 1 1
5 Shop 26.22 1 1
6 Shop 27.11 1 1
7 Shop 23.91 1 1
8 Shop 27.2 1 1
9 Shop 26.08 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 30
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 13
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 SAI SUNCITY PHASE 1 Tower 2-CARINA 30/12/2026 1 1 1 16 1 5 60
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop 22.06 1 1
2 Shop 31.31 1 1
3 Shop 22.82 1 1
4 Shop 24.31 1 1
5 Shop 21.75 1 1
6 Shop 25.45 1 1
7 Shop 25.2 1 1
8 Shop 26.36 1 1
9 1BHK 41.8 60 47
10 Shop 19.73 1 1
11 Shop 21.51 1 1
12 Shop 40.3 1 0
13 2BHK 59.97 58 43
14 Shop 18.18 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 30
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 13

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Spaceage Cosultants NA Architect
Hiten Sethi Architects NA Architect
Structural concept designs Pvt Ltd NA Engineer
Rangani and Company NA Chartered Accountant
YOGESH VITTHAL BADHE A52000000706 Real Estate Agent
SHADAB PORE A52000037595 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
1 Details of encumbrances
2 a Details of encumbrances concerned to Finance
1 b Details of encumbrances concerned to Legal
2 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
3 Building Plan Approval / NA Order for plotted development
4 Building Plan Approval / NA Order for plotted development
5 Building Plan Approval / NA Order for plotted development
6 Building Plan Approval / NA Order for plotted development
7 Building Plan Approval / NA Order for plotted development
8 Building Plan Approval / NA Order for plotted development
9 Building Plan Approval / NA Order for plotted development
10 Building Plan Approval / NA Order for plotted development
11 Building Plan Approval / NA Order for plotted development
12 Building Plan Approval / NA Order for plotted development
13 Building Plan Approval / NA Order for plotted development
14 Building Plan Approval / NA Order for plotted development
15 Building Plan Approval / NA Order for plotted development
16 Building Plan Approval / NA Order for plotted development
17 Building Plan Approval / NA Order for plotted development
18 Building Plan Approval / NA Order for plotted development
19 Building Plan Approval / NA Order for plotted development
20 Building Plan Approval / NA Order for plotted development
21 Building Plan Approval / NA Order for plotted development
22 Building Plan Approval / NA Order for plotted development
23 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
2 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement