MahaRERA Application

General Information

Other Than Individual

Organization

ROYAL DEVELOPERS
Partnership
NA
Do you have any Past Experience ?
No

Address Details

195/1+2
BRAHMAPUTRA CHS
UDYOGNAGAR
CHINCHWAD
CHINCHWAD
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411033

Organization Contact Details

09373905906

Past Experience Details

Member Information

Member Name Designation Photo
SUJIT VASANT PATIL Authorized Signatory View Photo
SAJID GULABHUSHAN BAGWAN Partner View Photo
TUKARAM CHANDAR TUPE Partner View Photo
GANESH BABANRAO PINJAN Partner View Photo
HIMATLAL RATANSHI POKAR Partner View Photo
ASHOK RATANSHI POKAR Partner View Photo
RAHUL SATYANARAYAN OZA Partner View Photo
DEVCHAND DHANJI CHAUDHARI Partner View Photo
KIRTIKUMAR DEVCHAND CHAUDHARI Partner View Photo
PRAVIN JAYANTIBHAI POKAR Partner View Photo
BHIMRAO RAMCHANDRA KALE Partner View Photo
HARESH DEVCHAND CHAUDHARI Partner View Photo

Project

HILL CREST PHASE II
New Project
30/06/2024
No
Others
Yes
97/1A/1A/1P,97/1A/1A/19P AT RAVET
12 MTRS ROAD AND THEREAFTER S NO 98
PROPERTY OF MS ADITYA ENTERPRISES
45 MTRS BRT ROAD
PROPERTY OF MS ADITYA ENTERPRISES
MAHARASHTRA
Pune
Pune
Haveli
Pimpri Chinchawad (M Corp.)
RAVET
RAVET
412101
2210.36
1
1
0
245.65

FSI Details

2328.78
4700.00
7028.78

Bank Details

HDFC BANK
HDFC0000437

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
HILL CREST PHASE II ADITYA ENTERPRISES Partnership Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 23 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 AS PER PCMC RULE
Energy management : YES 0 NA
Fire Protection And Fire Safety Requirements : YES 0 AS PER FIRE NOC (PCMC)
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 WILL BE DONE
Aggregate area of recreational Open Space : YES 0 NA
Open Parking : YES 0 NIL
Water Supply : YES 0 MUNICIPAL WATER SUPPLY
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 AS PER MUNCIPAL DRAINAGE NOC
Storm Water Drains : YES 0 WILL BE DONE
Landscaping & Tree Planting : YES 0 AS PER MUNICIPAQL GARDEN RULES
Street Lighting : YES 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 AS PER MUNICIPAL RULES
Solid Waste Management And Disposal : YES 0 AS PER DRAINAGE NOC (PCMC)

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 HILL CREST PHASE II HILL CREST PHASE II 30/06/2024 0 1 0 11 1 0 23
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Office space 24.75 1 0
2 Office space 26.14 1 0
3 114.11 1 0
4 Office space 13.44 1 0
5 Office space 14.74 1 0
6 Office space 15.02 1 0
7 Office space 21.11 1 0
8 Office space 21.12 1 0
9 2BHK 47.84 1 0
10 2BHK 55.32 11 5
11 2BHK 58.17 11 5
12 2BHK 61.32 20 10
13 2BHK 61.64 11 8
14 2BHK 67.4 9 5
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

60
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 40
11 Overall Percentage of Completion of the work done For the entire Building /Wing 58

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
ARCON ASSOCIATES NA Architect
JAYESH DEODHAR NA Engineer
N.K.ENTERPRISES NA Contractor
CA PANKAJ PATNI NA Chartered Accountant

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
3 Building Plan Approval / NA Order for plotted development
4 Building Plan Approval / NA Order for plotted development
5 Building Plan Approval / NA Order for plotted development
6 Building Plan Approval / NA Order for plotted development
7 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
5 Disclosure of sold/ booked inventory
6 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement