MahaRERA Application

General Information

Other Than Individual

Organization

Bhoomi & Arkade Associates
Partnership
NA
Do you have any Past Experience ?
No

Address Details

BHOOMI & ARKADE ASSOCIATES
ACROPOLIS
MMRDA LAYOUT SECTOR 3
BOLINJ DONGRI CHIKALDONGRI
VIRAR WEST
MAHARASHTRA
Konkan
Palghar
Vasai
Vasai-Virar City (M Corp)
401303

Organization Contact Details

02228874742
WWW.INACROPOLIS.COM

Past Experience Details

Member Information

Member Name Designation Photo
Amit Mangilal Jain Authorized Signatory View Photo
Chaitya Ajay Mehta Authorized Signatory View Photo
Arkade Developers Private Limited Arkade Developers Private Limited Partner View Photo
Bhoomi Shashwat Estate Private Limited Bhoomi Shashwat Estate Private Limited Partner View Photo

Project

ACROPOLIS 2
On-Going Project
31/12/2018
30/12/2022
Yes
Residential
No
37-46 PART 51-57PART 98-121PART 124, 145-147PART 368 and others as per title certificate attached
Acropolis 1
40METER WIDE ROAD
S R AND SHAH
OPEN PLOT
MAHARASHTRA
Konkan
Palghar
Vasai
Vasai-Virar City (M Corp)
Chilkhaldongri Road
Virar west
401303
2077
6
6
0
0

FSI Details

19946.34
0
19946.34

Bank Details

KOTAK MAHINDRA BANK
KKBK0000629

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 125 77 92

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 FACILITY AVAILABLE IN A LARGER LAYOUT
Water Conservation, Rain water Harvesting : YES 100 COMPLETED
Energy management : YES 100 POWER BACKUP FOR LIFT & STAIRCASE
Fire Protection And Fire Safety Requirements : YES 100 IN PROGRESS
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 IN PROGRESS
Podium with Clubhouse : YES 100 PART OF AGGREGATE AREA OF RECREATIONAL OPEN SPACE
Aggregate area of recreational Open Space : YES 100 FOR ENTIRE PROJECT OF TWO PHASES
Open Parking : NO 0 NA
Water Supply : YES 100 FACILITY START ONCE VVCMC WATER SUPPLY COMMENCES
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 COMPLETED
Storm Water Drains : YES 100 NA
Landscaping & Tree Planting : YES 100 FOR ENTIRE PROJECT OF TWO PHASES
Street Lighting : YES 100 FACILITY AVAILABLE IN THE LARGER LAYOUT
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 100 COMPLETED
Solid Waste Management And Disposal : YES 100 COMPLETED

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 ACROPOLIS 2 A 31/12/2021 0 1 0 16 1 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 31.95 15 14
2 1BHK 32.08 15 15
3 2BHK 47.38 15 13
4 SHOP 19.57 1 0
5 SHOP 18.60 1 0
6 SHOP 15.76 1 0
7 SHOP 19.72 1 0
8 SHOP 19.39 1 0
9 SHOP 26.04 1 0
10 SHOP 21.55 1 0
11 2BHK 45.30 15 15
12 2BHK 48.15 15 14
13 2BHK 49.11 12 11
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 ACROPOLIS 2 B 31/12/2021 0 1 0 16 1 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1.5BHK 42.37 15 15
2 SHOP 18.37 1 0
3 SHOP 20.58 1 0
4 SHOP 19.28 1 0
5 SHOP 18.05 1 0
6 SHOP 16.43 1 0
7 SHOP 18.90 1 0
8 SHOP 45.06 1 0
9 SHOP 57.46 1 0
10 1BHK 30.27 15 14
11 1BHK 31.36 30 30
12 1BHK 31.37 28 27
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 ACROPOLIS 2 C 31/12/2021 0 1 0 16 1 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 31.36 58 55
2 1.5BHK 42.37 15 15
3 SHOP1 12.52 1 0
4 1BHK 30.42 15 14
5 SHOP 13.54 1 0
6 SHOP 15.34 1 0
7 SHOP 19.78 1 0
8 SHOP 14.37 1 0
9 SHOP 14.81 1 0
10 SHOP 17.82 1 0
11 SHOP 44.65 1 0
12 SHOP 58.39 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
4 ACROPOLIS 2 D 31/12/2021 0 1 0 16 1 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 31.38 15 13
2 2BHK 48.37 15 13
3 SHOP 62.69 1 0
4 SHOP 16.73 1 0
5 SHOP 16.72 1 0
6 SHOP 12.60 1 0
7 SHOP 15.82 1 0
8 SHOP 8.74 1 0
9 SHOP 21.47 1 0
10 1BHK 30.78 15 14
11 1BHK 30.99 15 13
12 2BHK 48.15 13 4
13 2BHK 48.35 15 14
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
5 ACROPOLIS 2 E 31/12/2021 0 1 0 16 1 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 31.24 15 15
2 1BHK 31.95 56 54
3 1.5BHK 42.70 15 10
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
6 ACROPOLIS 2 F 31/12/2021 0 1 0 16 1 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 47.37 30 13
2 1BHK 31.90 13 11
3 2BHK 46.08 15 14
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SHREEHANS INFRA COM NA Contractor
REZA KABUL NA Architect
AJAY WADE AND ASSOCIATES NA Architect
HIREN M TANNA NA Engineer
GUPTA ENTERPRISE NA Contractor
HOUSE MAKER NA Contractor

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
ACROPOLIS 2 BOMBAY HIGH COURT 2901 Civil No Writ Petition NA 2015 PENDING FOR ADMISSION
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
5 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
2 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC006000000000224 Rakesh Jain View Orders
2 CC006000000000691 SANGEETA CHANDRASHEKHAR RAI View Orders
3 CC006000000054591 Hina Nimavat View Orders
4 CC006000000023768 Riyaz Jetham View Orders
5 CC006000000023768 Hitesh Shah and Seema Shah View Orders
6 CC006000000044090 Mr Sachin Prabhakar Kadam and Mrs Meena Sachin Kadam View Orders
7 CC006000000089573 Rehana Hussain / Sameer Hussain View Orders
8 CC006000000057038 Aarti Yeshwant Kamble View Orders
9 CC006000000057490 Austin Selvaraj Pillai View Orders
10 CC006000000057254 Suresh Sadanand Shetty View Orders
11 CC006000000057254 Savita Suresh Shetty View Orders
12 CC006000000057050 Vijay Lal Menaria View Orders
13 CC006000000057050 Premlata Menaria View Orders
14 CC006000000057050 Vijay Lal Menaria View Orders
15 CC006000000057050 Premlata Menaria View Orders
16 CC006000000193037 Hasmukh Waghela View Orders
17 CC006000000195151 Laxmi Madaswamy & anr View Orders
18 CC006000000195155 Velpandian Thevar View Orders
19 CC006000000196172 YASMEEN M NAIK View Orders
20 CC006000000197127 Arun Shankar Soneji View Orders
21 CC006000000197198 Hemant Lalwani View Orders
22 CC006000000197198 Renu Lalwani View Orders
23 CC006000000199349 Jayprakash R. Yadav View Orders
24 CC006000000198194 RAMESH KESHAV PANDEY View Orders
25 CC006000000198194 KESHAVPRASAD K PANDEY View Orders
26 CC006000000193875 Neelam Vishwakarma View Orders
27 CC006000000197239 Chintan Suresh Mehta View Orders
28 CC006000000197439 Abhijeet Santosh Sakhardande View Orders
29 CC006000000197439 Kavita Abhijeet Sakhardande View Orders
30 CC006000000197123 Mangal Maruti Nikanke View Orders
31 CC006000000197123 Sandeep M. Nikanke View Orders
32 CC006000000197123 Mahesh Maruti Nikanke View Orders
33 CC006000000196809 Mr. Vijay Valanju View Orders
34 CC006000000197107 Sachin L. Kulaye View Orders
35 CC006000000197107 Kalpana Lahu Kulaye View Orders
36 CC006000000197155 Avinash Ashokkumar Dubedi View Orders
37 CC006000000197155 Ashish Dwevedi View Orders
38 CC006000000197159 Vilas Ravindra Bhat View Orders
39 CC006000000197178 Vinod Nanalal Mody View Orders
40 CC006000000197178 Sanket J Gandhi View Orders
41 CC006000000197241 Chinmaya Sundar Mishra View Orders
42 CC006000000197337 Anthony Dasu Jerry View Orders
43 CC006000000197418 Ekta Shyamdhar Pandey View Orders
44 CC006000000197556 Danesh Jashanlal Karnani View Orders
45 CC006000000197556 Anisha Danesh Karnani View Orders
46 CC006000000198124 Felio Teogenes Dsilva View Orders
47 CC006000000198810 Hiren Jitendra Mistry View Orders
48 CC006000000198810 Mrs. Pinky Hiren Mistry View Orders
49 CC006000000199115 Noor Gulam Baig View Orders
50 CC006000000209432 Francis Savio DSa View Orders
51 CC006000000209432 Audrey Natalia Soares View Orders
52 CC006000000210230 Vasim Sultan Ahmad View Orders
53 CC006000000196893 SURESH SADANAND SHETTY View Orders
54 CC006000000197916 Austin Selvaraj Pillai View Orders
55 CC006000000197916 Sagaimary Pillai View Orders