MahaRERA Application

General Information

Other Than Individual

Organization

AKSHAR SPACE PVT LTD
Company
NA
Do you have any Past Experience ?
No

Address Details

230, 2ND FLOOR
BIG SPLASH
PLOT NO. 78/79, SECTOR 17
VASHI
NEAR NAVRATNA HOTEL
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
400703

Organization Contact Details

02227889991
www.akshardevelopers.com

Past Experience Details

Member Information

Member Name Designation Photo
BACHUBHAI DHARAMSHI ARETHIYA Authorized Signatory View Photo
HARI BACHUBHAI MUJAT Authorized Signatory View Photo
HEMANG JADAVJI SHAH Authorized Signatory View Photo
MEHUL JADAVJI SHAH Authorized Signatory View Photo

Project

GREEN WORLD
On-Going Project
31/12/2015
31/12/2019
Yes
Others
Yes
GUT NO.242, HISSA NO.1 TO 7
THANE BELAPUR ROAD
MIDC LAND
MIDC LAND
NODAL ROAD AND MRTP RAILWAY LINE
MAHARASHTRA
Konkan
Thane
Thane
Thane (M Corp.)
400708
34817
11
11
0
9933.91

FSI Details

52225.5
0
52225.50

Bank Details

HDFC BANK
HDFC0000540

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
GREEN WORLD MOUNT MARY BUILDERS Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 780 390 50

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 75 For internal driveway being develop
Water Conservation, Rain water Harvesting : YES 80 IN PROCESS
Energy management : YES 0 PENDING
Fire Protection And Fire Safety Requirements : YES 70 IN PROCESS
Electrical Meter Room, Sub-Station, Receiving Station : YES 80 PENDING
Aggregate area of recreational Open Space : YES 100 COMPLETED
Open Parking : YES 90 ALMOST COMPLETED
Water Supply : YES 0 TO BE PROVIDED BY NMMC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 75 IN PROCESS
Storm Water Drains : YES 100 TO BE PROVIDED BY NMMC/MIDC
Landscaping & Tree Planting : YES 85 IN PROCESS
Street Lighting : YES 0 PENDING
Community Buildings : YES 80 COMMUNITY CENTER MADE
Treatment And Disposal Of Sewage And Sullage Water : YES 0 IN PROCESS
Solid Waste Management And Disposal : YES 0 TO BE PROVIDED BY NMMC/MIDC

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 GREEN WORLD B WING 31/12/2019 0 1 0 23 1 22 17
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1.5 BHK 38.08 22 16
2 2 BHK 48.98 22 17
3 3 BHK 65.43 22 13
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 40
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

80
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 65
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 GREEN WORLD C WING 31/12/2019 0 1 0 23 1 22 17
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 48.05 44 34
2 3 BHK 68.22 22 12
3 3 BHK 69.15 22 11
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 40
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

80
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 65
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 GREEN WORLD D WING 31/12/2019 0 1 0 23 1 22 18
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 40
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

80
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 65
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
4 GREEN WORLD H WING 31/12/2019 0 1 0 23 1 22 16
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 45.39 66 45
2 3 BHK 72.55 22 14
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 40
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

80
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 65
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
5 GREEN WORLD I WING 31/12/2019 0 1 0 22 1 22 14
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1.5 BHK 37.37 84 68
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 40
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

80
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 65
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
6 GREEN WORLD A1 WING 0 1 0 23 1 0 8
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1.5 BHK 40.01 22 18
2 2.5 BHK 60.90 22 15
3 2.5 BHK 55.30 44 34
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 40
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

80
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 65
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
7 GREEN WORLD E WING 0 1 0 23 1 22 16
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 48.05 44 44
2 3 BHK 68.22 22 22
3 3 BHK 69.15 22 21
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 40
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

80
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 65
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
8 GREEN WORLD A2 WING 0 1 0 23 1 0 6
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 47.37 22 21
2 2 BHK 47.59 22 21
3 2.5 BHK 58.51 22 21
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 40
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

80
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 65
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
9 GREEN WORLD F WING 0 1 0 23 1 0 17
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 48.05 44 39
2 3 BHK 68.22 22 20
3 3 BHK 69.15 22 19
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 40
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

80
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 65
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
10 GREEN WORLD G WING 0 1 0 23 1 0 16
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 48.05 44 40
2 3 BHK 68.22 22 18
3 3 BHK 69.15 22 18
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 80
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 40
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

80
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 65
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
11 GREEN WORLD SHOPS 0 1 1 1 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 80.29 1 0
2 SHOP 86.10 1 0
3 SHOP 66.57 2 0
4 SHOP 59.70 3 3
5 SHOP 57.12 1 1
6 SHOP 57.66 1 1
7 SHOP 66.64 2 1
8 SHOP 65.96 30 13
9 SHOP 89.61 1 1
10 SHOP 97.73 1 0
11 SHOP 88.46 1 0
12 SHOP 111.11 1 0
13 SHOP 87.46 1 0
14 SHOP 93.13 1 1
15 SHOP 23.67 6 0
16 SHOP 23.43 3 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 85
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 90
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 70
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

90
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 70
11 Overall Percentage of Completion of the work done For the entire Building /Wing 70.5

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
NARESH RAMNIKLAL SATRA A51700001076 Real Estate Agent
Thirty Six Properties Pvt Ltd A51700001354 Real Estate Agent
Stellar Design Studio NA Architect
Satish Ahuja & Associates NA Architect
Generic Engineering & Const. Pvt. Ltd. NA Contractor
Structural Concept Designs Pvt. Ltd. NA Engineer
Arunkumar Landscape Architect Pvt. Ltd. NA Architect
SACHIN DNYANESHWAR MORE A51700002799 Real Estate Agent
Indiabulls Brokerage Limited A51900000082 Real Estate Agent

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
GREEN WORLD Honourable Thane Court 116/2014 Civil No Suit NA 2014 AMENDED PLAINT
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
2 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC006000000001586 Amit Shankar Bhalotia View Orders
2 CC006000000001573 Dhansukhlal K. Morabia View Orders
3 CC006000000001581 Rajesh Ramchandra Mahadik View Orders
4 CC006000000000089 VENKATA PHANINDRA KUMAR VALLURI View Orders
5 CC006000000000977 Ramesh P Singh View Orders
6 CC006000000000870 Abhijit Jadhav View Orders
7 CC006000000000950 HARSH KURRA & NEETU KURRA View Orders
8 CC006000000000985 P V S S VARMA View Orders
9 CC006000000000987 Somaji Kubal View Orders
10 CC006000000000733 SANDIP NAMDEO SHERKAR View Orders
11 CC006000000000733 SANDIP NAMDEO SHERKAR View Orders
12 CC006000000001014 Lalit Bhosale View Orders
13 CC006000000001407 HARVINDAR SINGH GAMBHIR View Orders
14 CC006000000001407 HARVINDAR SINGH GAMBHIR View Orders
15 CC006000000001597 Rajkishor Rajak View Orders
16 CC006000000001737 Richa Agrawal View Orders
17 CC006000000012669 Manojkumar Lalbahadur Singh View Orders
18 CC006000000012669 Anita Singh View Orders
19 CC006000000012758 P Satyanarayan View Orders
20 CC006000000022978 Souvik Das View Orders
21 CC006000000022905 Farzana Shaikh View Orders
22 CC006000000023649 Shrikant Muthineni View Orders
23 CC006000000001720 Sayee Subramanian View Orders
24 CC006000000001720 Compensation for delay in possession . View Orders
25 CC006000000023859 Deepak Anand View Orders
26 CC006000000012750 Nitin J Jaigude View Orders
27 CC006000000055006 Prathamesh Vijay Ternikar View Orders
28 CC006000000055006 Prathamesh Vijay Ternikar View Orders
29 CC006000000055006 Prathamesh Vijay Ternikar View Orders
30 CC006000000023844 Possession delayed View Orders
31 CC006000000001092 Deepa Dalvi View Orders
32 CC006000000054816 ABODH KUMAR PATHAK AND ANUPAMA A PATHAK View Orders
33 CC006000000054837 RAMESH JADHAV View Orders
34 CC006000000054842 Aditi Mazumder View Orders
35 CC006000000054969 VISHAL NALKUR View Orders
36 CC006000000054995 manoj kumar singh View Orders
37 CC006000000055000 Mr. Irfan Goundi View Orders
38 CC006000000023869 Varghese Samuel View Orders
39 CC006000000055342 Reshma Ritesh Shetty View Orders
40 CC006000000022920 Vishal Bhosale View Orders
41 CC006000000054663 Vinod Kanjan View Orders
42 CC006000000054976 DR. CHARUSHEELA ASHWIN GAJRA View Orders
43 CC006000000055015 Pranav Sawant View Orders
44 CC006000000023880 Tirupati Kodari View Orders
45 CC006000000055254 ASHISH KESHAVPRASAD CHATURVEDI View Orders
46 CC006000000055418 Patel Anjali Suryaprakash Reddy View Orders
47 CC006000000055426 Anis Abdul Kader Khan View Orders
48 CC006000000055331 Mr. Ramdas Date View Orders
49 CC006000000001294 Prashant Pandey View Orders
50 CC006000000055516 CC006000000055516 View Orders
51 CC006000000055774 Narendra Kumar View Orders
52 CC006000000023649 Shrikant Muthineni View Orders
53 CC006000000055404 Mr.Samson Pandi View Orders
54 CC006000000055404 Mr.Samson Pandi View Orders
55 CC006000000055404 Mr.Samson Pandi View Orders
56 CC006000000055476 JITENDRA SWARNKAR View Orders
57 CC006000000055452 Sayee Subramanian View Orders
58 CC006000000055144 Pritam Vilas Murudkar View Orders
59 CC006000000057112 KARUNAKAR GOVIND SHETTY View Orders
60 CC006000000057112 PRATHIMA KARUNAKAR SHETTY View Orders
61 CC006000000057103 RATNAKAR GOVIND SHETTY View Orders
62 CC006000000057103 VIMALA RATNAKAR SHETTY View Orders
63 CC006000000057099 KARUNAKAR GOVIND SHETTY View Orders
64 CC006000000057099 PRATHIMA KARUNAKAR SHETTY View Orders
65 CC006000000057363 Amit Kitey View Orders
66 CC006000000023887 Niladri Sen View Orders
67 CC006000000056366 Rohan Tadke View Orders
68 CC006000000056364 zahid patel View Orders
69 CC006000000078624 Prashant Pandey View Orders
70 CC006000000078630 MANOJ KUMAR MATHUR View Orders
71 CC006000000110676 Anis Abdul Kader Khan View Orders
72 CC006000000089795 SANA HOSPITALITY SERVICES PVT. LTD. View Orders
73 CC006000000100580 PRAHLAD SINGH View Orders
74 CC006000000100580 BABITA PRAHLAD SINGH View Orders
75 CC006000000193026 Siddharth kochar & Richa Kochar View Orders
76 CC006000000192719 Mr Dhanesh Raheja and Mrs Devika Raheja View Orders
77 CC006000000100458 S N DAMANI HOLDINGS P LTD View Orders
78 CC006000000192263 S.N.DAMANI HOLDINGS PRIVATE LIMITED View Orders
79 CC006000000171806 Rameshchandra L. Mahajan & Ors View Orders
80 CC006000000023880 Tirupati Kodari View Orders
81 CC006000000195420 Sandeep Daga View Orders
82 CC006000000198071 Allwyn Cyril Dcosta View Orders
83 CC006000000198320 PRADIP SHRIPAT PATANKAR View Orders
84 CC006000000196821 Tajbar Aslam Saudagar View Orders
85 CC006000000196424 KUNVARJIT SINGH MALKEET SINGH MATHARU KARTA OF MALKEET SINGH G MATHARU HUF View Orders
86 CC006000000196427 MALKEET SINGH G MATHARU HUF THROUGH KARTA KUNVARJIT SINGH MALKEET SINGH MATHARU View Orders
87 CC006000000171806 Rameshchandra L. Mahajan & Ors View Orders
88 CC006000000100580 PRAHLAD SINGH View Orders
89 CC006000000100580 BABITA PRAHLAD SINGH View Orders
90 CC006000000078630 MANOJ KUMAR MATHUR View Orders
91 CC006000000110676 Anis Abdul Kader Khan View Orders
92 CC006000000396391 Shakuntala Atmaram Deokar View Orders
93 CC006000000078630 MANOJ KUMAR MATHUR View Orders
94 CC006000000078624 Prashant Pandey View Orders
95 CC006000000171806 Rameshchandra L. Mahajan & Ors View Orders
96 CC006000000209889 Nikhil Shinde View Orders
97 CC006000000209890 Vidyadhar Naik View Orders
98 CC006000000209882 Shailesh Kadam View Orders
99 CC006000000209886 Sameer Vagal View Orders
100 CC006000000209888 Milind Pawar View Orders