MahaRERA Application

General Information

Other Than Individual

Organization

VEENA REALCON PRIVATE LIMITED
Company
NA
Do you have any Past Experience ?
No

Address Details

1,2 & 3
VEENA SARANG COMPLEX
SAIBABA NAGAR EXTN. ROAD
BORIVALI (WEST)
OPP. KVC CLUB
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Borivali
400092

Organization Contact Details

02261069800

Past Experience Details

Member Information

Member Name Designation Photo
NIKUNJ HARESH SANGHAVI Managing Director View Photo
HARESH NATVARLAL SANGHAVI Authorized Signatory View Photo

Project

Veena Serenity
On-Going Project
01/12/2020
01/12/2021
Yes
Residential
No
58-PT
Chawl
12 Mt wide internal DP road no 4
Samaj Mandir Hall
9 Mt wide existing pathway
MAHARASHTRA
Konkan
Mumbai Suburban
Kurla
Kurla
Sahakar Nagar Road No.3
Chambur
400071
3067.29
5
5
0
0

FSI Details

17685
0
17685.00

Bank Details

RBL Bank Limited
RATN0000062

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 212 118 50

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 By Developer
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 75 By Developer
Electrical Meter Room, Sub-Station, Receiving Station : YES 50 By Developer
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 50 By BMC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 35 By Developer
Storm Water Drains : YES 45 By BMC
Landscaping & Tree Planting : YES 0 By Developer
Street Lighting : YES 25 By BMC
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 By Developer
Solid Waste Management And Disposal : YES 0 By Developer

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Veena Serenity Wing A 01/12/2020 1 1 0 16 0 0 66
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 72.6 14 9
2 2BHK 58.64 42 36
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 75
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 75
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

75
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 75
11 Overall Percentage of Completion of the work done For the entire Building /Wing 80
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Veena Serenity Wing B 01/12/2020 1 1 0 16 0 0 29
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 39.83 43 43
2 2BHK 53.80 15 14
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 25
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 25
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

40
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50
11 Overall Percentage of Completion of the work done For the entire Building /Wing 60
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 Veena Serenity Wing C 1 1 0 16 0 0 57
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 72.6 14 4
2 2BHK 58.63 15 10
3 2 BHK 58.64 27 21
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 50
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 15
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 35
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

35
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 25
11 Overall Percentage of Completion of the work done For the entire Building /Wing 56
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
4 Veena Serenity Wing D 01/12/2020 1 1 0 16 0 0 32
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 53.10 15 15
2 2BHK 53.11 14 13
3 2BHK 53.17 30 30
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 80
11 Overall Percentage of Completion of the work done For the entire Building /Wing 88
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
5 Veena Serenity Wing E 01/12/2020 1 1 0 16 0 0 28
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 53.10 29 28
2 2BHK 53.17 30 30
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 85
11 Overall Percentage of Completion of the work done For the entire Building /Wing 88.5

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Jitendra G Dewoolkar NA Architect
RAHEJA ESTATE AGENCY A51800003110 Real Estate Agent
QUICK HOMES PROPERTY ADVISORY A51800005188 Real Estate Agent
Mulraj Ratanshi Thakker A51900007257 Real Estate Agent
Kishore Manohar Jethe A51800012466 Real Estate Agent
Rajesh vitthal Doiphode A51900010215 Real Estate Agent
Bhumi Laxman Shah A51800009972 Real Estate Agent

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
Veena Serenity High Court of Bombay 460 Civil No Suit NA 2014 Disposed off
NA
Veena Serenity City Civil Court Mumbai 1935 Civil No Suit NA 2015 Disposed off
NA
Veena Serenity Consumer Forum CC/16/1188 Others No Suit NA 2016 Disposed off
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
8 Building Plan Approval (IOD)
9 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
4 Proforma of Allotment letter
5 Proforma of Allotment letter
6 Proforma of Allotment letter
7 Proforma of Allotment letter
8 Proforma of Allotment letter
9 Proforma of Allotment letter
10 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC006000000054617 Shivkumar Shankar Inamdar View Orders
2 CC006000000054913 vijay shekhar View Orders
3 CC006000000023553 Bais Taj Kumar View Orders
4 CC006000000023553 Chandrakaushi Purohit View Orders
5 CC006000000023946 Narendra Ramchand Ochani View Orders
6 CC006000000171842 Mr. John Dolphin Sequeira Through His Power Of Attorney Mrs. Michelle Sequeira View Orders
7 CC006000000171842 Mrs. Michelle Sequeira View Orders