MahaRERA Application

General Information

Other Than Individual

Organization

VISION CREATIVE PROMOTERS
Partnership
NA
Do you have any Past Experience ?
No

Address Details

OFFICE NO.03
SHUBH COMPLEX
PLOT NO. SDC-6, SECTOR NO. 01
INDRAYANI NAGAR, BHOSARI
ABOVE AXIS BANK
MAHARASHTRA
Pune
Pune
Haveli
BHOSARI
411039

Organization Contact Details

07774082765

Past Experience Details

Member Information

Member Name Designation Photo
NITESHKUMAR SURESHBHAI PATEL Partner View Photo
VIPULKUMAR CHIMANLAL BHAVANI Authorized Signatory View Photo
MANISH SURESHBHAI PATEL Partner View Photo
MAHENDRA SURESH THAKUR Partner View Photo
JAYESHKUMAR SHANTILAL PATEL Partner View Photo
RAMESHKUMAR VITTHALBHAI PATEL Partner View Photo
JAYKUMAR BIPINBHAI PATEL Partner View Photo

Project

VISION ARISTO
New Project
31/03/2026
No
Others
No
39(P), KIWALE
18 METER ROAD
SURVEY NO 39
12 METER ROAD
SURVEY NO 39
MAHARASHTRA
Pune
Pune
Haveli
Pimpri Chinchawad (M Corp.)
SR NO 39 NEAR MUKAI CHOWK
KIWALE
412101
10000
4
4
0
1000

FSI Details

38930.83
5738.22
44669.05

Bank Details

HDFC BANK LTD
HDFC0001795

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 0 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 Will be completed before Completion
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 0 Will be completed before Completion
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 Will be completed before Completion
Aggregate area of recreational Open Space : YES 0 Will be completed before Completion
Open Parking : YES 0 Will be completed before Completion
Water Supply : YES 0 Will be provided by PCMC after Completion
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 Will be completed before Completion
Storm Water Drains : YES 0 Will be completed before Completion
Landscaping & Tree Planting : YES 0 Will be completed before Completion
Street Lighting : NO 0 NA
Community Buildings : YES 0 Will be completed before Completion
Treatment And Disposal Of Sewage And Sullage Water : YES 0 Will be completed before Completion
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 VISION ARISTO A BUILDING 30/06/2025 1 1 0 20 1 0 76
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop 20.90 1 1
2 Shop 22.86 1 1
3 2BHK 71.13 6 6
4 Shop 27.88 2 2
5 Shop 23.20 1 1
6 Shop 23.03 2 2
7 Shop 21.55 1 1
8 3BHK 80.93 70 70
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 VISION ARISTO B BUILDING 30/06/2025 1 1 0 20 1 54 95
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop 20.90 1 1
2 Shop 24.57 4 4
3 3BHK 81.62 3 3
4 Shop 23.76 4 4
5 Shop 38.26 1 1
6 Shop 46.91 2 2
7 Shop 26.27 2 1
8 2BHK 61.78 142 142
9 2BHK 62.01 4 4
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 VISION ARISTO C BUILDING 31/03/2026 1 1 0 20 1 65 85
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 61.78 126 126
2 2BHK 49.81 12 12
3 3BHK 81.68 3 3
4 Shop 23.76 4 4
5 2BHK 49.90 8 7
6 Shop 24.57 4 4
7 Shop 46.91 2 2
8 Shop 20.90 1 1
9 Shop 38.27 1 1
10 Shop 26.27 2 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
4 VISION ARISTO D BUILDING 31/03/2026 1 1 0 20 1 0 76
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop 20.90 1 1
2 Shop 23.20 1 1
3 2BHK 71.12 6 6
4 3BHK 80.93 70 68
5 Shop 26.00 1 0
6 Shop 21.55 1 1
7 Shop 25.51 1 1
8 Shop 18.53 2 2
9 Shop 22.86 1 1
10 Shop 27.88 2 2
11 Shop 48.30 1 1
12 Shop 16.84 2 2
13 Shop 17.39 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
MS MAHENDRA THAKUR AND ASSOCIATES NA Architect
R K RANDHAVE CONSULTANTS NA Engineer
BANKIM PATEL & ASSOCIATES NA Chartered Accountant
Ravi Ranjan Kumar Gautam A52100007332 Real Estate Agent
VIMALESH KUMAR SINGH A52100021675 Real Estate Agent
SPACEINDIA NEST PRIVATE LIMITED A52100002248 Real Estate Agent
SWATI JAIN A52100008300 Real Estate Agent
Manvendra Tripathi A52100009070 Real Estate Agent
PRANOO REALTY A52100000324 Real Estate Agent
Yogesh Pandurang Ingole A52100021313 Real Estate Agent
PROPINN PROPERTIES PRIVATE LIMITED A52100011114 Real Estate Agent
AKSHAY ARUN KULKARNI A52100017562 Real Estate Agent
Saiphan Basulal Shaikh A52100017405 Real Estate Agent
Kalp Sureshbhai Patel A52100025555 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
2 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
8 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
7 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement