MahaRERA Application

General Information

Other Than Individual

Organization

MAHAVEER CONSTRUCTION
Partnership
NA
Do you have any Past Experience ?
No

Address Details

101
JEEVAN VAIBHAV
M G X ROAD NO 4
KANDIVALI WEST
BEHIND PATEL NAGAR
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Borivali
400067

Organization Contact Details

02228657697
WWW.MAHAVEERCONSTRUCTION.COM

Past Experience Details

Member Information

Member Name Designation Photo
PINAKIN SHAH Authorized Signatory View Photo

Project

Solitaire Edge
New Project
31/12/2026
No
Others
No
CTS NO 3pt, 4pt, 5pt, 6pt and 7pt
CTS NO 8
CTS NO 3
EXISTING SUHAS MODI ROAD
27 45 MTR WIDE DP ROAD RAJGURU FLYOVER
MAHARASHTRA
Konkan
Mumbai Suburban
Borivali
Borivali
VILLAGE - WADHAWAN
KANDIVALI EAST
400101
5820.61
1
1
0
0

FSI Details

1354.01
9282.76
10636.77

Bank Details

AXIS BANK
UTIB0001578

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 85 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 WIP
Energy management : YES 0 WIP
Fire Protection And Fire Safety Requirements : YES 0 WIP
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 WIP
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 0 WIP
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 WIP
Storm Water Drains : YES 0 WIP
Landscaping & Tree Planting : YES 0 WIP
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 0 WIP
Solid Waste Management And Disposal : YES 0 WIP

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Solitaire Edge Solitaire Edge 31/12/2026 0 1 9 35 1 0 85
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 37.35 72 17
2 1BHK 37.81 65 14
3 2BHK 55.64 20 8
4 2BHK 58.81 24 8
5 SHOPPING MART 476.08 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 0
2 X number of Basement(s) and Plinth 0
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 0
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 0

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
M/s. STS Consultants LLP NA Engineer
NEHALI & CO NA Chartered Accountant
VISHWAS SATODIA NA Architect

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
4 Copy of Layout Approval (in case of layout)
5 Copy of Layout Approval (in case of layout)
6 Copy of Layout Approval (in case of layout)
7 Copy of Layout Approval (in case of layout)
8 Copy of Layout Approval (in case of layout)
9 Copy of Layout Approval (in case of layout)
10 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of the allotment letter and agreement for sale
2 Proforma of the allotment letter and agreement for sale
3 Proforma of the allotment letter and agreement for sale
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical