Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
1 |
GODREJ URBAN PARK
|
Tower 1
|
31/03/2026
|
3
|
1
|
0
|
16
|
1 |
0 |
81 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
Shop |
141.31 |
1 |
1 |
2 |
3BHK |
85.97 |
14 |
3 |
3 |
Shop |
22.53 |
1 |
1 |
4 |
Shop |
26.05 |
1 |
1 |
5 |
Shop |
94.61 |
1 |
1 |
6 |
3BHK |
83.91 |
13 |
12 |
7 |
3BHK |
84.13 |
15 |
6 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
30
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
80
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
95
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
70.5
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
2 |
GODREJ URBAN PARK
|
Tower 2
|
31/03/2026
|
3
|
1
|
0
|
16
|
1 |
1 |
76 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
Shop |
20.11 |
1 |
1 |
2 |
Shop |
21.87 |
1 |
1 |
3 |
Shop |
25.82 |
1 |
1 |
4 |
Shop |
26.28 |
1 |
1 |
5 |
Shop |
28.36 |
1 |
1 |
6 |
Shop |
32.98 |
1 |
1 |
7 |
Shop |
40.98 |
1 |
1 |
8 |
3BHK |
86.07 |
1 |
0 |
9 |
3BHK |
86.62 |
12 |
11 |
10 |
3BHK |
86.65 |
1 |
1 |
11 |
3BHK |
87.22 |
12 |
12 |
12 |
3BHK |
86.90 |
14 |
11 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
30
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
70
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
95
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
69.5
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
3 |
GODREJ URBAN PARK
|
Tower 3
|
31/03/2026
|
3
|
1
|
0
|
16
|
1 |
0 |
78 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
Shop |
23.02 |
1 |
1 |
2 |
Shop |
25.84 |
1 |
1 |
3 |
Shop |
11.32 |
1 |
1 |
4 |
Shop |
17.53 |
1 |
1 |
5 |
Shop |
17.54 |
1 |
1 |
6 |
Shop |
9.45 |
1 |
1 |
7 |
Shop |
29.01 |
1 |
1 |
8 |
Shop |
21.60 |
1 |
1 |
9 |
Shop |
21.73 |
1 |
1 |
10 |
Shop |
21.32 |
1 |
1 |
11 |
Shop |
31.60 |
1 |
1 |
12 |
Shop |
108.30 |
1 |
1 |
13 |
Shop |
123.02 |
1 |
1 |
14 |
2BHK |
55.67 |
12 |
12 |
15 |
2BHK |
56.41 |
1 |
1 |
16 |
2BHK |
56.33 |
1 |
1 |
17 |
1BHK |
40.47 |
15 |
15 |
18 |
2BHK |
55.51 |
12 |
12 |
19 |
2BHK |
55.76 |
12 |
12 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
30
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
70
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
95
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
69.5
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
4 |
GODREJ URBAN PARK
|
Tower 4
|
31/03/2026
|
3
|
1
|
0
|
16
|
1 |
0 |
75 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
Shop |
38.45 |
1 |
1 |
2 |
Shop |
38.99 |
1 |
1 |
3 |
Studio |
31.16 |
1 |
0 |
4 |
Shop |
9.93 |
1 |
1 |
5 |
Shop |
12.30 |
1 |
1 |
6 |
Shop |
15.32 |
1 |
1 |
7 |
Shop |
15.34 |
1 |
1 |
8 |
Shop |
22.02 |
2 |
2 |
9 |
Shop |
27.86 |
1 |
1 |
10 |
Shop |
29.39 |
1 |
1 |
11 |
1BHK |
40.48 |
14 |
8 |
12 |
2BHK |
55.48 |
14 |
5 |
13 |
2BHK |
58.78 |
13 |
12 |
14 |
2BHK |
58.96 |
13 |
10 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
40
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
60
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
10
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
41
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
5 |
GODREJ URBAN PARK
|
Tower 5
|
31/03/2026
|
3
|
1
|
0
|
16
|
1 |
0 |
76 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
Shop |
62.04 |
1 |
1 |
2 |
Shop |
20.59 |
1 |
1 |
3 |
Shop |
20.89 |
1 |
1 |
4 |
Shop |
12.45 |
1 |
1 |
5 |
Shop |
15.53 |
1 |
1 |
6 |
Shop |
16.18 |
1 |
1 |
7 |
Shop |
17.98 |
1 |
1 |
8 |
Shop |
18.12 |
1 |
1 |
9 |
Shop |
19.40 |
1 |
1 |
10 |
Shop |
61.72 |
1 |
1 |
11 |
Studio |
31.16 |
1 |
1 |
12 |
1BHK |
40.48 |
14 |
6 |
13 |
2BHK |
55.48 |
14 |
7 |
14 |
2BHK |
58.78 |
13 |
12 |
15 |
2BHK |
58.96 |
13 |
11 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
40
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
60
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
10
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
41
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
6 |
GODREJ URBAN PARK
|
Tower 6
|
31/03/2026
|
3
|
1
|
0
|
15
|
1 |
0 |
112 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
Shop |
17.94 |
1 |
1 |
2 |
Shop |
20.94 |
1 |
1 |
3 |
1BHK |
40.48 |
13 |
8 |
4 |
Shop |
32.88 |
1 |
1 |
5 |
Shop |
36.34 |
1 |
1 |
6 |
Shop |
94.92 |
1 |
1 |
7 |
1BHK |
41.66 |
2 |
0 |
8 |
2BHK |
57.16 |
1 |
0 |
9 |
Shop |
9.11 |
1 |
1 |
10 |
Shop |
12.18 |
1 |
1 |
11 |
Shop |
13.26 |
1 |
1 |
12 |
Shop |
13.55 |
1 |
1 |
13 |
Shop |
14.49 |
1 |
1 |
14 |
Shop |
14.69 |
1 |
1 |
15 |
1BHK |
40.47 |
12 |
7 |
16 |
Shop |
18 |
1 |
1 |
17 |
Shop |
20.52 |
1 |
1 |
18 |
1BHK |
40.33 |
12 |
8 |
19 |
2BHK |
55.52 |
25 |
10 |
20 |
1BHK |
40.17 |
14 |
5 |
21 |
1BHK |
41.51 |
1 |
0 |
22 |
Shop |
111.30 |
1 |
1 |
23 |
Shop |
17.98 |
1 |
1 |
24 |
Shop |
16.36 |
1 |
1 |
25 |
Shop |
17.11 |
1 |
1 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
75
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
30
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
60
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
10
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
37.5
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
7 |
GODREJ URBAN PARK
|
Tower 7
|
31/03/2026
|
3
|
1
|
0
|
15
|
1 |
0 |
89 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHK |
58.81 |
28 |
0 |
2 |
3BHK |
82.84 |
1 |
0 |
3 |
3BHK |
83.36 |
12 |
0 |
4 |
3BHK |
87.19 |
1 |
0 |
5 |
3BHK |
87.71 |
12 |
0 |
6 |
Shop |
32.77 |
1 |
1 |
7 |
Shop |
37.05 |
1 |
1 |
8 |
Shop |
20.95 |
2 |
2 |
9 |
Shop |
21.77 |
1 |
1 |
10 |
Shop |
23.41 |
1 |
1 |
11 |
Shop |
23.69 |
1 |
1 |
12 |
Shop |
26.58 |
1 |
1 |
13 |
Shop |
28.45 |
1 |
1 |
14 |
Shop |
30.54 |
1 |
1 |
15 |
Shop |
32.15 |
1 |
1 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
38
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
20
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
25.8
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
8 |
GODREJ URBAN PARK
|
Tower 8
|
31/03/2026
|
3
|
1
|
0
|
15
|
1 |
0 |
79 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
3BHK |
83.89 |
1 |
0 |
2 |
3BHK |
84.41 |
12 |
0 |
3 |
3BHK |
86.52 |
1 |
0 |
4 |
3BHK |
87.04 |
12 |
0 |
5 |
Shop |
21.58 |
1 |
1 |
6 |
Shop |
24.65 |
1 |
1 |
7 |
Shop |
26.62 |
1 |
1 |
8 |
Shop |
26.94 |
1 |
1 |
9 |
3BHK |
87.66 |
14 |
0 |
10 |
Shop |
28.81 |
1 |
1 |
11 |
Shop |
29.39 |
1 |
1 |
12 |
Shop |
29.83 |
1 |
1 |
13 |
Shop |
31.75 |
1 |
1 |
14 |
Shop |
18.02 |
1 |
1 |
15 |
Shop |
28.45 |
1 |
1 |
16 |
Shop |
18.71 |
1 |
1 |
17 |
Shop |
20.99 |
1 |
1 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
19
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
20
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
23.9
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
9 |
GODREJ URBAN PARK
|
Tower 9
|
31/03/2026
|
3
|
1
|
0
|
15
|
1 |
0 |
95 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHK |
61.16 |
13 |
0 |
2 |
2BHK |
61.75 |
1 |
0 |
3 |
Shop |
23.32 |
1 |
1 |
4 |
Shop |
25.04 |
1 |
1 |
5 |
Shop |
142 |
1 |
1 |
6 |
Studio |
25.75 |
1 |
0 |
7 |
Shop |
77.66 |
1 |
1 |
8 |
1BHK |
36.83 |
13 |
1 |
9 |
1BHK |
38.95 |
15 |
0 |
10 |
1BHK |
37.55 |
1 |
0 |
11 |
1BHK |
39.82 |
15 |
0 |
12 |
2BHK |
58.84 |
13 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
6
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
0
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
20
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
0
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
0
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
22.6
|
|