MahaRERA Application

General Information

Other Than Individual

Organization

Godrej Landmark Redevelopers Private Limited
Company
NA
Do you have any Past Experience ?
No

Address Details

5th Floor
Godrej One
Pirojshanagar
Vikhroli East
Off Eastern Express Highway
MAHARASHTRA
Konkan
Mumbai Suburban
Kurla
Kurla
400079

Organization Contact Details

02261198500

Past Experience Details

Member Information

Member Name Designation Photo
Pranav Chaudhary Authorized Signatory View Photo

Project

Godrej Central
On-Going Project
30/03/2019
30/03/2021
Yes
Residential
Yes
CTS 49/pt, 56, 54, 45, 58/pt
CTS No 58 1834 pt and Eastern Express Highway
CTS No 49 pt
18 meter wide road and railway line
9 meter wide Sahakar Nagar Road No 1 and CTS No 53
MAHARASHTRA
Konkan
Mumbai Suburban
Kurla
Kurla
400071
17541.98
20
20
0
0

FSI Details

81664.14
1033.90
82698.04

Bank Details

Axis Bank Limited
UTIB0001394

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Godrej Central Shell Tower Co-operative Housing Society Limited Societies Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Upload Agreement / MoU Copy
4 Upload Agreement / MoU Copy
5 Upload Agreement / MoU Copy
6 Upload Agreement / MoU Copy
7 Upload Agreement / MoU Copy
8 Upload Agreement / MoU Copy
9 Upload Agreement / MoU Copy
10 Upload Agreement / MoU Copy
11 Upload Agreement / MoU Copy
12 Upload Agreement / MoU Copy
13 Upload Agreement / MoU Copy
14 Upload Agreement / MoU Copy
15 Upload Agreement / MoU Copy
16 Upload Agreement / MoU Copy
17 Upload Agreement / MoU Copy
18 Upload Agreement / MoU Copy
19 Upload Agreement / MoU Copy
20 Upload Agreement / MoU Copy
21 Upload Agreement / MoU Copy
22 Upload Agreement / MoU Copy
23 Upload Agreement / MoU Copy
24 Upload Agreement / MoU Copy
25 Upload Agreement / MoU Copy
26 Upload Agreement / MoU Copy
27 Upload Agreement / MoU Copy
28 Upload Agreement / MoU Copy
29 Upload Agreement / MoU Copy
30 Upload Agreement / MoU Copy
31 Upload Agreement / MoU Copy
32 Upload Agreement / MoU Copy
33 Upload Agreement / MoU Copy
34 Upload Agreement / MoU Copy
35 Upload Agreement / MoU Copy
36 Upload Agreement / MoU Copy
37 Upload Agreement / MoU Copy
38 Upload Agreement / MoU Copy
39 Upload Agreement / MoU Copy
40 Upload Agreement / MoU Copy
41 Upload Agreement / MoU Copy
42 Upload Agreement / MoU Copy
43 Upload Agreement / MoU Copy
44 Upload Agreement / MoU Copy
45 Upload Agreement / MoU Copy
46 Upload Agreement / MoU Copy
47 Upload Agreement / MoU Copy
48 Upload Agreement / MoU Copy
49 Upload Agreement / MoU Copy
50 Upload Agreement / MoU Copy
51 Upload Agreement / MoU Copy
52 Upload Agreement / MoU Copy
53 Upload Agreement / MoU Copy
54 Upload Agreement / MoU Copy
55 Upload Agreement / MoU Copy
56 Upload Agreement / MoU Copy
57 Upload Agreement / MoU Copy
58 Upload Agreement / MoU Copy
59 Upload Agreement / MoU Copy
60 Upload Agreement / MoU Copy
61 Upload Agreement / MoU Copy
62 Upload Agreement / MoU Copy
63 Upload Agreement / MoU Copy
64 Upload Agreement / MoU Copy
65 Upload Agreement / MoU Copy
66 Upload Agreement / MoU Copy
67 Upload Agreement / MoU Copy
68 Upload Agreement / MoU Copy
69 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Godrej Central M Patankar Buildcons Private Limited Company Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Upload Agreement / MoU Copy
4 Upload Agreement / MoU Copy
5 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Godrej Central Kamla Landmarc Property Leasing and Finance Pvt Li Company Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Upload Agreement / MoU Copy
3 Upload Agreement / MoU Copy
4 Upload Agreement / MoU Copy
5 Upload Agreement / MoU Copy
6 Upload Agreement / MoU Copy
7 Upload Agreement / MoU Copy
8 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 1044 533 69

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 Complete
Water Conservation, Rain water Harvesting : YES 100 Water tank provided
Energy management : YES 100 IGBC COMPLIANT
Fire Protection And Fire Safety Requirements : YES 100 AS PER CFO REQUIREMENTS
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 Complete
CLUB HOUSE : YES 100 Complete
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : YES 100 BY DEVELOPER
Water Supply : YES 100 TO BE SUPPLIED BY BMC
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 WORK IN PROGRESS
Storm Water Drains : YES 100 Complete
Landscaping & Tree Planting : YES 100 Complete
Street Lighting : YES 100 IN MCGM SCOPE
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 100 Complete
Solid Waste Management And Disposal : YES 100 WORK IN PROGRESS

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Godrej Central A 30/09/2020 2 1 0 16 1 5 85
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 70.06 16 16
2 2.5 BHK 83.77 15 15
3 2 BHK 72.25 16 16
4 2 BHK 72.18 14 14
5 2.5 BHK 83 1 1
6 1 BHK 55.17 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Godrej Central B 10/11/2018 2 1 0 16 1 6 146
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3 BHK 105.38 1 1
2 3 BHK 106.03 15 15
3 3 BHK 107.43 15 15
4 3 BHK 106.63 15 15
5 3 BHK 107.45 15 15
6 3 BHK 106.02 1 1
7 3 BHK 106.82 2 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 Godrej Central C 10/11/2018 2 1 0 16 1 5 82
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 72.19 14 14
2 2.5 BHK 83.77 15 15
3 2.5 BHK 82.98 1 1
4 2 BHK 72.18 30 30
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
4 Godrej Central D 10/11/2018 2 1 0 16 1 6 82
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2 BHK 71.92 16 16
2 2.5 BHK 83.70 14 14
3 2 BHK 70.06 14 14
4 2 BHK 72.18 16 14
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
5 Godrej Central E 10/11/2018 2 1 0 16 1 6 101
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2.5 BHK 81.34 15 15
2 3 BHK 106.86 2 2
3 2.5 BHK 80.69 1 1
4 3 BHK 107.49 30 30
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
6 Godrej Central F 2 1 0 16 1 5 70
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2.5 BHK 83.71 15 15
2 2.5 BHK 81.35 15 15
3 2 BHK 72.19 16 16
4 2.5 BHK 82.92 1 1
5 2.5 BHK 80.65 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
7 Godrej Central G 30/09/2020 2 1 0 16 1 6 116
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3 BHK 107.49 30 30
2 2 BHK 72.19 32 32
3 3 BHK 106.87 2 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
8 Godrej Central BUILDING NO 14 TOWER I 30/09/2020 1 1 0 16 1 3 8
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 44.52 16 16
2 2BHK 65.59 15 15
3 2 BHK 68.58 16 16
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
9 Godrej Central PRIVE TOWER J BUILDING NO 39 30/09/2020 1 1 0 14 1 14 19
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3 BHK 100.76 28 28
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
10 Godrej Central H 10/11/2018 1 1 0 14 1 0 47
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 44.14 14 13
2 2 BHK 67.99 14 14
3 2 BHK 63.38 14 14
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
11 Godrej Central L 1 1 0 14 1 0 39
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3 BHK 91.84 13 13
2 3 BHK 91.84 14 14
3 3 BHK 91.58 14 14
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
12 Godrej Central M 1 1 0 14 1 0 39
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3 BHK 91.84 14 14
2 3 BHK 88.98 13 13
3 3 BHK 91.86 14 14
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
13 Godrej Central N 30/09/2020 1 1 0 14 1 0 39
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3 BHK 91.83 14 14
2 1 BHK 37.27 1 1
3 3 BHK 91.72 13 13
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
14 Godrej Central O 1 1 0 14 1 0 39
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3 BHK 91.74 13 13
2 3 BHK 92.81 14 14
3 3 BHK 91.77 14 14
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
15 Godrej Central P 30/09/2020 1 1 0 14 1 0 39
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3 BHK 91.84 13 13
2 1 BHK 33.59 1 1
3 3 BHK 91.84 14 14
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
16 Godrej Central Q 30/09/2020 1 1 0 14 1 0 39
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3 BHK 91.67 14 14
2 3 BHK 91.87 14 14
3 3 BHK 91.15 13 13
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
17 Godrej Central R 30/09/2020 1 1 0 14 1 0 35
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3 BHK 91.84 14 14
2 2.5 BHK 82.45 13 13
3 3 BHK 91.73 14 14
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
18 Godrej Central MHADA BUILDING NO 2 1 1 0 16 1 3 7
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 34.18 64 64
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
19 Godrej Central MHADA BUILDING NO 23 1 1 0 14 1 2 7
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 34.65 41 41
2 1 BHK 36.74 13 13
3 1 BHK 43.22 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
20 Godrej Central MHADA BUILDING NO 37 1 1 0 13 1 2 5
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1 BHK 33.38 52 52
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
FANM Property Services Pvt Ltd A52000000045 Real Estate Agent
SYNERGY INFRACON A51900000176 Real Estate Agent
ICICI Home Finance Company Limited A51800000727 Real Estate Agent
HDFC Realty Limited A51900000107 Real Estate Agent
ANMOL BALAJI BROKING A51800000364 Real Estate Agent
ASHISH KUMAR JHA A51800000901 Real Estate Agent
360 REALTORS LLP A51900000246 Real Estate Agent
Nitesh Jaikishan Changani A51900000918 Real Estate Agent
Mumbai Property Exchange Pvt Ltd A51900000211 Real Estate Agent
Nikhil Lalit Parekh A51900000040 Real Estate Agent
PROPERTYPISTOL REALTY PRIVATE LIMITED A51700000043 Real Estate Agent
RAMESH GUJJA A51800000610 Real Estate Agent
Rioga Premium Real Estate Advisory LLP A51800000974 Real Estate Agent
P G Patki Architects NA Architect
Advance Brickstone Construction Pvt. Ltd NA Contractor
Capacite Infraprojects Ltd NA Contractor
A M Decorators NA Contractor
Gold Finger Est Pvt. Ltd NA Contractor
Azure Systems Pvt. Ltd NA Contractor
Schindler India Pvt. Ltd NA Contractor
Klaus Multiparking Systems Pvt. Ltd NA Contractor
RGB texteriors LLP NA Contractor
Yogesh Enterprises NA Contractor
M S Hydro solutions Pvt. Ltd NA Contractor
Safetreat Engineers & Contractors Pvt. Ltd NA Contractor
Hatim Glazing & Cladding Pvt. Ltd NA Contractor
Pooja Architectural Systems Pvt. Ltd NA Contractor
M/S Raje Structural Consultants Private Limited NA Engineer
Pankaj Dharkar and Associates NA Other Professional
GEM Engserv NA Other Professional
Godrej Project development Pvt Ltd NA Other Professional
Aakar Architects & Consultants NA Architect
Fortune Financial Services(India)Limited A51900004280 Real Estate Agent
BDL Estate and Property A51900002831 Real Estate Agent
Dream Homes Realty A51700000406 Real Estate Agent
Amit M Gala A51900000588 Real Estate Agent
TERRAA PROPEX PRIVATE LIMITED A51900000455 Real Estate Agent
RAJANI PROPERTY CONSULTANTS A51900001345 Real Estate Agent
New Project Deals A51900003045 Real Estate Agent
OK Sir E-Commerce Pvt. Ltd. A51900000943 Real Estate Agent
PROPERTY ADDRESS A51900006765 Real Estate Agent
ANJANEYA SPACES LLP A51900006346 Real Estate Agent
PANKAJ SHIVKUMAR DEMBLA A51900003761 Real Estate Agent
GLOBAL GROUP A52000006598 Real Estate Agent
Asset India Realty A51700003799 Real Estate Agent
SUMED SHIVAJI JADHAV A51700001185 Real Estate Agent
VINOD DATTATREAY POL A51700006099 Real Estate Agent
Gaurav Kishorkant Vajaria A51700001595 Real Estate Agent
SUNDAR JAGANNATH BANAVALIKAR A51700000591 Real Estate Agent
DEEPU J SHETTY A51700001868 Real Estate Agent
BARCODE REALTY A51700006225 Real Estate Agent
MS PROPERTY SOLUTION A51700009898 Real Estate Agent
DT REALTORS A51700008479 Real Estate Agent

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
Godrej Central High Court 11078 Civil Yes Writ Petition NA 2016 Next hearing is on Nineteenth July Two Thousand Seventeen

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
3 Copy of the legal title report
4 Copy of the legal title report
5 Copy of the legal title report
6 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
4 Copy of Layout Approval (in case of layout)
5 Copy of Layout Approval (in case of layout)
6 Copy of Layout Approval (in case of layout)
7 Copy of Layout Approval (in case of layout)
8 Copy of Layout Approval (in case of layout)
9 Copy of Layout Approval (in case of layout)
10 Copy of Layout Approval (in case of layout)
11 Copy of Layout Approval (in case of layout)
12 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
7 Building Plan Approval (IOD)
8 Building Plan Approval (IOD)
9 Building Plan Approval (IOD)
10 Building Plan Approval (IOD)
11 Building Plan Approval (IOD)
12 Building Plan Approval (IOD)
13 Building Plan Approval (IOD)
14 Building Plan Approval (IOD)
15 Building Plan Approval (IOD)
16 Building Plan Approval (IOD)
17 Building Plan Approval (IOD)
18 Building Plan Approval (IOD)
19 Building Plan Approval (IOD)
20 Building Plan Approval (IOD)
21 Building Plan Approval (IOD)
22 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
5 Commencement Certificates / NA Order for plotted development
6 Commencement Certificates / NA Order for plotted development
7 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
2 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
4 Proforma of Allotment letter
5 Proforma of Allotment letter
6 Proforma of Allotment letter
7 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
4 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
5 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
6 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
7 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
8 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
9 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
2 Status of Formation of Legal Entity (Society/Co Op etc.)
3 Status of Formation of Legal Entity (Society/Co Op etc.)
4 Status of Formation of Legal Entity (Society/Co Op etc.)
5 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC006000000043992 Mrs. Renu Mohta View Orders
2 CC006000000043993 Mrs. Meenakshi Mohta View Orders
3 CC006000000043992 Mr. Asheesh Mohta View Orders
4 CC006000000043993 Mr. Anurag Mohta View Orders
5 CC006000000054576 SANJAY SHAMRAO HIRE View Orders
6 CC006000000056249 Anita Castellino View Orders
7 CC006000000056998 MRS. PRACHI SANDESH KOTWAL AND MR. SANDESH ANIL KOTWAL View Orders
8 CC006000000079338 Kanchan Kanti Chandra View Orders
9 CC006000000089654 Geetha Narayan View Orders
10 CC006000000192640 Ruchi Agarwal View Orders
11 CC006000000192676 Jayesh Ashok Shah View Orders
12 CC006000000193732 Anisha Bhandari and Seema Bhandari View Orders
13 CC006000000193869 Mrs Punam Nitin Nikam View Orders
14 CC006000000193881 1) Mrs Kala Tikle and 2) Ms Aditi Bhivandker alias Mrs Aditi Maurya View Orders