MahaRERA Application

General Information

Other Than Individual

Organization

R A ASSOCIATES
Partnership
NA
Do you have any Past Experience ?
No

Address Details

113-A
MITTAL TOWER
BARRISTER RAJNI PATEL MARG
NARIMAN POINT
OPP. VIDHAN BHAVAN
MAHARASHTRA
Konkan
Mumbai City
Ward ABCD
ABCD-400021
400021

Organization Contact Details

02266325076

Past Experience Details

Member Information

Member Name Designation Photo
SUSHIL RAJENDRA KOTHARI Authorized Signatory View Photo
RAJENDRA KHEMCHAND KOTHARI Partner View Photo
ASHOK KHEMCHAND KOTHARI Partner View Photo
VINAY KHEMCHAND KOTHARI Partner View Photo
VIVEK KAMALCHAND KOTHARI Partner View Photo
VARUN ASHOK KOTHARI Partner View Photo
SUSHIL RAJENDRA KOTHARI Partner View Photo
CHANDRAPRAKASH SIROYA Partner View Photo

Project

RA RESIDENCES
On-Going Project
30/06/2018
30/06/2019
31/03/2025
No
Others
No
2/12
BY ADJOINING NTC LAND
BABASAHEB AMBEDKAR ROAD
BY ADJOINING C S NO 12 PART
NAIGOAN CROSS ROAD
MAHARASHTRA
Konkan
Mumbai City
Ward FNorth
FNorth-400014
400014
12751.44
3
3
0
3187.2

FSI Details

33772.40
0
33772.40

Bank Details

HDFC BANK LIMITED
HDFC0000001

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 492 202 72

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 Completed
Water Conservation, Rain water Harvesting : YES 90 IN PROGRESS
Energy management : YES 50 IN PROGRESS
Fire Protection And Fire Safety Requirements : YES 80 IN PROGRESS
Electrical Meter Room, Sub-Station, Receiving Station : YES 50 IN PROGRESS
CHILDREN PLAY AREA : YES 100 Completed
CLUB HOUSE : YES 100 Completed
FIRE CHUTE : YES 100 Completed
FITNESS CENTRE : YES 100 Completed
IBMS : YES 100 Completed
SWIMMING POOL : YES 100 Completed
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 90 IN PROGRESS
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 Completed
Storm Water Drains : YES 80 IN PROGRESS
Landscaping & Tree Planting : YES 80 IN PROGRESS
Street Lighting : YES 0 IN PROGRESS
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : YES 100 Completed

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 RA RESIDENCES RA RESIDENCES WING A 31/03/2021 0 1 4 49 2 0 209
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 STORE ROOM 15.82 1 1
2 3BHK 170.79 38 38
3 4BHK 200.63 31 31
4 DUPLEX 328.37 4 4
5 STORE ROOM 15.62 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

95
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 99.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 RA RESIDENCES RA BUSINESS PARK 30/11/2021 0 1 0 4 1 0 74
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 Shop 789.67 1 1
2 Shop 765.08 1 0
3 Shop 650.41 1 1
4 Shop 567.54 1 1
5 Office space 223.2 3 2
6 Office space 197.63 3 2
7 Office space 177.48 3 2
8 Office space 157.11 3 2
9 Office space 74.07 6 1
10 Office space 65.85 6 6
11 Office space 106.22 6 2
12 Office space 78.23 6 1
13 Office space 78.17 6 5
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 90
3 X number of Podiums 0
4 Stilt Floor 80
5 X number of Slabs of Super Structure 80
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 60
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 75
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

10
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 49.5
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 RA RESIDENCES RA RESIDENCES WING B 31/03/2021 0 1 4 49 2 0 209
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 4BHK 200.63 31 31
2 STORE ROOM 15.62 1 1
3 STORE ROOm 15.82 1 1
4 DUPLEX 328.37 4 4
5 3BHK 170.79 38 38
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

95
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 99.5

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
SKYLINE ARCHITECTS NA Architect
SPACE AGE CONSULTANTS NA Architect
STERLING ENGINEERING CONSULTANCY SERVICES PVT LTD NA Engineer
NARANG ENTERPRISES A51900009937 Real Estate Agent
RUCHI KISHORE NARANG A51900007019 Real Estate Agent
HDFC DEVELOPERS LIMITED A51900000930 Real Estate Agent
Biren Lukka NA Chartered Accountant

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC006000000197392 Laxmi Jain View Orders
2 CC006000000197392 Gaurav Jain View Orders
3 CC006000000303513 GU MERCHANDISE PVT LTD View Orders
4 CC006000000303514 SUVIRA PROPERTIES PVT LTD View Orders
5 CC006000000396253 Ashok Suresh Deshmukh View Orders
6 CC006000000397857 Gaurav Satyapal Jain View Orders
7 CC006000000197392 Laxmi Jain View Orders
8 CC006000000197392 Gaurav Jain View Orders