MahaRERA Application

General Information

Other Than Individual

Organization

Konark Builders
Partnership
NA
Do you have any Past Experience ?
No

Address Details

U-01
Konark Buisness Centre
Opp Renuka Mata Mandir
Keshavnagar
Keshavnagar
MAHARASHTRA
Pune
Pune
Haveli
Mundhawa
411036

Organization Contact Details

02026800100
www.kariabuilders.com

Past Experience Details

Member Information

Member Name Designation Photo
Jyoti Mahendra Karia Partner View Photo
Mahendra Chagpal Karia Authorized Signatory View Photo

Project

Konark Virtue
On-Going Project
30/06/2020
30/12/2022
30/06/2023
No
Residential
Yes
S.NO.41/12/13 A PART, 41/13 B PART, 41/13 C PART, 41/13 D PART
S No 41-14
Florida Estate and Tarabai Park
Part S No 41 H No-12-13A-13B-13C-13D
Florida Estate
MAHARASHTRA
Pune
Pune
Haveli
Mundhawa
kESHAVNAGAR
kESHAVNAGAR
411036
20152
4
4
0
1850.28

FSI Details

23535.31
0
23535.31

Bank Details

ICICI Bank
ICIC0000074

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Konark Virtue Mr. Mohan Bajaj Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Konark Virtue Mrs. Megha Phull Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Konark Virtue Mr. Tarun Sharma Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Konark Virtue Mrs. Sunanda Y Bhimale Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Konark Virtue Mr. Prasad Y Bhimale Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Konark Virtue Mr. Srinath Y Bhimale Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 94 0 95

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 70 PAVER FINISHED ROADS INTERNALLY
Water Conservation, Rain water Harvesting : YES 50 RAIN WATER HAREVSTING SYSTEM WILL BE PROVIDED
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 50 FIRE FIGHITNG SYSTEM WILL BE PROVIDED AS PER FIRE
Electrical Meter Room, Sub-Station, Receiving Station : YES 50 METER ROOM PROVIDED
Childrens Play Area : YES 50 In open space
Gymnasium : YES 50 With basic equipment
Swimming Pool : YES 70 In open space
Aggregate area of recreational Open Space : YES 50 1850.28 sq mtrs divided over 3 open spaces
Open Parking : YES 50 TOTAL 154 NO OF OPEN PARKS ARE PROVIDED
Water Supply : YES 50 PIPING SYSTEM LAID INTERNALLY TO RECEIVE WATER FRO
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 50 SEWAGE LINE SYSTEM LAID AROUND ALL BUILDINGS AND C
Storm Water Drains : YES 50 Natural Water Drainage pattern will be provided
Landscaping & Tree Planting : YES 50 WILL BE PROVIDED AS PER SANCTION DRAWING
Street Lighting : YES 10 STREET LIGHT AS PER EC DRAWING SUBMITTED
Community Buildings : YES 50 CLUB HOUSE IN OPEN SPACE
Treatment And Disposal Of Sewage And Sullage Water : YES 50 STP PROVIDED TO TREAT SEWAGE AND SULLAGE WATER
Solid Waste Management And Disposal : YES 50 ORGANIC WASTE CONVERTER FOR TREATING WET GARBAGE

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Konark Virtue Tower - 1 30/06/2020 0 1 0 18 1 40 18
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 42.89 1 1
2 1BHK 44.31 14 13
3 1BHK 43.89 4 4
4 1BHK 43.90 6 6
5 1BHK 43.92 4 4
6 1BHK 44.30 6 6
7 1BHK 44.32 4 4
8 1BHK 44.8 1 1
9 2BHK 73.56 1 1
10 1BHK 44.27 3 3
11 2BHK 71.51 1 1
12 2BHK 74.93 2 1
13 1BHK 44.01 1 1
14 1BHK 74.97 4 2
15 1BHK 39.73 7 5
16 2BHK 73.76 1 1
17 1BHK 43.65 2 2
18 1BHK 43.82 1 1
19 1BHK 55.78 1 1
20 1BHK 55.75 1 1
21 2BHK 74.21 1 1
22 2BHK 73.83 1 1
23 1BHK 39.72 7 6
24 1BHK 42.88 2 2
25 1BHK 43.88 1 1
26 1BHK 55.89 2 1
27 2BHK 74.75 1 1
28 1BHK 44.33 6 6
29 2BHK 73.52 6 4
30 2BHK 75.00 2 1
31 2BHK 73.71 11 11
32 2BHK 73.72 5 1
33 2BHK 74.7 1 0
34 1BHK 44.13 2 2
35 2BHK 73.23 1 1
36 2BHK 74.23 7 5
37 2BHK 72.19 2 1
38 2BHK 72.29 2 1
39 2BHK 74.24 11 11
40 2BHK 74.71 2 2
41 2BHK 73.98 6 5
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 60
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 57
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 15
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 40
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

30
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 21
11 Overall Percentage of Completion of the work done For the entire Building /Wing 52.3
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Konark Virtue Tower - 2 30/06/2020 0 1 0 18 1 53 24
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 45.73 2 2
2 1BHK 46.10 1 1
3 2BHK 74.46 2 2
4 2BHK 73.61 1 1
5 2BHK 74.28 3 3
6 2BHK 74.23 2 2
7 2BHK 74.04 2 2
8 1BHK 43.92 2 2
9 1BHK 43.93 2 2
10 2BHK 74.03 4 3
11 2BHK 74.06 1 1
12 1BHK 44.27 6 6
13 2BHK 74.26 1 1
14 2BHK 71.50 2 2
15 1BHK 42.90 1 1
16 2BHK 73.70 5 5
17 1BHK 43.95 1 1
18 1BHK 42.19 2 2
19 2BHK 74.11 2 2
20 2BHK 74.07 2 2
21 1BHK 43.89 5 5
22 1BHK 42.64 2 2
23 1BHK 44.29 1 1
24 1BHK 46.09 1 1
25 2BHK 73.63 1 1
26 1BHK 41.36 1 1
27 2BHK 74.24 5 5
28 1BHK 44.31 11 11
29 2BHK 73.71 12 11
30 2BHK 74.29 8 8
31 1BHK 42.88 2 2
32 1BHK 55.37 1 1
33 1BHK 55.38 1 1
34 2BHK 74.22 1 1
35 1BHK 42.68 1 1
36 1BHK 43.90 12 12
37 1BHK 43.91 5 5
38 1BHK 44.30 11 11
39 1BHK 55.9 1 1
40 1BHK 55.93 1 1
41 2BHK 71.51 5 5
42 2BHK 73.51 1 1
43 2BHK 73.57 4 3
44 1BHK 44.28 2 2
45 1BHK 42.49 1 1
46 2BHK 74.00 1 1
47 2BHK 73.56 2 2
48 2BHK 74.02 1 1
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 95
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 98
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 85
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 75
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

94
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 85
11 Overall Percentage of Completion of the work done For the entire Building /Wing 83.2
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 Konark Virtue Tower - 3 30/06/2020 0 1 0 12 1 35 16
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 55.74 2 2
2 2BHK 73.68 1 1
3 1BHK 44.27 3 3
4 2BHK 74.27 2 2
5 2BHK 74.29 4 3
6 2BHK 73.50 2 2
7 1BHK 42.88 1 1
8 2BHK 71.51 4 4
9 2BHK 71.5 1 1
10 1BHK 43.91 1 1
11 2BHK 73.59 1 1
12 2BHK 74.23 2 1
13 2BHK 74.28 3 3
14 2BHK 73.94 4 4
15 2BHK 73.52 4 4
16 2BHK 73.74 6 6
17 2BHK 74.24 3 3
18 1BHK 43.89 9 9
19 1BHK 44.31 10 10
20 1BHK 42.64 1 1
21 2BHK 73.73 4 4
22 1BHK 43.88 1 1
23 2BHK 73.70 5 5
24 1BHK 43.90 12 12
25 1BHK 44.30 10 10
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 97
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 85
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 93
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

93
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 85
11 Overall Percentage of Completion of the work done For the entire Building /Wing 85.3
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
4 Konark Virtue Tower - 4 30/06/2020 0 1 0 9 1 26 12
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 44.28 1 1
2 2BHK 74.02 1 1
3 2BHK 74.24 6 6
4 2BHK 74.28 1 1
5 1BHK 43.89 2 2
6 1BHK 44.31 19 18
7 1BHK 55.74 2 2
8 2BHK 74.23 4 3
9 1BHK 39.92 1 1
10 2BHK 73.52 5 5
11 2BHK 74.03 2 1
12 1BHK 43.92 6 6
13 2BHK 74.09 5 3
14 1BHK 39.72 7 5
15 2BHK 73.71 10 10
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 95
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 95
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 80
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 93
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

98
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 85
11 Overall Percentage of Completion of the work done For the entire Building /Wing 84.6

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
DGCON CONSULTING SERVICES PRIVATE LIMITED A52100002078 Real Estate Agent
NIKHIL HEMANT SHAH A52100001352 Real Estate Agent
HIREN SURESHBHAI SANGHANI A52100001649 Real Estate Agent
EMPIRE CONSTRUCTIONS NA Contractor
SQUARE YARDS CONSULTING PRIVATE LIMITED A51800000454 Real Estate Agent
HIREN NATVARLAL TRIVEDI A52100001413 Real Estate Agent
RENU SINGH A52100000118 Real Estate Agent
SAVLI HINGMIRE & ASSOCIATES NA Architect
JW CONSULTANTS LLP NA Engineer
MEP SYTEM SOLUTIONS PVT LTD. NA Other Professional
VIKAS & NILIMA BHOSEKAR, LANDSCAPE ARCHITECTS NA Other Professional
Moco Design Studio NA Other Professional
Kunal Viajy Chadha A52100000853 Real Estate Agent
HDFC Realty Limited A51900000107 Real Estate Agent
ANAROCK Property Consultants Pvt. Ltd. A51900000108 Real Estate Agent
JAIDEEP PATHAK A52100010212 Real Estate Agent
HIREN SURESHBHAI SANGHANI A52100001649 Real Estate Agent
WISTERIA REAL VISION PVT LTD A52100003089 Real Estate Agent
Mahesh Gopaldas Mali A52100007848 Real Estate Agent
Amit Jagdish Agrawal A52100009011 Real Estate Agent
ELARA MARKETING SERVICES PRIVATE LIMITED A51700000030 Real Estate Agent
SMS PROPERTIES AND CONSULTANT LLP A52100009687 Real Estate Agent
Avik Sarkar A52100003887 Real Estate Agent
NITIN SHANKAR KADDE A52100000577 Real Estate Agent
Anish Neema A52100003324 Real Estate Agent
Paresh Lachman Hardwani A52100000163 Real Estate Agent
PRAVIIN PRATAP PAWAR A52100010041 Real Estate Agent
JAIDEEP PATHAK A52100010212 Real Estate Agent
SHELTER TRADING & CONSULTANCY SERVICES PVT. LTD. A51900007095 Real Estate Agent
Vrinda Gonte NA Chartered Accountant
Dnyaneshwar Admane NA Engineer

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
2 Declaration in FORM B
3 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
4 Disclosure of sold/ booked inventory
5 Disclosure of sold/ booked inventory
6 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
3 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
2 Status of Formation of Legal Entity (Society/Co Op etc.)
3 Status of Formation of Legal Entity (Society/Co Op etc.)
4 Status of Formation of Legal Entity (Society/Co Op etc.)
5 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC005000000011106 Adv. Sandhya View Orders
2 CC005000000096143 SUHAS GAIKWAD View Orders