MahaRERA Application

General Information

Other Than Individual

Organization

CALYX MERLIN VENTURES LLP
Partnership
NA
Do you have any Past Experience ?
No

Address Details

5TH FLOOR
THE FORUM BUILDING
NEAR D MART
PUNE SATARA ROAD
ABOVE RANKA JWELLERS
MAHARASHTRA
Pune
Pune
Pune City
Pune (M Corp.)
411009

Organization Contact Details

08888850014
WWW.CALYXCORP.CO.IN

Past Experience Details

Member Information

Member Name Designation Photo
SHAM BHAGWANDAS LADDHA Partner View Photo
RADHA KISAN LADDHA Partner View Photo
KAMLESH BALDEV JHAWAR Partner View Photo
CALYX CONSTRUCTIONS LLP NA Authorized Signatory View Photo
SAKET MOHTA Partner View Photo
SUNIL CHAMPALAL SOMANI Partner View Photo

Project

Nikunj Navyangan
On-Going Project
31/10/2017
31/12/2017
No
Residential
Yes
Gat No. 109 Part
Road
Gat No 98
Part of land of Gat No 109
Gat No 108
MAHARASHTRA
Pune
Pune
Mulshi
Kasar Amboli
412108
9700
3
3
0
902

FSI Details

10614.92
0
10614.92

Bank Details

State Bank of India
SBIN0004726

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Nikunj Navyangan Bhimrao Maruti Dhumal Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Nikunj Navyangan Vitthal Vasant Hulavale Individual Area Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 52 52 95

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 100 AS PER LAYOUT
Water Conservation, Rain water Harvesting : YES 100 NA
Energy management : YES 100 NA
Fire Protection And Fire Safety Requirements : YES 100 NA
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 NA
Aggregate area of recreational Open Space : YES 100 NA
Open Parking : YES 100 VISITOR's PARKING PROVIDED
Water Supply : YES 100 WATER SUPPLY AVAILABLE THROUGH TANKER
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 AS PER CONSULTANT
Storm Water Drains : YES 100 AS PER CONSULTANT
Landscaping & Tree Planting : YES 100 AS PER CONSULTANT
Street Lighting : YES 0 NA
Community Buildings : YES 100 NA
Treatment And Disposal Of Sewage And Sullage Water : YES 100 NA
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Nikunj Navyangan Nikunj Bldg E 31/12/2017 0 1 0 13 1 0 23
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 1BHK 31.93 24 20
2 1BHK 33.89 12 11
3 1BHK 29.12 11 10
4 1BHK 30.59 24 24
5 2BHK 46.83 12 12
6 2BHK 48.28 12 10
7 2BHK 48.88 12 10
8 2BHK 49.99 12 11
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Nikunj Navyangan Nikunj Bldg F 31/12/2017 0 1 0 12 1 0 29
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 48.38 12 12
2 2BHK 50.44 10 10
3 2BHK 51.2 10 10
4 2BHK 51.23 12 12
5 2BHK 51.28 10 10
6 2BHK 51.67 9 9
7 2BHK 52.3 12 12
8 2BHK 55.08 12 12
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 Nikunj Navyangan Novelty Market 31/12/2017 0 1 0 3 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 SHOP 9.58 2 2
2 SHOP 9.76 4 4
3 SHOP 13.66 2 2
4 Office1 41.81 1 0
5 Office2 52.49 1 0
6 SHOP 16.63 10 6
7 SHOP 16.82 10 10
8 Shop 20.9 4 2
9 Shop 21.18 4 4
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 80

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Niwara Buildcon NA Contractor
Shivkrupa Enterprises NA Contractor
Sai Enterprises NA Contractor
Jai Ganesh Enterprises NA Contractor
Lingesh Chavan NA Contractor
Shree Sai Electricals NA Contractor
Samarth Enterprises NA Contractor
Vishnukrupa Enterprises NA Contractor
Atharva Enterprises NA Contractor
Pratik Painting Works NA Contractor
M/s: Saniya Aluminium & Glass Centre NA Contractor
JAY AREAM & ASSOCIATES NA Architect
SANJEEV MEHTA NA Architect
Sandeep Kulkarni NA Engineer
360 REALTORS LLP A51900000246 Real Estate Agent
HDFC DEVELOPERS LIMITED A51900000930 Real Estate Agent
SATTAR JAMAL SAYYAD A52100001107 Real Estate Agent
JONES LANG LASALLE RESIDENTIAL PRIVATE LIMITED A51900000108 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
2 Building Plan Approval (IOD)
3 Building Plan Approval (IOD)
4 Building Plan Approval (IOD)
5 Building Plan Approval (IOD)
6 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Certificates of Architect (Form 4)
2 Certificates of Architect (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
2 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement