Common areas And Facilities, Amenities |
Available |
Percent |
Details |
Internal Roads & Footpaths :
|
YES
|
57
|
To be done before completion of Whole Project
|
Internal Roads & Footpaths :
|
YES
|
0
|
To be done before completion of Whole Project
|
Internal Roads & Footpaths :
|
YES
|
0
|
To be done before completion of Whole Project
|
Water Conservation, Rain water Harvesting :
|
YES
|
67
|
To be done before completion of Whole Project
|
Water Conservation, Rain water Harvesting :
|
YES
|
93
|
To be done before completion of Whole Project
|
Energy management :
|
YES
|
0
|
To be done before completion of Whole Project
|
Energy management :
|
YES
|
40
|
To be done before completion of Whole Project
|
Fire Protection And Fire Safety
Requirements :
|
YES
|
90
|
To be done before completion of Whole Project
|
Electrical Meter Room, Sub-Station, Receiving Station :
|
YES
|
38
|
Electric Meter Room and Sub-station only
|
Electrical Meter Room, Sub-Station, Receiving Station :
|
YES
|
56
|
Electric Meter Room and Sub-station only
|
Electrical Meter Room, Sub-Station, Receiving Station :
|
YES
|
95
|
Electric Meter Room and Sub-station only
|
2 Nos of Common Basement :
|
YES
|
1
|
Common Develpoment as per AFS
|
2 Nos of Common Basement :
|
YES
|
66
|
Common Develpoment as per AFS
|
3 Nos of Common Podiums :
|
YES
|
0
|
Common Develpoment as per AFS
|
3 Nos of Common Podiums :
|
YES
|
63
|
Common Develpoment as per AFS
|
Club House, Fitness Centre, Swimming Pool and other Recreational Areas :
|
YES
|
0
|
Common development as per AFS
|
Club House, Fitness Centre, Swimming Pool and other Recreational Areas :
|
YES
|
70
|
Common development as per AFS
|
Aggregate area of recreational Open Space :
|
YES
|
0
|
5460 Sq.Mtr common RG as per AFS
|
Aggregate area of recreational Open Space :
|
YES
|
40
|
5460 Sq.Mtr common RG as per AFS
|
Open Parking :
|
YES
|
0
|
To be done before completion of Whole Project
|
Water Supply :
|
YES
|
0
|
Suppy from local authority
|
Water Supply :
|
YES
|
100
|
Suppy from local authority
|
Sewerage (Chamber, Lines, Septic Tank , STP) :
|
YES
|
81
|
STP only
|
Sewerage (Chamber, Lines, Septic Tank , STP) :
|
YES
|
96
|
STP only
|
Storm Water Drains :
|
YES
|
31
|
To be done before completion of Whole Project
|
Storm Water Drains :
|
YES
|
80
|
To be done before completion of Whole Project
|
Landscaping & Tree Planting :
|
YES
|
4
|
To be done before completion of Whole Project
|
Landscaping & Tree Planting :
|
YES
|
69
|
To be done before completion of Whole Project
|
Street Lighting :
|
YES
|
0
|
To be done before completion of Whole Project
|
Community Buildings :
|
NO
|
0
|
NA
|
Treatment And Disposal Of Sewage And Sullage Water :
|
YES
|
0
|
To be done before completion of Whole Project
|
Treatment And Disposal Of Sewage And Sullage Water :
|
YES
|
90
|
To be done before completion of Whole Project
|
Solid Waste Management And Disposal :
|
YES
|
100
|
To be done before completion of Whole Project
|
Solid Waste Management And Disposal :
|
YES
|
90
|