MahaRERA Application

General Information

Other Than Individual

Organization

Namla Developers Private Limited
Company
NA
Do you have any Past Experience ?
Yes

Address Details

6th Floor
Fortune Classic
15th Road
Khar (W)
Above Toyota showroom
MAHARASHTRA
Konkan
Mumbai Suburban
Andheri
Andheri
400052

Organization Contact Details

02226467878

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1FORTUNE MIGNASResidentialNA704.02Dr.A.Nair Road Agreepada Mumbai 4000117/18761302017-08-172017-08-17
2FORTUNE MIGNASResidentialNA704.02Dr A Nair Road Agreepada Mumbai 4000117 18761302017-08-172017-08-17
3FORTUNE MIGNASResidentialNA704.02Dr.A.Nair Road Agreepada Mumbai 4000117/18761302017-08-172017-08-17

Member Information

Member Name Designation Photo
Nisar Kazi Managing Director View Photo
AFZAL UMER FURNITUREWALA Managing Director View Photo
MITESH PATEL Managing Director View Photo

Project

FORTUNE MAKHDOOM
New Project
31/12/2027
No
Residential
No
Sr No Ward Plot/CTS/Survey Number File/Reference Number
1 G/North 740A CHE/CTY/2952/G/N/337(NEW)
740A
KASHINATH BUILDING
NEW MESTAPE ESTATE
OLD MESTAPE BUILDING
MAIN ROAD
MAHARASHTRA
Konkan
Mumbai City
Ward GNorth
GNorth-400028
VEER SAVARKAR MARG
MAHIM
400028
858.42
1
1
0
0

FSI Details

1525.11
1474.10
2999.21

Details of RERA Designated Separate Bank Account

UNION BANK OF INDIA
UBIN0544434

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
FORTUNE MAKHDOOM NAMLA DEVELOPERS PRIVATE LIMITED Company Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 32 18 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 0 AS PER ARCHITECT CERTIFICATE
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 0 AS PER ARCHITECT CERTIFICATE
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 AS PER ARCHITECT CERTIFICATE
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : YES 0 AS PER DETAILS
Water Supply : YES 0 AS PER ARCHITECT CERTIFICATE
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 AS PER ARCHITECT CERTIFICATE
Storm Water Drains : YES 0 AS PER ARCHITECT CERTIFICATE
Landscaping & Tree Planting : YES 0 AS PER ARCHITECT CERTIFICATE
Street Lighting : NO 0 NA
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : YES 0 AS PER ARCHITECT CERTIFICATE

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 FORTUNE MAKHDOOM FORTNE MAKHDOOM 31/12/2027 1 1 0 19 0 32 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 86.86 12 0
2 3BHK 93.09 12 0
3 4BHK 100.33 1 0
4 4BHK 104.21 1 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 80
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 30
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 0
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 0
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 0
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

0
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 0
11 Overall Percentage of Completion of the work done For the entire Building /Wing 21

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
AMAN & ASSOCIATES NA Architect
SHAH & SHAH NA Engineer
VC GANGWANI & CO NA Chartered Accountant

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 a Details of encumbrances concerned to Finance
2 a Details of encumbrances concerned to Finance
3 a Details of encumbrances concerned to Finance
1 b Details of encumbrances concerned to Legal
2 b Details of encumbrances concerned to Legal
3 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
4 Copy of Layout Approval (in case of layout)
5 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
3 Building Plan Approval / NA Order for plotted development
4 Building Plan Approval / NA Order for plotted development
5 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
8 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
7 Engineer’s Certificate on Cost Incurred on Project (Form 2)
8 Engineer’s Certificate on Cost Incurred on Project (Form 2)
9 Engineer’s Certificate on Cost Incurred on Project (Form 2)
10 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)
1 Proforma of Agreement for sale
1 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement
1 Other – Legal
1 Other – Finance
1 Other – Technical