MahaRERA Application

General Information

Other Than Individual

Organization

Moze Associates
Partnership
NA
Do you have any Past Experience ?
Yes

Address Details

Sr. No. 284
Moze Vasti
Porwal Road
Lohegaon
Lohegaon
MAHARASHTRA
Pune
Pune
Haveli
LOHGAON
411047

Organization Contact Details

08007040005
www.skyways.co.in

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1Skyways SerenoResidentialNA10000Sr No 297 Opp D Y Patil Knowledge City Lohegaon Pune 29732142018-12-312018-12-31

Member Information

Member Name Designation Photo
Mohanraj Namdeo Moze Partner View Photo
Nagunath Balasaheb Moze Partner View Photo
Santosh Nivruti Moze Partner View Photo
Haridas Baban Moze Partner View Photo
Navnath Bhagwan Moze Partner View Photo
Sahebrao Bhagwan Moze Partner View Photo
Ajay Namdeo Moze Partner View Photo
Vijay Namdeo Moze Partner View Photo
Satish Sudam Moze Partner View Photo
Adwait Suresh Mulay Partner View Photo
Vijay Namdeo Moze Authorized Signatory View Photo

Project

Skyways Esfera 1
New Project
30/10/2021
No
Others
Yes
Sr No 284
By Porwal Road
By remaining Land of Sr No 284
By property of Pride Builders
By property of Bhagwanta Devram Moze
MAHARASHTRA
Pune
Pune
Haveli
LOHGAON
Porwal Road
Lohegaon
411047
2182.86
1
1
0
0

FSI Details

2182.86
0
2182.86

Bank Details

State Bank of India
SBIN0004523

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Skyways Esfera 1 Moze Associates Partnership Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 22 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 To be done
Water Conservation, Rain water Harvesting : YES 0 To be done
Energy management : NO 0 NA
Fire Protection And Fire Safety Requirements : YES 0 To be done
Electrical Meter Room, Sub-Station, Receiving Station : YES 0 To be done
Aggregate area of recreational Open Space : NO 0 NA
Open Parking : NO 0 NA
Water Supply : YES 0 To be done
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 0 To be done
Storm Water Drains : YES 0 To be done
Landscaping & Tree Planting : YES 0 To be done
Street Lighting : YES 0 To be done
Community Buildings : YES 0 To be done
Treatment And Disposal Of Sewage And Sullage Water : YES 0 To be done
Solid Waste Management And Disposal : NO 0 NA

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Skyways Esfera 1 Amenity 30/04/2021 1 1 0 4 0 0 0
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 005 214.33 2 0
2 006 222.97 2 0
3 001 254.37 1 0
4 002 229.10 1 0
5 003 245.54 1 0
6 004 206.89 2 0
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 100
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Atit Shrikant Admulwar NA Architect
WISTERIA REAL VISION PVT LTD A52100003089 Real Estate Agent
YOGESH PANDURAANG RAJGURUU A52100019945 Real Estate Agent
Guru Contruction NA Contractor

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Architect’s Certificate on Completion of Project (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement