Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
1 |
Upper Thane Greenville A - E, E1, F - I
|
GREENVILLE A
|
30/09/2021
|
0
|
1
|
0
|
19
|
0 |
31 |
81 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
38.57 |
18 |
18 |
2 |
1BHK |
38.65 |
1 |
1 |
3 |
1BHK |
38.78 |
16 |
16 |
4 |
1BHK |
38.83 |
1 |
0 |
5 |
1BHK |
41.1 |
1 |
1 |
6 |
1BHK |
41.28 |
18 |
16 |
7 |
1BHK |
41.3 |
1 |
0 |
8 |
1BHK |
41.34 |
1 |
1 |
9 |
1BHK |
43.1 |
1 |
0 |
10 |
1BHK |
43.8 |
1 |
1 |
11 |
2BHK |
47.5 |
2 |
2 |
12 |
2BHK OPTIMA |
45.45 |
18 |
17 |
13 |
2BHK OPTIMA |
45.52 |
1 |
1 |
14 |
2 BHK ULTIMA |
51.87 |
36 |
35 |
15 |
2 BHK ULTIMA |
51.93 |
2 |
2 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
70
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
2 |
Upper Thane Greenville A - E, E1, F - I
|
GREENVILLE B
|
30/09/2021
|
0
|
1
|
0
|
19
|
0 |
31 |
81 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
43.80 |
1 |
0 |
2 |
1BHK |
38.83 |
1 |
1 |
3 |
1BHK |
41.34 |
1 |
1 |
4 |
2BHK |
47.50 |
2 |
1 |
5 |
2BHK ULTIMA |
51.93 |
2 |
2 |
6 |
1BHK |
38.78 |
18 |
18 |
7 |
1BHK |
38.65 |
1 |
1 |
8 |
1BHK |
41.28 |
16 |
14 |
9 |
1BHK |
38.57 |
18 |
18 |
10 |
1BHK |
41.10 |
1 |
1 |
11 |
2BHKULTIMA |
54.40 |
2 |
2 |
12 |
2BHKULTIMA |
51.87 |
34 |
31 |
13 |
2BHK OPTIMA |
45.52 |
1 |
0 |
14 |
2BHKOPTIMA |
45.45 |
18 |
16 |
15 |
1BHK |
41.3 |
1 |
1 |
16 |
1BHK |
43.10 |
1 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
70
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
3 |
Upper Thane Greenville A - E, E1, F - I
|
GREENVILLE C
|
30/09/2021
|
0
|
1
|
0
|
19
|
0 |
31 |
81 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHK OPTIMA |
45.52 |
1 |
1 |
2 |
1BHK |
38.83 |
1 |
1 |
3 |
1BHK |
41.30 |
2 |
1 |
4 |
1BHK |
41.34 |
1 |
0 |
5 |
1BHK |
38.65 |
1 |
1 |
6 |
2BHK ULTIMAWITHDECK |
55.29 |
36 |
36 |
7 |
1BHK |
38.78 |
16 |
13 |
8 |
1BHK |
41.1 |
1 |
1 |
9 |
1BHK |
43.80 |
1 |
1 |
10 |
2BHK |
47.50 |
2 |
2 |
11 |
1BHK |
38.57 |
18 |
18 |
12 |
1BHK |
41.28 |
17 |
14 |
13 |
1BHK |
43.10 |
1 |
0 |
14 |
2BHK OPTIMA |
45.45 |
18 |
16 |
15 |
2BHKULTIMADECK |
55.37 |
2 |
2 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
4 |
Upper Thane Greenville A - E, E1, F - I
|
GREENVILLE D
|
30/09/2021
|
0
|
1
|
0
|
19
|
0 |
31 |
81 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
41.34 |
1 |
0 |
2 |
1BHK |
43.10 |
1 |
0 |
3 |
1BHK |
38.65 |
1 |
0 |
4 |
1BHK |
38.83 |
1 |
0 |
5 |
1BHK |
43.80 |
1 |
0 |
6 |
1BHK |
38.57 |
18 |
17 |
7 |
1BHK |
41.10 |
1 |
1 |
8 |
1BHK |
41.30 |
1 |
1 |
9 |
2BHK |
47.5 |
2 |
01 |
10 |
1BHK |
38.78 |
18 |
16 |
11 |
1BHK |
41.28 |
16 |
12 |
12 |
2 BHK OPTIMA |
45.45 |
18 |
16 |
13 |
2 BHK OPTIMA |
45.52 |
1 |
0 |
14 |
2 BHK ULTIMA |
51.93 |
2 |
2 |
15 |
2 BHK ULTIMA |
54.4 |
2 |
0 |
16 |
2 BHK ULTIMA |
51.87 |
34 |
31 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
5 |
Upper Thane Greenville A - E, E1, F - I
|
GREENVILLE E
|
30/09/2021
|
0
|
1
|
0
|
19
|
0 |
31 |
81 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHK ULTIMAWITHDECK |
55.37 |
2 |
2 |
2 |
1BHK |
38.83 |
1 |
0 |
3 |
2BHK OPTIMA |
45.52 |
1 |
0 |
4 |
1BHK |
43.10 |
1 |
0 |
5 |
1BHK |
38.65 |
1 |
1 |
6 |
1BHK |
41.30 |
2 |
1 |
7 |
2BHK OPTIMA |
45.45 |
18 |
17 |
8 |
1BHK |
38.57 |
18 |
18 |
9 |
1BHK |
41.10 |
1 |
01 |
10 |
1BHK |
41.34 |
1 |
01 |
11 |
1BHK |
43.80 |
1 |
01 |
12 |
2BHKULTIMAWITHDECK |
55.29 |
36 |
36 |
13 |
1BHK |
38.78 |
16 |
16 |
14 |
1BHK |
41.28 |
17 |
14 |
15 |
2BHK |
47.50 |
2 |
2 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
6 |
Upper Thane Greenville A - E, E1, F - I
|
GREENVILLE E1
|
30/09/2021
|
0
|
1
|
0
|
19
|
0 |
31 |
81 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
41.34 |
1 |
0 |
2 |
1BHK |
43.80 |
1 |
0 |
3 |
2BHKULTIMA |
57.76 |
2 |
0 |
4 |
1BHK |
41.30 |
1 |
0 |
5 |
1BHK |
43.10 |
1 |
0 |
6 |
1BHK |
38.83 |
1 |
1 |
7 |
1BHK |
38.57 |
18 |
15 |
8 |
1BHK |
38.78 |
18 |
14 |
9 |
1BHK |
41.28 |
16 |
14 |
10 |
1BHK |
41.10 |
1 |
1 |
11 |
2BHK |
47.50 |
2 |
01 |
12 |
2BHKOPTIMA |
45.45 |
18 |
17 |
13 |
2BHK OPTIMA |
45.52 |
1 |
01 |
14 |
2BHKULTIMA |
51.87 |
34 |
32 |
15 |
2BHK ULTIMA |
51.93 |
2 |
01 |
16 |
1BHK |
38.65 |
1 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
7 |
Upper Thane Greenville A - E, E1, F - I
|
GREENVILLE F
|
30/09/2021
|
0
|
1
|
0
|
19
|
0 |
31 |
81 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
38.65 |
1 |
0 |
2 |
1BHK |
41.34 |
1 |
0 |
3 |
2BHK OPTIMA |
45.52 |
1 |
1 |
4 |
1BHK |
43.80 |
1 |
0 |
5 |
2BHKULTIMA |
57.76 |
2 |
0 |
6 |
1BHK |
38.83 |
1 |
1 |
7 |
1BHK |
38.57 |
18 |
18 |
8 |
1BHK |
41.28 |
16 |
10 |
9 |
1BHK |
41.10 |
1 |
01 |
10 |
1BHK |
41.30 |
1 |
01 |
11 |
2BHK OPTIMA |
45.45 |
18 |
18 |
12 |
2BHK ULTIMA |
51.87 |
34 |
31 |
13 |
2BHK ULTIMA |
51.93 |
2 |
2 |
14 |
1BHK |
43.10 |
1 |
1 |
15 |
1BHK |
38.78 |
18 |
17 |
16 |
2BHK |
47.50 |
2 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
8 |
Upper Thane Greenville A - E, E1, F - I
|
GREENVILLE G
|
30/09/2021
|
0
|
1
|
0
|
19
|
0 |
31 |
81 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
43.80 |
1 |
01 |
2 |
1BHK |
41.10 |
1 |
01 |
3 |
2BHK OPTIMA |
45.52 |
1 |
1 |
4 |
1BHK |
38.83 |
1 |
0 |
5 |
2BHKULTIMAWITHDECK |
55.29 |
36 |
36 |
6 |
2BHK OPTIMA |
45.45 |
18 |
17 |
7 |
1BHK |
41.34 |
1 |
1 |
8 |
1BHK |
41.30 |
2 |
1 |
9 |
1BHK |
43.10 |
1 |
0 |
10 |
1BHK |
38.65 |
1 |
1 |
11 |
1BHK |
41.28 |
17 |
16 |
12 |
1BHK |
38.57 |
18 |
18 |
13 |
1BHK |
38.78 |
16 |
13 |
14 |
2BHK ULTIMAWITHDECK |
55.37 |
2 |
2 |
15 |
2BHK |
47.5 |
2 |
1 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
9 |
Upper Thane Greenville A - E, E1, F - I
|
GREENVILLE H
|
30/09/2021
|
0
|
1
|
0
|
19
|
0 |
31 |
81 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHK OPTIMA |
45.52 |
1 |
0 |
2 |
2BHKULTIMA |
57.76 |
2 |
0 |
3 |
1BHK |
41.10 |
1 |
0 |
4 |
1BHK |
41.30 |
1 |
0 |
5 |
1BHK |
43.10 |
1 |
0 |
6 |
1BHK |
43.80 |
1 |
0 |
7 |
1BHK |
38.65 |
1 |
0 |
8 |
1BHK |
38.83 |
1 |
0 |
9 |
1BHK |
41.34 |
1 |
0 |
10 |
2BHK ULTIMA |
51.93 |
2 |
0 |
11 |
2BHKOPTIMA |
45.45 |
18 |
18 |
12 |
1BHK |
38.57 |
18 |
18 |
13 |
2BHK |
47.50 |
2 |
01 |
14 |
2BHKULTIMA |
51.87 |
34 |
31 |
15 |
1BHK |
38.78 |
18 |
17 |
16 |
1BHK |
41.28 |
16 |
9 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
80
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
10 |
Upper Thane Greenville A - E, E1, F - I
|
GREENVILLE I
|
30/09/2021
|
0
|
1
|
0
|
19
|
0 |
31 |
81 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
43.10 |
1 |
0 |
2 |
1BHK |
38.83 |
1 |
1 |
3 |
1BHK |
43.80 |
1 |
0 |
4 |
1BHK |
41.10 |
1 |
0 |
5 |
1BHK |
38.65 |
1 |
0 |
6 |
2BHK ULTIMAWITHDECK |
55.37 |
2 |
2 |
7 |
2BHK OPTIMA |
45.45 |
18 |
17 |
8 |
1BHK |
41.30 |
2 |
02 |
9 |
1BHK |
41.28 |
17 |
16 |
10 |
1BHK |
41.34 |
1 |
1 |
11 |
2BHK OPTIMA |
45.52 |
1 |
1 |
12 |
1BHK |
38.78 |
16 |
15 |
13 |
1BHK |
38.57 |
18 |
18 |
14 |
2BHK |
47.50 |
2 |
2 |
15 |
2BHK ULTIMA WITHDECK |
55.29 |
36 |
35 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
0
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
0
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
70
|
|