General Information

Other Than Individual

Organization

KONBIL LANDMARKS LLP
Partnership
NA
Do you have any Past Experience ?
No

Address Details

Plot No. 5
Mulberry Garden
Magarpatta city
Hadapsar
Near Laxmi Lawn
MAHARASHTRA
Pune
Pune
Haveli
Hadapsar
411013

Organization Contact Details

02025889733

Past Experience Details

Member Information

Member Name Designation Photo
Rajesh Mamidwar Authorized Signatory View Photo

Project

KONIFER
New Project
31/07/2023
31/12/2023
No
Others
Yes
Survey No 89A Hissa No 11D
By part of Survey No 90
By part of Survey No 89A-10
By part of Survey No 89A-11D
By part of Survey No 89A-11E
MAHARASHTRA
Pune
Pune
Haveli
Mundhawa
Mundhawa
Pune
411036
2050
1
1
0
201.33

FSI Details

5016
0
5016.00

Bank Details

BANK OF MAHARASHTRA
MAHB0000114

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
KONIFER konbil landmarks llp Individual Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B
Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
KONIFER konbil landmarks Individual Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 60 0 0

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 0 As per Agreement
Water Conservation, Rain water Harvesting : YES 0 As per Agreement
Energy management : YES 0 As per Agreement
Fire Protection And Fire Safety Requirements : YES 0 As per Agreement
Electrical Meter Room, Sub-Station, Receiving Station : YES 1 As per Agreement
Aggregate area of recreational Open Space : YES 0 As per Agreement
Open Parking : NO 0 NA
Water Supply : YES 50 As per Agreement
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 15 As per Agreement
Storm Water Drains : YES 0 As per Agreement
Landscaping & Tree Planting : YES 20 As per Agreement
Street Lighting : YES 0 As per Agreement
Community Buildings : NO 0 NA
Treatment And Disposal Of Sewage And Sullage Water : NO 0 NA
Solid Waste Management And Disposal : YES 0 As Per Agreement

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 KONIFER KONIFER 31/07/2022 0 1 0 11 0 19 28
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 61.16 11 11
2 2BHK 62.75 11 10
3 2BHK 63.56 11 11
4 Shop 21.28 1 0
5 Shop 24.07 1 1
6 Shop 31.41 1 0
7 Shop 67.16 3 0
8 Shop 79.27 4 0
9 1BHK 35.83 10 10
10 2BHK 49.98 11 7
11 2BHK 61.07 11 11
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 85
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 85
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

85
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 50
11 Overall Percentage of Completion of the work done For the entire Building /Wing 70.5

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Space Designers Studio NA Architect
Ahuja Valecha Associates LLP NA Chartered Accountant
G A BHILARE NA Contractor
Nikhil Gourshettiwar NA Engineer

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
2 Copy of Layout Approval (in case of layout)
3 Copy of Layout Approval (in case of layout)
4 Copy of Layout Approval (in case of layout)
5 Copy of Layout Approval (in case of layout)
6 Copy of Layout Approval (in case of layout)
7 Copy of Layout Approval (in case of layout)
8 Copy of Layout Approval (in case of layout)
1 Building Plan Approval / NA Order for plotted development
2 Building Plan Approval / NA Order for plotted development
3 Building Plan Approval / NA Order for plotted development
4 Building Plan Approval / NA Order for plotted development
5 Building Plan Approval / NA Order for plotted development
6 Building Plan Approval / NA Order for plotted development
1 Commencement Certificates / NA Order for plotted development
2 Commencement Certificates / NA Order for plotted development
3 Commencement Certificates / NA Order for plotted development
4 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
2 Declaration in FORM B
1 Architect’s Certificate of Percentage of Completion of Work (Form 1)
2 Architect’s Certificate of Percentage of Completion of Work (Form 1)
3 Architect’s Certificate of Percentage of Completion of Work (Form 1)
4 Architect’s Certificate of Percentage of Completion of Work (Form 1)
5 Architect’s Certificate of Percentage of Completion of Work (Form 1)
6 Architect’s Certificate of Percentage of Completion of Work (Form 1)
7 Architect’s Certificate of Percentage of Completion of Work (Form 1)
8 Architect’s Certificate of Percentage of Completion of Work (Form 1)
1 Engineer’s Certificate on Cost Incurred on Project (Form 2)
2 Engineer’s Certificate on Cost Incurred on Project (Form 2)
3 Engineer’s Certificate on Cost Incurred on Project (Form 2)
4 Engineer’s Certificate on Cost Incurred on Project (Form 2)
5 Engineer’s Certificate on Cost Incurred on Project (Form 2)
6 Engineer’s Certificate on Cost Incurred on Project (Form 2)
7 Engineer’s Certificate on Cost Incurred on Project (Form 2)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)
1 CERSAI details
1 Disclosure of sold/ booked inventory
2 Disclosure of sold/ booked inventory
3 Disclosure of sold/ booked inventory
1 Disclosure of Interest in Other Real Estate Organizations
1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
3 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement