MahaRERA Application

General Information

Other Than Individual

Organization

Guardian Promoters & Developers Private Limited
Company
NA
Do you have any Past Experience ?
Yes

Address Details

101, 102
Chintamani Pride
Paschima Nagari Road
Kothrud
Near City Pride Multiplex
MAHARASHTRA
Pune
Pune
Haveli
Kothrud
411038

Organization Contact Details

02066413737
www.guardiandevelopers.in

Past Experience Details

Sr.No.
Project Name
Type of Project
Others
Land Area(In Sq mtrs)
Address
CTS Number
Number of Buildings/Plot
Number of Apartments
Original Proposed Date of Completion
Actual Date of Completion
1AadityaResidentialNA746Shriram Society Warje Pune-411052S No 126/2b/1 Plot No 431122014-03-312014-06-19
2KanchangauriResidentialNA1077.09Kanchan Lane Near Krishna Dining Hall Law college Road Pune-411004Plot No 86/31192014-04-092014-11-14
3GaurishankarResidentialNA522.5Mayur Colony Kothrud Pune-411038CTS No 755 Plot No 46 S No 14/129P/130/1311102014-03-312014-05-27

Member Information

Member Name Designation Photo
Manish Murlidhar Sabade Managing Director View Photo
Manish Madhav Soman Director View Photo

Project

Guardian Eastern Meadows - Phase 1
On-Going Project
31/12/2018
30/06/2021
30/06/2023
No
Residential
Yes
Plot A, Gat No. 1344/1/1 and 1344/1/2,
18 Mrts Proposed Lay out Road
By Road and Boundary of Kharadi wagholi Village
Part of land bearing GAT No 1344-1-1 and 1344-1-2
Part of land bearing GAT No 1344-3
MAHARASHTRA
Pune
Pune
Haveli
WAGHOLI
Grant Road
Off Nagar Road
412207
15484
5
5
0
3100

FSI Details

21272
100
21372.00

Bank Details

HDFC Bank Ltd
HDFC0000007

Promoter(Land Owner/ Investor) Details

Project Name Promoter Name Promoter(Land Owner/ Investor) Type Type of Agreement/ Arrangement VIEW
Guardian Eastern Meadows - Phase 1 Yashwant Sakhare & Usha Sakhare Individual Revenue Share View Details
Sr No. Document Name View
1 Upload Agreement / MoU Copy
2 Declaration in Form B

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 338 284 50

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : YES 90 Proposed
Water Conservation, Rain water Harvesting : YES 100 Proposed
Energy management : YES 75 Proposed
Fire Protection And Fire Safety Requirements : YES 75 Proposed
Electrical Meter Room, Sub-Station, Receiving Station : YES 100 Proposed
Aggregate area of recreational Open Space : YES 100 Proposed
Open Parking : NO 0 NA
Water Supply : YES 100 Proposed
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 100 Proposed
Storm Water Drains : YES 100 Proposed
Landscaping & Tree Planting : YES 75 Proposed
Street Lighting : YES 75 Proposed
Community Buildings : YES 0 Proposed
Treatment And Disposal Of Sewage And Sullage Water : YES 100 Proposed
Solid Waste Management And Disposal : YES 100 Proposed

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 Guardian Eastern Meadows - Phase 1 A1 31/12/2020 0 1 0 13 0 0 34
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 3BHK 69.36 1 1
2 3BHK 71.41 5 5
3 3BHK 76.44 5 5
4 3BHK 75.36 1 1
5 3BHK 71.09 12 12
6 2BHK 50.11 5 5
7 2BHK 53.38 1 1
8 2BHK 55.15 5 5
9 2BHK 55.39 12 12
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 83
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 85
11 Overall Percentage of Completion of the work done For the entire Building /Wing 76.8
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
2 Guardian Eastern Meadows - Phase 1 B1 31/12/2020 0 1 0 13 0 0 42
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 53.36 11 10
2 2BHK 53.45 11 10
3 2BHK 53.52 1 1
4 2BHK 49.80 2 2
5 2BHK 51.06 1 1
6 2BHK 53.61 1 1
7 2BHK 53.96 11 10
8 2BHK 52.59 11 8
9 2BHK 50.90 11 10
10 2BHK 49.52 34 33
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 0
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 97
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 91
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 85
11 Overall Percentage of Completion of the work done For the entire Building /Wing 77.3
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
3 Guardian Eastern Meadows - Phase 1 C1 31/12/2020 0 1 1 12 0 0 96
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 52.73 22 22
2 2BHK 50.29 10 8
3 2BHK 51.08 10 10
4 2BHK 55.85 22 22
5 2BHK 57.53 22 22
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 92
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 85
11 Overall Percentage of Completion of the work done For the entire Building /Wing 87.7
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
4 Guardian Eastern Meadows - Phase 1 B4 31/12/2020 0 1 2 13 0 0 54
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 51.05 1 1
2 2BHK 53.51 1 1
3 2BHK 49.67 2 2
4 2BHK 52.49 12 11
5 2BHK 53.36 11 10
6 2BHK 53.96 11 11
7 2BHK 55.55 11 10
8 2BHK 50.90 11 11
9 2BHK 49.52 22 17
10 2BHK 53.45 12 12
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 97
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 100
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 85
11 Overall Percentage of Completion of the work done For the entire Building /Wing 88.2
Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
5 Guardian Eastern Meadows - Phase 1 A8 31/12/2020 0 1 2 13 0 0 52
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 53.38 1 1
2 2BHK 55.39 10 10
3 2BHK 50.11 6 6
4 2BHK 55.15 6 6
5 3BHK 71.09 12 12
6 3BHK 76.44 6 6
7 3BHK 71.41 6 5
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 0
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 100
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 98
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

96
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 85
11 Overall Percentage of Completion of the work done For the entire Building /Wing 87.9

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
HDFC DEVELOPERS LIMITED A51900000930 Real Estate Agent
NADIRSHAH NOORDDIN AJANEY A52100000784 Real Estate Agent
ELARA MARKETING SERVICES PRIVATE LIMITED A51700000030 Real Estate Agent
PROPERTY CHEF CONSULTING SERVICES A52100000044 Real Estate Agent
JONES LANG LASALLE RESIDENTIAL PRIVATE LIMITED A51900000108 Real Estate Agent
Jatin Kacha A52100000900 Real Estate Agent
Vikas Achalkar NA Architect
Spectrum Consultants NA Engineer
360 REALTORS LLP A51900000246 Real Estate Agent
SUNJOTH CHANDRAKANT LONDHE A52100008666 Real Estate Agent
SQUARE YARDS CONSULTING PRIVATE LIMITED A51800000454 Real Estate Agent

Litigations Details

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
3 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
2 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Form 2A
2 Form 2A
3 Form 2A
4 Form 2A
5 Form 2A
6 Form 2A
7 Form 2A
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other – Legal
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement

Complaint Details

Sr.No. Complaint No Complainant Name
1 CC005000000022738 Sunil Sasidharan Pillai View Orders
2 CC005000000022745 Madhuri Gupta View Orders
3 CC005000000022823 Deepanshu Chopra View Orders
4 CC005000000023117 Sainath Kotgire View Orders
5 CC005000000023198 DEVENDER SINGH GARHA View Orders