MahaRERA Application

General Information

Other Than Individual

Organization

METRO DEVELOPMENT
Partnership
NA
Do you have any Past Experience ?
No

Address Details

301/302
THE AMBIENCE COURT
Plot No-2
Sector-19D
Vashi RTO
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
400703

Organization Contact Details

02227839017
www.metrogroupindia.com

Past Experience Details

Member Information

Member Name Designation Photo
HITESH SURESH JAIN Partner View Photo
SURESH CHAMPALAL JAIN Partner View Photo
MANOJ LAXMILAL KOTHARI Partner View Photo
KISHORE LADHARAM MANGE Partner View Photo

Project

THE PALMS
On-Going Project
31/12/2018
31/03/2019
Yes
Residential
No
Plot No- 14
Plot No-17
11 m wide road
Reserve Plot
11 m wide road
MAHARASHTRA
Konkan
Thane
Thane
Navi Mumbai (M Corp.)
Sector-50
Nerul
400706
3680.00
1
1
0
0

FSI Details

5514.29
0
5514.29

Bank Details

HDFC Bank
HDFC0000540

Project Details

Name Proposed Booked WorkDone(In %)
Number of Garages ( In Numbers) 0 0 0
Covered Parking ( In Numbers) 159 95 75

Development Work

Common areas And Facilities, Amenities Available Percent Details
Internal Roads & Footpaths : NO 0 NA
Water Conservation, Rain water Harvesting : YES 90 In later scope of work
Energy management : NO 0 In later scope of work
Fire Protection And Fire Safety Requirements : YES 90 In progress
Electrical Meter Room, Sub-Station, Receiving Station : YES 60 In Progress
SWIMMING POOL : YES 20 Civil work completed
Aggregate area of recreational Open Space : NO 0 Civil work completed
Open Parking : YES 0 In progress
Water Supply : YES 50 In Progress
Sewerage (Chamber, Lines, Septic Tank , STP) : YES 90 Chamber line work in progress
Storm Water Drains : YES 100 S.T/STP not required
Landscaping & Tree Planting : YES 50 Completed
Street Lighting : NO 0 IIn progress
Community Buildings : NO 0 In Progress
Treatment And Disposal Of Sewage And Sullage Water : YES 0 NA
Solid Waste Management And Disposal : NO 0 In later scope of work

Building Details

Sr.No. Project Name Name (Also mention identification of building/wing/other as per approved plan) Proposed Date of Completion Number of Basement's Number of Plinth Number of Podium's Number of Sanctioned Floors Number of Stilts Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler) Number of Closed Parking
1 THE PALMS THE PALMS 31/03/2019 1 1 1 14 1 13 159
Sr.No. Apartment Type Carpet Area (in Sqmts) Number of Apartment Number of Booked Apartment
1 2BHK 44.98 1 1
2 2BHK 46.36 1 1
3 2BHK 46.37 1 1
4 2BHK 46.65 2 2
5 2BHK 48.45 18 18
6 2BHK 48.81 10 10
7 3BHK 69.01 1 1
8 3BHK 69.35 1 1
9 3BHK 71.40 18 18
10 3BHK 72.13 1 1
11 3BHK 72.40 1 1
12 3BHK 73.20 2 2
13 3BHK 74.08 9 9
14 3BHK 74.62 9 9
15 3BHK 76.29 1 1
16 3BHK 79.36 1 1
17 5BHK & more 144.66 2 2
Sr.No. Tasks / Activity Percentage of Work
1 Excavation 100
2 X number of Basement(s) and Plinth 100
3 X number of Podiums 100
4 Stilt Floor 100
5 X number of Slabs of Super Structure 100
6 Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises 95
7 Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises 25
8 Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. 100
9

The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing

100
10 Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate 87
11 Overall Percentage of Completion of the work done For the entire Building /Wing 90.7

Project Professional Information

Professional Name MahaRERA Certificate No. Professional Type
Wheel Buildwell NA Contractor
Amit N .Patil Architects NA Architect
Structural Concept Designs Pvt. Ltd NA Engineer
ANIL VERMA & ASSOCIATES NA Other Professional
AJAY NARSINGH AGRAWAL A51700001666 Real Estate Agent
Rajnandan kumar Jaiswal A51700000071 Real Estate Agent
Jeetu Ashwanikumar Hira A51700001318 Real Estate Agent
DEEPAK HIRABHAI JAGASIA A51800004133 Real Estate Agent
SAHARA REALITY A51700009169 Real Estate Agent
Kunal Premji Vira A51700005215 Real Estate Agent
Dinesh Dhiraj Jain A51700011139 Real Estate Agent
BIPIN ASHWANI KUMAR HIRA A51700007660 Real Estate Agent
BIPIN ASHWANI KUMAR HIRA A51700007660 Real Estate Agent
SUDESH AMRITLAL ARORA A51700014094 Real Estate Agent
BEST DEAL REAL ESTATE CONSULTANT A51700006907 Real Estate Agent
SANJIV KUMAR SHAH A51700012081 Real Estate Agent
Haresh Gurnomal Rochani A51700000412 Real Estate Agent
Khataumal Chelaram Maghnani A51700012990 Real Estate Agent
Adheep Jaydeep Bakshi A51800016968 Real Estate Agent
Haresh Gurnomal Rochani A51700000412 Real Estate Agent
DC SEJPAL & CO NA Other Professional

Litigations Details

Project Name Court Name Case Number Case Type Preventive/Injunction/Interim Order is Passed? Petition Name Other Petition Details Year Present Status Documents
THE PALMS BOMBAY HIGH COURT 26 Others No Suit NA 2007 Direction
NA
THE PALMS JOINT CIVIL JUDGE SENIOR DIVISON THANE 118 Civil No Suit NA 2008 Evidence
NA
THE PALMS JCJSD THANE 610 Civil No Suit NA 2009 Written Statement
NA

Uploaded Documents

Document Name Uploaded Document
1 Copy of the legal title report
2 Copy of the legal title report
1 Details of encumbrances
2 Details of encumbrances
3 Details of encumbrances
1 b Details of encumbrances concerned to Legal
1 Copy of Layout Approval (in case of layout)
1 Building Plan Approval (IOD)
1 Commencement Certificates / NA Order for plotted development
1 Declaration about Commencement Certificate
1 Declaration in FORM B
1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)
1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)
1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)
1 Disclosure of sold/ booked inventory
1 CERSAI details
1 Disclosure of Interest in Other Real Estate Organizations
1 Certificates of CA (Form 5)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)
1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)
1 Proforma of Agreement for sale
1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)
1 Proforma of Allotment letter
2 Proforma of Allotment letter
3 Proforma of Allotment letter
4 Proforma of Allotment letter
1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted development
1 Certificates of Architect (Form 4)
1 Status of Formation of Legal Entity (Society/Co Op etc.)
1 Status of Conveyance
1 Other
2 Other
1 Other – Finance
1 Other – Technical
1 Foreclosure of the Project
1 Deviation Report with respect to Allotment letter
1 Deviation Report with respect to model copy of Agreement