Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
1 |
The Trees, Residential Phase 1
|
A
|
30/06/2021
|
2
|
1
|
0
|
7
|
1 |
6 |
28 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
SHOP |
18.40 |
1 |
0 |
2 |
SHOP |
18.56 |
1 |
0 |
3 |
SHOP |
18.76 |
1 |
0 |
4 |
SHOP |
20.79 |
1 |
0 |
5 |
1BHK |
43.60 |
6 |
6 |
6 |
3BHKCOMPACT |
78.07 |
1 |
1 |
7 |
1BHK |
44.12 |
20 |
20 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
90
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
2 |
The Trees, Residential Phase 1
|
B
|
30/06/2021
|
2
|
1
|
0
|
7
|
1 |
6 |
28 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
SHOP |
16.68 |
1 |
0 |
2 |
1BHK |
44.66 |
14 |
14 |
3 |
1BHK |
43.60 |
6 |
6 |
4 |
1BHK |
43.71 |
6 |
6 |
5 |
3BHKCOMPACT |
77.97 |
1 |
1 |
6 |
SHOP |
11.56 |
1 |
0 |
7 |
SHOP |
14.40 |
1 |
0 |
8 |
SHOP |
15.26 |
1 |
0 |
9 |
SHOP |
16.28 |
1 |
0 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
90
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
3 |
The Trees, Residential Phase 1
|
C
|
30/06/2021
|
2
|
2
|
0
|
7
|
1 |
6 |
28 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
43.07 |
6 |
6 |
2 |
1BHK |
43.57 |
6 |
6 |
3 |
3BHKCOMPACT |
76.92 |
1 |
1 |
4 |
SHOP |
11.56 |
1 |
0 |
5 |
SHOP |
17.80 |
1 |
0 |
6 |
SHOP |
21.45 |
1 |
0 |
7 |
SHOP |
22.93 |
1 |
0 |
8 |
1BHK |
44.67 |
14 |
13 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
90
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
4 |
The Trees, Residential Phase 1
|
D
|
30/06/2021
|
2
|
1
|
0
|
7
|
1 |
6 |
26 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
44.61 |
7 |
6 |
2 |
1BHK |
44.03 |
19 |
17 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
90
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
5 |
The Trees, Residential Phase 1
|
E
|
30/06/2021
|
2
|
1
|
0
|
18
|
1 |
19 |
83 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
PENTHOUSE |
207.26 |
1 |
1 |
2 |
SHOP |
14.75 |
1 |
0 |
3 |
SHOP |
17.30 |
1 |
0 |
4 |
SHOP |
18.82 |
1 |
0 |
5 |
SHOP |
21.59 |
1 |
0 |
6 |
1BHK |
48.27 |
1 |
1 |
7 |
2BHK |
65.40 |
13 |
13 |
8 |
3BHKCOMPACT |
81.98 |
16 |
16 |
9 |
PENTHOUSE |
209.09 |
1 |
1 |
10 |
3BHKCOMPACT |
79.66 |
15 |
14 |
11 |
2BHKCOMPACT |
60.68 |
1 |
1 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
90
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
6 |
The Trees, Residential Phase 1
|
F
|
30/06/2021
|
2
|
1
|
0
|
18
|
1 |
20 |
87 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHK |
65.47 |
14 |
14 |
2 |
2BHK |
75.72 |
1 |
1 |
3 |
3BHKCOMPACT |
81.31 |
1 |
1 |
4 |
3BHK |
94.61 |
14 |
14 |
5 |
4BHKCOMPACTDUPLEX |
138.02 |
1 |
1 |
6 |
PENTHOUSE |
193.32 |
1 |
1 |
7 |
PENTHOUSE |
202.39 |
1 |
1 |
8 |
3BHK |
97.53 |
16 |
16 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
90
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
7 |
The Trees, Residential Phase 1
|
G
|
30/06/2021
|
2
|
1
|
0
|
12
|
1 |
8 |
35 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
46.50 |
11 |
11 |
2 |
1BHK |
47.82 |
11 |
11 |
3 |
1BHK |
52.07 |
1 |
1 |
4 |
2BHK |
60.98 |
1 |
1 |
5 |
2BHK |
64.31 |
11 |
11 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
90
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
8 |
The Trees, Residential Phase 1
|
H
|
30/06/2021
|
2
|
1
|
0
|
12
|
0 |
10 |
47 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
50.92 |
1 |
1 |
2 |
1BHK |
48.84 |
1 |
1 |
3 |
2BHK |
64.96 |
12 |
12 |
4 |
2BHK |
65.95 |
11 |
11 |
5 |
2BHK |
75.79 |
11 |
11 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
90
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
9 |
The Trees, Residential Phase 1
|
I
|
30/06/2021
|
2
|
1
|
0
|
18
|
1 |
23 |
99 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
1BHK |
48.45 |
1 |
1 |
2 |
2BHK |
77.50 |
1 |
1 |
3 |
3BHK |
96.52 |
15 |
15 |
4 |
3BHK |
98.56 |
16 |
16 |
5 |
PENTHOUSE |
199.04 |
1 |
1 |
6 |
PENTHOUSE |
205.97 |
1 |
1 |
7 |
2BHK |
67.18 |
14 |
14 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
90
|
|
Sr.No. |
Project Name
|
Name (Also mention identification of building/wing/other as per approved plan)
|
Proposed Date of Completion
|
Number of Basement's
|
Number of Plinth
|
Number of Podium's
|
Number of Sanctioned Floors
|
Number of Stilts
|
Total no. of open Parking as per Sanctioned Plan (4-wheeler+2-Wheeler)
|
Number of Closed Parking
|
10 |
The Trees, Residential Phase 1
|
J
|
30/06/2021
|
2
|
1
|
0
|
18
|
1 |
20 |
90 |
|
|
Sr.No.
|
Apartment Type
|
Carpet Area (in Sqmts)
|
Number of Apartment
|
Number of Booked Apartment
|
1 |
2BHK |
66.07 |
17 |
17 |
2 |
4BHKCOMPACT |
120.00 |
15 |
15 |
3 |
5BHKCOMPACT |
144.34 |
1 |
1 |
4 |
PENTHOUSE |
208.16 |
1 |
1 |
5 |
PENTHOUSE |
212.81 |
1 |
1 |
6 |
3BHKCOMPACT |
92.62 |
1 |
1 |
7 |
4BHKCOMPACT |
122.17 |
14 |
14 |
|
|
|
|
|
Sr.No.
|
Tasks / Activity
|
Percentage of Work
|
1
|
Excavation
|
100
|
2
|
X number of Basement(s) and Plinth
|
100
|
3
|
X number of Podiums
|
0
|
4
|
Stilt Floor
|
100
|
5
|
X number of Slabs of Super
Structure
|
100
|
6
|
Internal walls, Internal Plaster,
Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
|
100
|
7
|
Sanitary Fittings within the
Flat/Premises,Electrical Fittings within the Flat/Premises
|
100
|
8
|
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
|
100
|
9
|
The external plumbing and external plaster,
elevation, completion of terraces with waterproofing of the Building/Wing
|
100
|
10
|
Installation of lifts, water pumps, Fire
Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common
Areas, electro, mechanical equipment, Compliance to conditions of environment
/CRZ NOC,
Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to
Building/Wing, Compound Wall and all other requirements as may be required to
Obtain Occupation /Completion Certificate
|
100
|
11 |
Overall Percentage of Completion of the
work done For the entire Building /Wing
|
90
|
|